DESIGN MANAGEMENT · INFORMATION CONTROL
Document Control
Monitor information intake, QA, workflow movement, approval, response efficiency and design-information performance from the project's connected CDE.
Update frequencyHourly-ready
Primary CDEOracle Aconex
Latest source record28 Aug, 06:49
Design IntelligencePattern detection activePredictive learning model not yet enabled
Docs Received71000 controlled deliverables
QA Checked771.4% passed intake QA
QA Rejected228.6% rejection rate
In Workflow22 overdue
Approved A+B344A 168 · B 176
Status C10Current rejected design position
Pending Review1172 active workflows
Open RFIs1515 overdue
QA Rejection Patterns
Structured intake errors by category
Current Review Load
Active workflow steps by reviewer
Unanswered / Open RFIs
Information requests that can block document approval
RFI-006Curtain wall bracket tolerance confirmationIn Progress
RFI-007Smoke seal interface at door headsOpen
RFI-008Riser sleeve setting outAnswered
RFI-010Façade access restraint zone99d overdue
RFI-011Door hardware finish confirmationAnswered
RFI-012Curtain wall drainage route87d overdue
RFI-014Fire stopping tested detailAnswered
RFI-015Architectural ceiling zone coordination74d overdue
Requires Management Attention
Evidence-backed intelligence observations
Critical
RFI · Programme-critical unanswered informationMultiple active RFIs with programme impact remain unanswered beyond their response due dates.
High
RFI · Response bottleneck requires interventionAt least one recipient organisation has multiple overdue unanswered RFIs and repeated reminder burden.
Watch
RFI · Coordination demand is recurringCoordination/interface questions form a recurring share of the RFI workload and indicate opportunities for earlier multidisciplinary coordination.
High
Workflow bottleneck emergingA current fire-review workflow has exceeded its review due date and is holding the latest design position in Pending.