YAZU DESIGN MANAGEMENT REPORT
Executive Design Report
YAZU-001 · Yazu Design Demo Project · Yazu Group
Deliverables approved154/100015% complete
Overdue controls6074 actions · 11 RFIs
High risks46 open risks/issues
Compliance concerns22/6 submissions compliant
Programme pressure38 slipped · 7 critical
Change exposure41 approval · 1 not implemented
Management Attention
Highest-priority live interventions
1
Confirm coordinated builder's work openingsAction · Overdue · MEP Design Lead · due 27 Aug 2026
→2Resolve FAC-001Action · Overdue · Pm-Nadeem · due 07 Sept 2026
→3Steel interface delayRisk · Exposure 20/25 · Sarah Mitchell
→4The MEP trades are running late-the design need o concludeIssue · Exposure 20/25 · MEP Lead
→5RFI-001 · Curtain wall slab-edge interface dimensionsRFI · Overdue · response due 27 Aug 2026
→6RFI-006 · Curtain wall bracket tolerance confirmationRFI · Overdue · response due 17 Jun 2026
→7RFI-012 · Curtain wall drainage routeRFI · Overdue · response due 31 Jul 2026
→8RFI-002 · Façade fire barrier interface evidenceRFI · Overdue · response due 24 Aug 2026
→9DC-002 · Façade fire barrier interface revisionDesign Change · Approval required
→10PRG-STR-010 · Slab edge setting out approvalProgramme · -1d float · 80% complete
→Executive Position
Current control balance
Open actions4
Active RFIs11
Active changes4
Open reviews1
Blocked samples2
Cost exposure£1,850
Change delay8 days
Negative float3
Package Health
Derived from live delivery, risk, compliance and programme signals
| Package | Health | Deliverables | Overdue | Actions | Risks | Programme |
|---|---|---|---|---|---|---|
| ARCArchitectural | At Risk | 0/7 | 3 | 2 | 1 | 1 |
| FACFaçade | At Risk | 152/983 | 591 | 2 | 4 | 5 |
| INTInternal Fit-Out | Healthy | 0/0 | 0 | 0 | 0 | 0 |
| MEPMEP | At Risk | 0/5 | 1 | 0 | 1 | 0 |
| ROFRoofing & Waterproofing | Healthy | 0/0 | 0 | 0 | 0 | 0 |
| STRStructure | At Risk | 2/5 | 0 | 0 | 0 | 1 |
| VTRVertical Transportation | Healthy | 0/0 | 0 | 0 | 0 | 0 |