Y
YAZU Design
YAZU-001/Yazu Design Demo ProjectOperational Framework
Public demo
DESIGN PROGRAMME

Programme

Connect design dates, logic and control pressure so slippage is understood before it reaches construction.

Public demoSign in to edit
Active activities8Not started, in progress or on hold
Critical7Active critical activities
Slipped vs baseline8Current finish later than baseline
Negative float3Immediate recovery attention
Due in 14 days0Near-term design commitments
INTEGRATED TIMELINE

Baseline vs current

18 Aug 2026 → 16 Sept 2026
⌕
10 of 10 activitiesRead-only programme
PackageBaseline finishStatusControls
PRG-DES-001Design coordination freeze—Project-level21 Aug 202624 Aug 2026+3d
100%
0dCompleteCritical
0A0R0RFI0DC
PRG-MEP-010Plantroom builderwork coordination closureMEPMEP26 Aug 202625 Aug 2026-1d
100%
4dComplete
1A1R1RFI0DC
PRG-STR-010Slab edge setting out approvalSTRStructure25 Aug 202628 Aug 2026+3d
80%
-1dIn ProgressCritical
0A0R0RFI0DC
PRG-FAC-010Curtain wall typical bay coordinated designFACFaçade28 Aug 202631 Aug 2026+3d
65%
0dIn ProgressCritical
1A1R2RFI1DC
PRG-FAC-020Façade fire barrier interface closureFACFaçade27 Aug 202603 Sept 2026+7d
40%
-5dIn ProgressCritical
0A0R1RFI1DC
PRG-FAC-030Curtain wall technical submission approvalFACFaçade01 Sept 202604 Sept 2026+3d
50%
-3dIn ProgressCritical
1A0R0RFI1DC
PRG-ARC-010Door schedule and closer coordinationARCArchitectural02 Sept 202604 Sept 2026+2d
55%
2dIn Progress
0A0R1RFI1DC
PRG-FAC-040Curtain wall visual mock-up sign-offFACFaçade04 Sept 202608 Sept 2026+4d
0%
0dNot StartedCritical
0A0R0RFI0DC
PRG-MIL-001Design Release Gate 1Primavera P6 · P6-DES-1000—Project-level05 Sept 202609 Sept 2026+4d
0%
0dNot StartedCritical
0A0R0RFI0DC
PRG-MIL-002Façade construction releasePrimavera P6 · P6-FAC-1200FACFaçade12 Sept 202616 Sept 2026+4d
0%
0dNot StartedCritical
0A0R0RFI0DC