DESIGN PROGRAMME
Programme
Connect design dates, logic and control pressure so slippage is understood before it reaches construction.
Public demoSign in to edit
Active activities8Not started, in progress or on hold
Critical7Active critical activities
Slipped vs baseline8Current finish later than baseline
Negative float3Immediate recovery attention
Due in 14 days0Near-term design commitments
INTEGRATED TIMELINE
18 Aug 2026 → 16 Sept 2026Baseline vs current
| Package | Baseline finish | Status | Controls | |||||
|---|---|---|---|---|---|---|---|---|
| PRG-DES-001Design coordination freeze | —Project-level | 21 Aug 2026 | 24 Aug 2026 | +3d | 100% | 0d | CompleteCritical | 0A0R0RFI0DC |
| PRG-MEP-010Plantroom builderwork coordination closure | MEPMEP | 26 Aug 2026 | 25 Aug 2026 | -1d | 100% | 4d | Complete | 1A1R1RFI0DC |
| PRG-STR-010Slab edge setting out approval | STRStructure | 25 Aug 2026 | 28 Aug 2026 | +3d | 80% | -1d | In ProgressCritical | 0A0R0RFI0DC |
| PRG-FAC-010Curtain wall typical bay coordinated design | FACFaçade | 28 Aug 2026 | 31 Aug 2026 | +3d | 65% | 0d | In ProgressCritical | 1A1R2RFI1DC |
| PRG-FAC-020Façade fire barrier interface closure | FACFaçade | 27 Aug 2026 | 03 Sept 2026 | +7d | 40% | -5d | In ProgressCritical | 0A0R1RFI1DC |
| PRG-FAC-030Curtain wall technical submission approval | FACFaçade | 01 Sept 2026 | 04 Sept 2026 | +3d | 50% | -3d | In ProgressCritical | 1A0R0RFI1DC |
| PRG-ARC-010Door schedule and closer coordination | ARCArchitectural | 02 Sept 2026 | 04 Sept 2026 | +2d | 55% | 2d | In Progress | 0A0R1RFI1DC |
| PRG-FAC-040Curtain wall visual mock-up sign-off | FACFaçade | 04 Sept 2026 | 08 Sept 2026 | +4d | 0% | 0d | Not StartedCritical | 0A0R0RFI0DC |
| PRG-MIL-001Design Release Gate 1Primavera P6 · P6-DES-1000 | —Project-level | 05 Sept 2026 | 09 Sept 2026 | +4d | 0% | 0d | Not StartedCritical | 0A0R0RFI0DC |
| PRG-MIL-002Façade construction releasePrimavera P6 · P6-FAC-1200 | FACFaçade | 12 Sept 2026 | 16 Sept 2026 | +4d | 0% | 0d | Not StartedCritical | 0A0R0RFI0DC |