Total RFIs2011 active
Overdue & Unanswered911 active >14 days
Average Response7.8dP90 12.7d
On-time Response54.5%11 official responses
Impact Flagged10Programme / cost / change
Awaiting Close-out7Answered but not formally closed
Reminder Burden10Automated / recorded reminders
AI Classification100%77% avg confidence

Overdue & Unanswered RFIs by Date

Historical response backlog in the selected scope

02579Aug 26Sept 26Oct 26

Overdue RFIs by Issued To Organisation

Current response accountability

Lead Designer
3
Specialist Consultant
2
Façade Consultant
1
Design Team
1
Client Design Team
1
Structural Consultant
1

Management Exceptions

Oldest overdue unanswered RFIs — with Issued By, Issued To and current Ball in Court.

RFISubjectIssued ByIssued ToBall in CourtResponse DueDays OverdueImpact
RFI-010Façade access restraint zoneFaçade ContractorFaçade ContractorSpecialist ConsultantFaçade Access ConsultantSpecialist Consultant19 Jul 202698dP Δ
RFI-012Curtain wall drainage routeFaçade ContractorFaçade ContractorFaçade ConsultantFaçade ConsultantFaçade Consultant31 Jul 202686dP C Δ
RFI-015Architectural ceiling zone coordinationMEP ContractorMEP ContractorLead DesignerArchitectLead Designer13 Aug 202673dP Δ
RFI-002Façade fire barrier interface evidenceMain ContractorDesign ManagerDesign TeamFire Engineer / Façade ConsultantDesign Team24 Aug 202662dP Δ
RFI-019Client signage requirementsLead DesignerArchitectClient Design TeamClient Design ManagerClient Design Team27 Aug 202659dΔ
RFI-001Curtain wall slab-edge interface dimensionsMain ContractorFaçade Design ManagerStructural ConsultantStructural EngineerStructural Consultant27 Aug 202659dP Δ
RFI-020Parapet waterproofing terminationFaçade ContractorFaçade ContractorLead DesignerArchitectLead Designer30 Aug 202656dP Δ
RFI-004Door closer specification versus proposed productMain ContractorArchitectural Design ManagerLead DesignerArchitectLead Designer01 Sept 202654dC Δ