DESIGN MANAGEMENT · INFORMATION CONTROL
RFI Control
Manage information demand, accountability, response performance, impacts and closure — with CDE integration, automation and design intelligence.
Public demoOracle AconexConnected
Total RFIs2011 active
Overdue & Unanswered911 active >14 days
Average Response7.8dP90 12.7d
On-time Response54.5%11 official responses
Impact Flagged10Programme / cost / change
Awaiting Close-out7Answered but not formally closed
Reminder Burden10Automated / recorded reminders
AI Classification100%77% avg confidence
Overdue & Unanswered RFIs by Date
Historical response backlog in the selected scope
Overdue RFIs by Issued To Organisation
Current response accountability
Management Exceptions
Oldest overdue unanswered RFIs — with Issued By, Issued To and current Ball in Court.
| RFI | Subject | Issued By | Issued To | Ball in Court | Response Due | Days Overdue | Impact |
|---|---|---|---|---|---|---|---|
| RFI-010 | Façade access restraint zone | Façade ContractorFaçade Contractor | Specialist ConsultantFaçade Access Consultant | Specialist Consultant | 19 Jul 2026 | 98d | P Δ |
| RFI-012 | Curtain wall drainage route | Façade ContractorFaçade Contractor | Façade ConsultantFaçade Consultant | Façade Consultant | 31 Jul 2026 | 86d | P C Δ |
| RFI-015 | Architectural ceiling zone coordination | MEP ContractorMEP Contractor | Lead DesignerArchitect | Lead Designer | 13 Aug 2026 | 73d | P Δ |
| RFI-002 | Façade fire barrier interface evidence | Main ContractorDesign Manager | Design TeamFire Engineer / Façade Consultant | Design Team | 24 Aug 2026 | 62d | P Δ |
| RFI-019 | Client signage requirements | Lead DesignerArchitect | Client Design TeamClient Design Manager | Client Design Team | 27 Aug 2026 | 59d | Δ |
| RFI-001 | Curtain wall slab-edge interface dimensions | Main ContractorFaçade Design Manager | Structural ConsultantStructural Engineer | Structural Consultant | 27 Aug 2026 | 59d | P Δ |
| RFI-020 | Parapet waterproofing termination | Façade ContractorFaçade Contractor | Lead DesignerArchitect | Lead Designer | 30 Aug 2026 | 56d | P Δ |
| RFI-004 | Door closer specification versus proposed product | Main ContractorArchitectural Design Manager | Lead DesignerArchitect | Lead Designer | 01 Sept 2026 | 54d | C Δ |
| RFI-005 | Façade access loads at parapet restraint zones | Main ContractorFaçade Design Manager | Specialist ConsultantFaçade Access Consultant | Specialist Consultant | 02 Sept 2026 | 53d | P Δ |