DDS + CDE + PROGRAMME
Design Deliverables
Control stakeholder DDS commitments, design production, source-platform workflow and approval performance from one register.
Total DDS Deliverables35662927 issued · 639 forecast / outstanding
Deliverables PerformanceDocument Type and Originator are controlled by the main page filters / table selections. No duplicate dropdowns are shown here.
Originator Performance
When an originator is selected, only that originator remains in this table and the register below.
| Originator | Total | Planned | Actual | A | B | C | Pending | Overdue |
|---|---|---|---|---|---|---|---|---|
| WHL - William Hare Limited (WHL) | 2541 | 2541 | 2522 | 1749 (142) | 282 (23) | 81 | 112 | 19 |
| FKG - FK Group (FKG) | 978 | 967 | 371 | 135 (17) | 144 (12) | 7 | 49 | 596 |
| Facade Systems Ltd | 25 | 25 | 17 | 0 | 0 | 0 | 0 | 8 |
| Architect | 7 | 7 | 6 | 1 (1) | 3 (3) | 2 | 0 | 1 |
| MEP Consultant | 5 | 5 | 4 | 2 (2) | 2 (1) | 0 | 0 | 1 |
| Structural Engineer | 5 | 5 | 5 | 3 (1) | 1 | 0 | 1 | 0 |
| Façade Contractor | 3 | 3 | 1 | 1 | 0 | 0 | 0 | 2 |
| Façade Consultant | 2 | 2 | 1 | 0 | 0 | 0 | 0 | 1 |
| Total | 3566 | 3555 | 2927 | 1891 (163) | 432 (39) | 90 | 162 | 628 |
Deliverable Type Status
When a type is selected, only that type remains in this table and the register below.
| Deliverable Type | Total | Planned | Forecast | Actual | A | B | C | Pending | Overdue |
|---|---|---|---|---|---|---|---|---|---|
| DR - Drawing (DR) | 2466 | 2455 | 2455 | 1840 | 1129 (153) | 391 (29) | 82 | 124 | 615 |
| CA - Calculations (CA) | 813 | 813 | 813 | 813 | 707 (6) | 22 (2) | 0 | 26 | 0 |
| RP - Report (RP) | 106 | 106 | 106 | 106 | 4 | 0 | 0 | 2 | 0 |
| TS - Technical Submittals (TS) | 42 | 42 | 42 | 42 | 22 | 8 (2) | 3 | 8 | 0 |
| DN - Design Note (DN) | 32 | 32 | 32 | 32 | 0 | 0 | 0 | 0 | 0 |
| TW - Temporary Works (TW) | 27 | 27 | 27 | 27 | 16 | 1 | 0 | 1 | 0 |
| Unclassified | 25 | 25 | 25 | 17 | 0 | 0 | 0 | 0 | 8 |
| drawing | 11 | 11 | 11 | 9 | 4 (3) | 3 (2) | 1 | 0 | 2 |
| SS - Sample Submittal (SS) | 10 | 10 | 10 | 10 | 6 | 1 | 3 | 0 | 0 |
| PR - Programme (PR) | 6 | 6 | 6 | 6 | 0 | 0 | 0 | 0 | 0 |
| RG - Register (RG) | 6 | 6 | 6 | 6 | 0 | 1 | 0 | 0 | 0 |
| IP - Inspection and Test Plan (IP) | 4 | 4 | 4 | 4 | 0 | 0 | 0 | 0 | 0 |
| report | 4 | 4 | 4 | 2 | 2 (1) | 0 | 0 | 0 | 2 |
| schedule | 4 | 4 | 4 | 3 | 0 | 2 (1) | 1 | 0 | 1 |
| calculation | 2 | 2 | 2 | 2 | 1 | 0 | 0 | 1 | 0 |
| DS - Design Statement (DS) | 2 | 2 | 2 | 2 | 0 | 2 (2) | 0 | 0 | 0 |
| GU - Guide (GU) | 2 | 2 | 2 | 2 | 0 | 0 | 0 | 0 | 0 |
| SK - Sketch Drawing (SK) | 2 | 2 | 2 | 2 | 0 | 0 | 0 | 0 | 0 |
| IM - Information Management (IM) | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 0 | 0 |
| specification | 1 | 1 | 1 | 1 | 0 | 1 (1) | 0 | 0 | 0 |
| Total | 3566 | 3555 | 3555 | 2927 | 1891 (163) | 432 (39) | 90 | 162 | 628 |
Full-Scope Deliverables — Cumulative
Curve buttons now act as the legend. Projection uses the most recent 4-week issue and approval rates.
3566Total scope
Projected issue completionInsufficient recent progress0.0 docs/week · 639 remaining
Projected approval completionInsufficient recent progress0.0 docs/week · 1243 remaining
2323/2575A+B approved
Reporting cut-off: 25 Oct 2026. Projection: rolling 4-week current rate, not a contractual forecast. Prepublished: planned only. Pending: Awaiting Design Review only. A/B carry-forward: a previous A or B remains effective while a later revision is under review; C does not carry forward.
Package DDS Control
Every package remains visible. DDS files are expected through the configured document-control platform, reviewed by the Tier 1 Design Manager and consolidated only after acceptance.
Primary CDEOracle AconexConnected source · manual Excel retained as fallback
| Package | DDS Owner / Organisation | Planned | Anticipated | CDE Received | Revision | Status | CDE Source | Consolidated | |
|---|---|---|---|---|---|---|---|---|---|
| ARC · ArchitecturalDesign Lead | Lead ArchitectDesign Lead | 18 Aug 2026 | 18 Aug 20260d | 18 Aug 2026Simulated Oracle Aconex | DDS-03 | Under Review | TRN-3764F1ARC_DDS_DDS-03.xlsx | 3deliverables | |
| FAC · FaçadeFaçade Lead | Façade ConsultantFaçade Lead | 20 Aug 2026 | 22 Aug 2026+2d | 22 Aug 2026Simulated Oracle Aconex | DDS-04 | Accepted | TRN-C8BA33FAC_DDS_DDS-04.xlsx | 5deliverables | |
| INT · Internal Fit-OutEmma Clarke | Project Design Team— | — | — | — | — | Not configured | —No DDS received | 0deliverables | |
| MEP · MEPMEP Lead | MEP ConsultantMEP Lead | 25 Aug 2026 | 29 Aug 2026+4d | —Awaiting Oracle Aconex | — | DDS OverdueAwaiting Dds | ManualSynced DDS | 0deliverables | |
| ROF · Roofing & WaterproofingDaniel Wright | Project Design Team— | — | — | — | — | Not configured | —No DDS received | 0deliverables | |
| STR · StructureStructural Lead | Structural EngineerStructural Lead | 24 Aug 2026 | 26 Aug 2026+2d | 26 Aug 2026Simulated Oracle Aconex | DDS-02 | Accepted | TRN-9463FDSTR_DDS_DDS-02.xlsx | 0deliverables | |
| VTR · Vertical TransportationYousuf Nadeem | Project Design Team— | — | — | — | — | Not configured | —No DDS received | 0deliverables |