TECHNICAL ASSURANCE
Technical Submissions
Control product and system submissions against project requirements, review outcomes, deviations and supporting evidence.
Public demoSign in to edit
Active4In review or response cycle
Overdue4Review response overdue
Deviations2Declared or identified
Compliance concerns1Non-compliant / evidence gaps
Accepted2Accepted / accepted with comments
| Package | Deviation | Sample | ||||||
|---|---|---|---|---|---|---|---|---|
| TS-FAC-003Rev P03 | Insulated Glass Unit Technical DataMaterial | FAC | Façade SubcontractorArchitectural Glass Ltd | 21 Aug 2026 | Accepted | Compliant | — | SMP-FAC-003 |
| TS-ARC-001Rev P01 | Overhead Door Closer Technical SubmissionProduct | ARC | Door SubcontractorDoor Controls Ltd | 23 Aug 2026 | Accepted With Comments | Compliant With Deviation | Deviation | SMP-ARC-004 |
| TS-FAC-002Rev P02 | Façade Cavity Barrier and Fire Stop SystemSystem | FAC | Façade SubcontractorFire Barrier Systems UK | 25 Aug 2026Overdue | Overdue | Insufficient Evidence | Deviation | — |
| TS-FAC-001Rev P01 | Curtain Walling System Technical SubmissionSystem | FAC | Façade SubcontractorCurtain Wall Systems Ltd | 29 Aug 2026Overdue | Overdue | Not Checked | — | SMP-FAC-001 |
| TS-STR-001Rev P01 | Intumescent Coating Product SubmissionProduct | STR | Fire Protection SubcontractorProtective Coatings Ltd | 30 Aug 2026Overdue | Overdue | Not Checked | — | SMP-STR-002 |
| TS-MEP-001Rev P01 | Cable Containment System DataMaterial | MEP | Electrical SubcontractorContainment Systems Ltd | 31 Aug 2026Overdue | Overdue | Not Checked | — | — |