DESIGN INFORMATION PERFORMANCE
Design Deliverables
Monitor the full DDS scope, CDE issue and approval performance. Prepublished records remain planning placeholders until formally issued.
Total DDS Deliverables35662927 issued · 639 forecast / outstanding
Deliverables PerformanceDocument Type and Originator are controlled by the main page filters / table selections. No duplicate dropdowns are shown here.
Originator Performance
When an originator is selected, only that originator remains in this table and the register below.
| Originator | Total | Planned | Actual | A | B | C | Pending | Overdue |
|---|---|---|---|---|---|---|---|---|
| WHL - William Hare Limited (WHL) | 2541 | 2541 | 2522 | 1749 (142) | 282 (23) | 81 | 112 | 19 |
| FKG - FK Group (FKG) | 978 | 967 | 371 | 135 (17) | 144 (12) | 7 | 49 | 596 |
| Facade Systems Ltd | 25 | 25 | 17 | 0 | 0 | 0 | 0 | 8 |
| Architect | 7 | 7 | 6 | 1 (1) | 3 (3) | 2 | 0 | 1 |
| MEP Consultant | 5 | 5 | 4 | 2 (2) | 2 (1) | 0 | 0 | 1 |
| Structural Engineer | 5 | 5 | 5 | 3 (1) | 1 | 0 | 1 | 0 |
| Façade Contractor | 3 | 3 | 1 | 1 | 0 | 0 | 0 | 2 |
| Façade Consultant | 2 | 2 | 1 | 0 | 0 | 0 | 0 | 1 |
| Total | 3566 | 3555 | 2927 | 1891 (163) | 432 (39) | 90 | 162 | 628 |
Deliverable Type Status
When a type is selected, only that type remains in this table and the register below.
| Deliverable Type | Total | Planned | Forecast | Actual | A | B | C | Pending | Overdue |
|---|---|---|---|---|---|---|---|---|---|
| DR - Drawing (DR) | 2466 | 2455 | 2455 | 1840 | 1129 (153) | 391 (29) | 82 | 124 | 615 |
| CA - Calculations (CA) | 813 | 813 | 813 | 813 | 707 (6) | 22 (2) | 0 | 26 | 0 |
| RP - Report (RP) | 106 | 106 | 106 | 106 | 4 | 0 | 0 | 2 | 0 |
| TS - Technical Submittals (TS) | 42 | 42 | 42 | 42 | 22 | 8 (2) | 3 | 8 | 0 |
| DN - Design Note (DN) | 32 | 32 | 32 | 32 | 0 | 0 | 0 | 0 | 0 |
| TW - Temporary Works (TW) | 27 | 27 | 27 | 27 | 16 | 1 | 0 | 1 | 0 |
| Unclassified | 25 | 25 | 25 | 17 | 0 | 0 | 0 | 0 | 8 |
| drawing | 11 | 11 | 11 | 9 | 4 (3) | 3 (2) | 1 | 0 | 2 |
| SS - Sample Submittal (SS) | 10 | 10 | 10 | 10 | 6 | 1 | 3 | 0 | 0 |
| PR - Programme (PR) | 6 | 6 | 6 | 6 | 0 | 0 | 0 | 0 | 0 |
| RG - Register (RG) | 6 | 6 | 6 | 6 | 0 | 1 | 0 | 0 | 0 |
| IP - Inspection and Test Plan (IP) | 4 | 4 | 4 | 4 | 0 | 0 | 0 | 0 | 0 |
| report | 4 | 4 | 4 | 2 | 2 (1) | 0 | 0 | 0 | 2 |
| schedule | 4 | 4 | 4 | 3 | 0 | 2 (1) | 1 | 0 | 1 |
| calculation | 2 | 2 | 2 | 2 | 1 | 0 | 0 | 1 | 0 |
| DS - Design Statement (DS) | 2 | 2 | 2 | 2 | 0 | 2 (2) | 0 | 0 | 0 |
| GU - Guide (GU) | 2 | 2 | 2 | 2 | 0 | 0 | 0 | 0 | 0 |
| SK - Sketch Drawing (SK) | 2 | 2 | 2 | 2 | 0 | 0 | 0 | 0 | 0 |
| IM - Information Management (IM) | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 0 | 0 |
| specification | 1 | 1 | 1 | 1 | 0 | 1 (1) | 0 | 0 | 0 |
| Total | 3566 | 3555 | 3555 | 2927 | 1891 (163) | 432 (39) | 90 | 162 | 628 |
Full-Scope Deliverables — Cumulative
Curve buttons now act as the legend. Projection uses the most recent 4-week issue and approval rates.
3566Total scope
Projected issue completionInsufficient recent progress0.0 docs/week · 639 remaining
Projected approval completionInsufficient recent progress0.0 docs/week · 1243 remaining
2323/2575A+B approved
Reporting cut-off: 25 Oct 2026. Projection: rolling 4-week current rate, not a contractual forecast. Prepublished: planned only. Pending: Awaiting Design Review only. A/B carry-forward: a previous A or B remains effective while a later revision is under review; C does not carry forward.
Consolidated Deliverables Register
Current Asite position. Pending is reserved for Awaiting Design Review; Prepublished means not yet issued.
3566of 3566 deliverables
| Document | Type | Package | Plan | CDE Actual | Rev | Approval / Position | Last Status Change | CDE Workflow | Control |
|---|---|---|---|---|---|---|---|---|---|
| LCY11-WHL-B1-XX-PR-S-00001Information Required Schedule IRS | PR - Programme (PR) | STR | 18 Dec 2024 | 03 Aug 2026Asite issue | C07 | For InformationNo approval required | 03 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-PR-S-00001Information Required Schedule IRS | PR - Programme (PR) | STR | 18 Dec 2024 | 03 Aug 2026Asite issue | C07 | For InformationNo approval required | 03 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00001Trade Contract Weekly Report | RP - Report (RP) | STR | 19 Dec 2024 | 19 Dec 2024Asite issue | C01 | AAccepted | 20 Feb 2025 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00002Trade Contractor Weekly Report | RP - Report (RP) | STR | 19 Dec 2024 | 19 Dec 2024Asite issue | C01 | For InformationNo approval required | 21 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00003Trade Contractor Weekly Report | RP - Report (RP) | STR | 19 Dec 2024 | 19 Dec 2024Asite issue | C01 | For InformationNo approval required | 21 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00004Trade Contractor Weekly Report | RP - Report (RP) | STR | 19 Dec 2024 | 19 Dec 2024Asite issue | C01 | For InformationNo approval required | 21 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00001Trade Contract Weekly Report | RP - Report (RP) | STR | 19 Dec 2024 | 19 Dec 2024Asite issue | C01 | AAccepted | 20 Feb 2025 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00002Trade Contractor Weekly Report | RP - Report (RP) | STR | 19 Dec 2024 | 19 Dec 2024Asite issue | C01 | For InformationNo approval required | 21 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00003Trade Contractor Weekly Report | RP - Report (RP) | STR | 19 Dec 2024 | 19 Dec 2024Asite issue | C01 | For InformationNo approval required | 21 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00004Trade Contractor Weekly Report | RP - Report (RP) | STR | 19 Dec 2024 | 19 Dec 2024Asite issue | C01 | For InformationNo approval required | 21 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28129Connection No.: 28129 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28111Connection No.: 28111 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28115Connection No.: 28115 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28128Connection No.: 28128 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28106Connection No.: 28106 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28114Connection No.: 28114 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Mar 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28130Connection No.: 28130 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28112Connection No.: 28112 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29103Connection No.: 29103 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28110Connection No.: 28110 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28106Connection No.: 28106 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28112Connection No.: 28112 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28114Connection No.: 28114 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Mar 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28115Connection No.: 28115 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28111Connection No.: 28111 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28110Connection No.: 28110 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28129Connection No.: 28129 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29103Connection No.: 29103 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28128Connection No.: 28128 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28130Connection No.: 28130 | CA - Calculations (CA) | STR | 20 Dec 2024 | 20 Dec 2024Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00005Trade Contract Weekly Report | RP - Report (RP) | STR | 07 Jan 2025 | 07 Jan 2025Asite issue | C01 | AAccepted | 20 Feb 2025 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00005Trade Contract Weekly Report | RP - Report (RP) | STR | 07 Jan 2025 | 07 Jan 2025Asite issue | C01 | AAccepted | 20 Feb 2025 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00006Trade Contractor Weekly Report | RP - Report (RP) | STR | 13 Jan 2025 | 13 Jan 2025Asite issue | C01 | For InformationNo approval required | 21 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00006Trade Contractor Weekly Report | RP - Report (RP) | STR | 13 Jan 2025 | 13 Jan 2025Asite issue | C01 | For InformationNo approval required | 21 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00007Trade Contractor Weekly Report | RP - Report (RP) | STR | 21 Jan 2025 | 21 Jan 2025Asite issue | C01 | For InformationNo approval required | 21 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00007Trade Contractor Weekly Report | RP - Report (RP) | STR | 21 Jan 2025 | 21 Jan 2025Asite issue | C01 | For InformationNo approval required | 21 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00008Trade Contractor Weekly Report | RP - Report (RP) | STR | 28 Jan 2025 | 28 Jan 2025Asite issue | C01 | For InformationNo approval required | 21 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00008Trade Contractor Weekly Report | RP - Report (RP) | STR | 28 Jan 2025 | 28 Jan 2025Asite issue | C01 | For InformationNo approval required | 21 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00009Trade Contractor Weekly Report | RP - Report (RP) | STR | 03 Feb 2025 | 03 Feb 2025Asite issue | C01 | For InformationNo approval required | 21 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00009Trade Contractor Weekly Report | RP - Report (RP) | STR | 03 Feb 2025 | 03 Feb 2025Asite issue | C01 | For InformationNo approval required | 21 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00010Trade Contractor Weekly Report | RP - Report (RP) | STR | 11 Feb 2025 | 11 Feb 2025Asite issue | C01 | For InformationNo approval required | 21 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00010Trade Contractor Weekly Report | RP - Report (RP) | STR | 11 Feb 2025 | 11 Feb 2025Asite issue | C01 | For InformationNo approval required | 21 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-RG-S-00001TIDP | RG - Register (RG) | STR | 12 Feb 2025 | 15 Dec 2025Asite issue | P05 | For InformationNo approval required | 15 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-RG-S-00001TIDP | RG - Register (RG) | STR | 12 Feb 2025 | 15 Dec 2025Asite issue | P05 | For InformationNo approval required | 15 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28148Connection No.: 28148 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28146Connection No.: 28146 | CA - Calculations (CA) | STR | 14 Feb 2025 | 08 Sept 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28144Connection No.: 28144 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28150Connection No.: 28150 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28132Connection No.: 28132 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28133Connection No.: 28133 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28139Connection No.: 28139 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28161Connection No.: 28161 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28145Connection No.: 28145 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28151Connection No.: 28151 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28165Connection No.: 28165 | CA - Calculations (CA) | STR | 14 Feb 2025 | 20 Mar 2026Asite issue | C02 | AAccepted | 26 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28149Connection No.: 28149 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28134Connection No.: 28134 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28141Connection No.: 28141 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28154Connection No.: 28154 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | BAccepted with comments | 12 Feb 2026 | Design Team - Status BCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28167Connection No.: 28167 | CA - Calculations (CA) | STR | 14 Feb 2025 | 20 Mar 2026Asite issue | C03 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28174Connection No.: 28174 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28179Connection No.: 28179 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28181Connection No.: 28181 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28183Connection No.: 28183 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29105Connection No.: 29105 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 17 Apr 2026 | Awaiting Client ReviewCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29108Connection No.: 29108 | CA - Calculations (CA) | STR | 14 Feb 2025 | 08 Sept 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29117Connection No.: 29117 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29119Connection No.: 29119 | CA - Calculations (CA) | STR | 14 Feb 2025 | 20 Mar 2026Asite issue | C02 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29123Connection No.: 29123 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28148Connection No.: 28148 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29123Connection No.: 29123 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28146Connection No.: 28146 | CA - Calculations (CA) | STR | 14 Feb 2025 | 08 Sept 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28132Connection No.: 28132 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28144Connection No.: 28144 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28150Connection No.: 28150 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28149Connection No.: 28149 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29117Connection No.: 29117 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28179Connection No.: 28179 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28134Connection No.: 28134 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28141Connection No.: 28141 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28174Connection No.: 28174 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29108Connection No.: 29108 | CA - Calculations (CA) | STR | 14 Feb 2025 | 08 Sept 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28145Connection No.: 28145 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28151Connection No.: 28151 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28165Connection No.: 28165 | CA - Calculations (CA) | STR | 14 Feb 2025 | 20 Mar 2026Asite issue | C02 | AAccepted | 26 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28167Connection No.: 28167 | CA - Calculations (CA) | STR | 14 Feb 2025 | 20 Mar 2026Asite issue | C03 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28183Connection No.: 28183 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28133Connection No.: 28133 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29119Connection No.: 29119 | CA - Calculations (CA) | STR | 14 Feb 2025 | 20 Mar 2026Asite issue | C02 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28139Connection No.: 28139 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28161Connection No.: 28161 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28154Connection No.: 28154 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | BAccepted with comments | 12 Feb 2026 | Design Team - Status BCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28181Connection No.: 28181 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29105Connection No.: 29105 | CA - Calculations (CA) | STR | 14 Feb 2025 | 17 Feb 2025Asite issue | C01 | AAccepted | 17 Apr 2026 | Awaiting Client ReviewCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00011Trade Contractor Weekly Report | RP - Report (RP) | STR | 17 Feb 2025 | 17 Feb 2025Asite issue | C01 | For InformationNo approval required | 18 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00011Trade Contractor Weekly Report | RP - Report (RP) | STR | 17 Feb 2025 | 17 Feb 2025Asite issue | C01 | For InformationNo approval required | 18 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-PR-S-00002Offsite Programme | PR - Programme (PR) | STR | 18 Feb 2025 | 18 Feb 2025Asite issue | 05 | For InformationNo approval required | 18 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-PR-S-00003Construction Programme | PR - Programme (PR) | STR | 18 Feb 2025 | 20 Feb 2025Asite issue | P15 | For InformationNo approval required | 13 Mar 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-PR-S-00002Offsite Programme | PR - Programme (PR) | STR | 18 Feb 2025 | 18 Feb 2025Asite issue | 05 | For InformationNo approval required | 18 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-PR-S-00003Construction Programme | PR - Programme (PR) | STR | 18 Feb 2025 | 20 Feb 2025Asite issue | P15 | For InformationNo approval required | 13 Mar 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00001FK CLADDING WEIGHT MARK-UPS | TS - Technical Submittals (TS) | FAC | 19 Feb 2025 | 19 Feb 2025Asite issue | P01 | WithdrawnWithdrawn | 10 Feb 2026 | WithdrawnCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-SK-S-00001Phase Document Plan | SK - Sketch Drawing (SK) | STR | 20 Feb 2025 | 20 Feb 2025Asite issue | 01 | For InformationNo approval required | 20 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-RG-S-00002Contractor Project Risk Register | RG - Register (RG) | STR | 20 Feb 2025 | 20 Feb 2025Asite issue | 01 | For InformationNo approval required | 20 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-SK-S-00001Phase Document Plan | SK - Sketch Drawing (SK) | STR | 20 Feb 2025 | 20 Feb 2025Asite issue | 01 | For InformationNo approval required | 20 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-RG-S-00002Contractor Project Risk Register | RG - Register (RG) | STR | 20 Feb 2025 | 20 Feb 2025Asite issue | 01 | For InformationNo approval required | 20 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29133Connection No.: 29133 | CA - Calculations (CA) | STR | 21 Feb 2025 | 31 Dec 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29129Connection No.: 29129 | CA - Calculations (CA) | STR | 21 Feb 2025 | 21 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29129Connection No.: 29129 | CA - Calculations (CA) | STR | 21 Feb 2025 | 21 Feb 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29133Connection No.: 29133 | CA - Calculations (CA) | STR | 21 Feb 2025 | 31 Dec 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-RG-X-00001FK GROUP TIDP | RG - Register (RG) | FAC | 24 Feb 2025 | 11 Jun 2026Asite issue | P05 | For InformationNo approval required | 12 Jun 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00012Trade Contractor Weekly Report | RP - Report (RP) | STR | 24 Feb 2025 | 24 Feb 2025Asite issue | C01 | For InformationNo approval required | 25 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00012Trade Contractor Weekly Report | RP - Report (RP) | STR | 24 Feb 2025 | 24 Feb 2025Asite issue | C01 | For InformationNo approval required | 25 Feb 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00010Grids 07-23, Along A & K, Tolerance Steel Lug Setting Out | DR - Drawing (DR) | FAC | 28 Feb 2025 | 09 Mar 2026Asite issue | P02 | AAccepted | 14 May 2026 | Status B - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00013Trade Contract Weekly Report Report No. 13 - 03-March 2025 | RP - Report (RP) | STR | 03 Mar 2025 | 05 Mar 2025Asite issue | C01 | For InformationNo approval required | 05 Mar 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00013Trade Contract Weekly Report Report No. 13 - 03-March 2025 | RP - Report (RP) | STR | 03 Mar 2025 | 05 Mar 2025Asite issue | C01 | For InformationNo approval required | 05 Mar 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28186Connection No.:28186 | CA - Calculations (CA) | STR | 04 Mar 2025 | 20 Mar 2026Asite issue | C03 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28190Connection No.:28190 | CA - Calculations (CA) | STR | 04 Mar 2025 | 04 Mar 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28193Connection No.:28193 | CA - Calculations (CA) | STR | 04 Mar 2025 | 04 Mar 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28191Connection No.:28191 | CA - Calculations (CA) | STR | 04 Mar 2025 | 04 Mar 2025Asite issue | C01 | BAccepted with comments | 08 Apr 2025 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28192Connection No.:28192 | CA - Calculations (CA) | STR | 04 Mar 2025 | 04 Mar 2025Asite issue | C01 | BAccepted with comments | 08 Apr 2025 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28187Connection No.:28187 | CA - Calculations (CA) | STR | 04 Mar 2025 | 20 Mar 2026Asite issue | C02 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28187Connection No.:28187 | CA - Calculations (CA) | STR | 04 Mar 2025 | 20 Mar 2026Asite issue | C02 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28191Connection No.:28191 | CA - Calculations (CA) | STR | 04 Mar 2025 | 04 Mar 2025Asite issue | C01 | BAccepted with comments | 08 Apr 2025 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28190Connection No.:28190 | CA - Calculations (CA) | STR | 04 Mar 2025 | 04 Mar 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28192Connection No.:28192 | CA - Calculations (CA) | STR | 04 Mar 2025 | 04 Mar 2025Asite issue | C01 | BAccepted with comments | 08 Apr 2025 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28193Connection No.:28193 | CA - Calculations (CA) | STR | 04 Mar 2025 | 04 Mar 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28186Connection No.:28186 | CA - Calculations (CA) | STR | 04 Mar 2025 | 20 Mar 2026Asite issue | C03 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-CA-X-00001Wind Load Calculations | CA - Calculations (CA) | FAC | 07 Mar 2025 | 07 Mar 2025Asite issue | P02 | CancelledWorkflow cancelled | 10 Feb 2026 | Cancelled WorkflowCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00014Trade Contractor Weekly Report | RP - Report (RP) | STR | 10 Mar 2025 | 10 Mar 2025Asite issue | C01 | For InformationNo approval required | 11 Mar 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00014Trade Contractor Weekly Report | RP - Report (RP) | STR | 10 Mar 2025 | 10 Mar 2025Asite issue | C01 | For InformationNo approval required | 11 Mar 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00011Grids 14-17, Along F & G, Tolerance Steel Lug Details | DR - Drawing (DR) | FAC | 14 Mar 2025 | 06 Mar 2026Asite issue | P02 | AAccepted | 14 May 2026 | Status B - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00015Trade Contractor Weekly Report | RP - Report (RP) | STR | 17 Mar 2025 | 17 Mar 2025Asite issue | C01 | For InformationNo approval required | 18 Mar 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00015Trade Contractor Weekly Report | RP - Report (RP) | STR | 17 Mar 2025 | 17 Mar 2025Asite issue | C01 | For InformationNo approval required | 18 Mar 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-CA-X-00002Thermal Analysis | CA - Calculations (CA) | FAC | 19 Mar 2025 | 19 Mar 2025Asite issue | P01 | AAccepted | 26 Feb 2026 | Status B - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TS-S-00001Farrat TBK & TBF Thermal Break | TS - Technical Submittals (TS) | STR | 19 Mar 2025 | 22 Jul 2026Asite issue | C03 | PendingAwaiting Design Review | 24 Jul 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TS-S-00001Farrat TBK & TBF Thermal Break | TS - Technical Submittals (TS) | STR | 19 Mar 2025 | 22 Jul 2026Asite issue | C03 | PendingAwaiting Design Review | 24 Jul 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00002Kingspan K-Roc Karrier Panels | TS - Technical Submittals (TS) | FAC | 24 Mar 2025 | 03 Apr 2025Asite issue | P02 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00003Kingspan BrickClad Façade | TS - Technical Submittals (TS) | FAC | 24 Mar 2025 | 03 Apr 2025Asite issue | P02 | BAccepted with comments | 16 Feb 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00016Trade Contractor Weekly Report | RP - Report (RP) | STR | 24 Mar 2025 | 24 Mar 2025Asite issue | C01 | For InformationNo approval required | 25 Mar 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00016Trade Contractor Weekly Report | RP - Report (RP) | STR | 24 Mar 2025 | 24 Mar 2025Asite issue | C01 | For InformationNo approval required | 25 Mar 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY10-FKG-XX-XX-SS-X-00008KAWNEER AA110 CURTAIN WALL | SS - Sample Submittal (SS) | FAC | 25 Mar 2025 | 03 Apr 2025Asite issue | P02 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY10-FKG-XX-XX-SS-X-00009STEEL-LOOK FEATURE PANEL | SS - Sample Submittal (SS) | FAC | 25 Mar 2025 | 03 Apr 2025Asite issue | P02 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY10-FKG-XX-XX-SS-X-00006ALUMINIUM PERFORATED PLANK | SS - Sample Submittal (SS) | FAC | 25 Mar 2025 | 03 Apr 2025Asite issue | P02 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY10-FKG-XX-XX-SS-X-00011CAICE ACOUSTIC LOUVRE (ALL ROOF LOUVRES) | SS - Sample Submittal (SS) | FAC | 25 Mar 2025 | 03 Apr 2025Asite issue | P02 | CRejected | 16 Feb 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY10-FKG-XX-XX-SS-X-00001KINGSPAN K-ROC KARRIER PANEL 240mm DEEP | SS - Sample Submittal (SS) | FAC | 25 Mar 2025 | 03 Apr 2025Asite issue | P02 | AAccepted | 09 Feb 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY10-FKG-XX-XX-SS-X-00002BRICKCLAD RAINSCREEN - 250mm DEEP | SS - Sample Submittal (SS) | FAC | 25 Mar 2025 | 03 Apr 2025Asite issue | P02 | BAccepted with comments | 16 Feb 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY10-FKG-XX-XX-SS-X-00010CAICE VERTICAL WEATHER LOUVRE (GROUND FLOOR) | SS - Sample Submittal (SS) | FAC | 25 Mar 2025 | 03 Apr 2025Asite issue | P02 | CRejected | 16 Feb 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY10-FKG-XX-XX-SS-X-00004ALUMINIUM RAINSCREEN - 300mm DEEP | SS - Sample Submittal (SS) | FAC | 25 Mar 2025 | 03 Apr 2025Asite issue | P02 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29142Connection No.: 29142 | CA - Calculations (CA) | STR | 25 Mar 2025 | 25 Mar 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29138Connection No.: 29138 | CA - Calculations (CA) | STR | 25 Mar 2025 | 25 Mar 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29143Connection No.: 29143 | CA - Calculations (CA) | STR | 25 Mar 2025 | 25 Mar 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29138Connection No.: 29138 | CA - Calculations (CA) | STR | 25 Mar 2025 | 25 Mar 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29142Connection No.: 29142 | CA - Calculations (CA) | STR | 25 Mar 2025 | 25 Mar 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29143Connection No.: 29143 | CA - Calculations (CA) | STR | 25 Mar 2025 | 25 Mar 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00005FIXFAST MAIN PANEL FIX LIGHT | TS - Technical Submittals (TS) | FAC | 27 Mar 2025 | 03 Apr 2025Asite issue | P01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00008PREMSEAL 9X3 MASTIC TAPE | TS - Technical Submittals (TS) | FAC | 27 Mar 2025 | 03 Apr 2025Asite issue | P01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00011ILBROOK SP025 EPDM SEALANT | TS - Technical Submittals (TS) | FAC | 27 Mar 2025 | 03 Apr 2025Asite issue | P01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00006PREMSEAL VJ2 BUBBLE GASKETT | TS - Technical Submittals (TS) | FAC | 27 Mar 2025 | 03 Apr 2025Asite issue | P01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00009PREMSEAL 20x9 FOAM TAPE | TS - Technical Submittals (TS) | FAC | 27 Mar 2025 | 03 Apr 2025Asite issue | P01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00012STAINLESS STEEL RIVET | TS - Technical Submittals (TS) | FAC | 27 Mar 2025 | 03 Apr 2025Asite issue | P01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00004FIXFAST MAIN PANEL FIX - HEAVY | TS - Technical Submittals (TS) | FAC | 27 Mar 2025 | 03 Apr 2025Asite issue | P01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00007PREMSEAL BR GUN MASTIC | TS - Technical Submittals (TS) | FAC | 27 Mar 2025 | 03 Apr 2025Asite issue | P01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00013FIXFAST DF3 FIXING | TS - Technical Submittals (TS) | FAC | 27 Mar 2025 | 03 Apr 2025Asite issue | P01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00010ILBROOK ME220 EPDM MEMBRANE | TS - Technical Submittals (TS) | FAC | 27 Mar 2025 | 03 Apr 2025Asite issue | P01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00210South East core - SFS elevations | DR - Drawing (DR) | FAC | 28 Mar 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-11004Steelwork Foundation Details - Sheet 1 | DR - Drawing (DR) | STR | 28 Mar 2025 | 02 Apr 2025Asite issue | C01 | AAccepted | 23 Jul 2026 | Status A - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-20004Steelwork Foundation Details - Sheet 1 | DR - Drawing (DR) | STR | 28 Mar 2025 | 02 Apr 2025Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-40006Steelwork Foundation Details - Sheet3 | DR - Drawing (DR) | STR | 28 Mar 2025 | 28 Mar 2025Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-20006Steelwork Foundation Details - Sheet 3 | DR - Drawing (DR) | STR | 28 Mar 2025 | 02 Apr 2025Asite issue | C01 | AAccepted | 09 Feb 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-11005Steelwork Foundation Details - Sheet 2 | DR - Drawing (DR) | STR | 28 Mar 2025 | 02 Apr 2025Asite issue | C01 | AAccepted | 23 Jul 2026 | Status A - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-20005Steelwork Foundation Details - Sheet 2 | DR - Drawing (DR) | STR | 28 Mar 2025 | 02 Apr 2025Asite issue | C01 | AAccepted | 09 Feb 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-11004Steelwork Foundation Details - Sheet 1 | DR - Drawing (DR) | STR | 28 Mar 2025 | 02 Apr 2025Asite issue | C01 | AAccepted | 23 Jul 2026 | Status A - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-20004Steelwork Foundation Details - Sheet 1 | DR - Drawing (DR) | STR | 28 Mar 2025 | 02 Apr 2025Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-40006Steelwork Foundation Details - Sheet3 | DR - Drawing (DR) | STR | 28 Mar 2025 | 28 Mar 2025Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-20006Steelwork Foundation Details - Sheet 3 | DR - Drawing (DR) | STR | 28 Mar 2025 | 02 Apr 2025Asite issue | C01 | AAccepted | 09 Feb 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-11005Steelwork Foundation Details - Sheet 2 | DR - Drawing (DR) | STR | 28 Mar 2025 | 02 Apr 2025Asite issue | C01 | AAccepted | 23 Jul 2026 | Status A - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-20005Steelwork Foundation Details - Sheet 2 | DR - Drawing (DR) | STR | 28 Mar 2025 | 02 Apr 2025Asite issue | C01 | AAccepted | 09 Feb 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03056VMU 5 - SECTION DETAIL 3 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C02 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-02003VMU 3 - ELEVATION | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03011VMU 2 - PLAN DETAIL 2 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03020VMU 3 - PLAN DETAIL 1 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C02 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-02002VMU 2 - ELEVATION | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03010VMU 2 - PLAN DETAIL 1 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03016VMU 2 - SECTION DETAIL 4 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03060VMU 6 - PLAN DETAIL 1 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C02 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-02006VMU 5 - ELEVATION | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C02 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03012VMU 2 - PLAN DETAIL 3 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03021VMU 3 - PLAN DETAIL 2 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C02 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03063VMU 6 - PLAN DETAIL 2 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03001VMU 1 - PLAN DETAIL 1 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03014VMU 2 - SECTION DETAIL 2 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03050VMU 5 - PLAN DETAIL 1 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03030VMU 4 - PLAN DETAIL 1 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 01 Apr 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03061VMU 6 - SECTION DETAIL 1 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-02007VMU 6 - ELEVATION | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03013VMU 2 - SECTION DETAIL 1 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03022VMU 3 - SECTION DETAIL 1 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03033VMU 4 - SECTION DETAIL 2 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 01 Apr 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-02001VMU 1 - ELEVATION | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03002VMU 1 - SECTION DETAIL 1 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03015VMU 2 - SECTION DETAIL 3 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03051VMU 5 - PLAN DETAIL 2 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03031VMU 4 - PLAN DETAIL 2 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 01 Apr 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-02004VMU 4 - ELEVATION | DN - Design Note (DN) | FAC | 31 Mar 2025 | 01 Apr 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03053VMU 5 - PLAN DETAIL 4 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03032VMU 4 - SECTION DETAIL 1 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 01 Apr 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03054VMU 5 - SECTION DETAIL 1 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03055VMU 5 - SECTION DETAIL 2 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-XX-XX-DN-X-03052VMU 5 - PLAN DETAIL 3 | DN - Design Note (DN) | FAC | 31 Mar 2025 | 31 Mar 2025Asite issue | C01 | For InformationNo approval required | 09 Dec 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00017Trade Contractor Weekly Report | RP - Report (RP) | STR | 01 Apr 2025 | 01 Apr 2025Asite issue | C01 | For InformationNo approval required | 02 Apr 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-40005Steelwork Foundation Details - Sheet2 | DR - Drawing (DR) | STR | 01 Apr 2025 | 02 Apr 2025Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-40004Steelwork Foundation Details - Sheet1 | DR - Drawing (DR) | STR | 01 Apr 2025 | 02 Apr 2025Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-31004Steelwork Foundation Details - Sheet 1 | DR - Drawing (DR) | STR | 01 Apr 2025 | 02 Apr 2025Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00017Trade Contractor Weekly Report | RP - Report (RP) | STR | 01 Apr 2025 | 01 Apr 2025Asite issue | C01 | For InformationNo approval required | 02 Apr 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-31004Steelwork Foundation Details - Sheet 1 | DR - Drawing (DR) | STR | 01 Apr 2025 | 02 Apr 2025Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-40005Steelwork Foundation Details - Sheet2 | DR - Drawing (DR) | STR | 01 Apr 2025 | 02 Apr 2025Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-40004Steelwork Foundation Details - Sheet1 | DR - Drawing (DR) | STR | 01 Apr 2025 | 02 Apr 2025Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00014CAICE LOUVRE TECHNICAL INFO | TS - Technical Submittals (TS) | FAC | 03 Apr 2025 | 01 Apr 2026Asite issue | P03 | AAccepted | 04 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00017FIXFAST DF12 FIXING | TS - Technical Submittals (TS) | FAC | 03 Apr 2025 | 03 Apr 2025Asite issue | P01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00018PRE COAT 0.7MM FLASHING | TS - Technical Submittals (TS) | FAC | 03 Apr 2025 | 03 Apr 2025Asite issue | P01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00016POWDERCOATING | TS - Technical Submittals (TS) | FAC | 03 Apr 2025 | 03 Apr 2025Asite issue | P01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00019M10 - NUT & BOLT | TS - Technical Submittals (TS) | FAC | 03 Apr 2025 | 03 Apr 2025Asite issue | P01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00020S280 GALV | TS - Technical Submittals (TS) | FAC | 03 Apr 2025 | 03 Apr 2025Asite issue | P01 | BAccepted with comments | 16 Feb 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00022CURTAIN WALL INFO | TS - Technical Submittals (TS) | FAC | 03 Apr 2025 | 03 Apr 2025Asite issue | P01 | BAccepted with comments | 10 Feb 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00015ALUMINIUM FLASHING | TS - Technical Submittals (TS) | FAC | 03 Apr 2025 | 03 Apr 2025Asite issue | P01 | BAccepted with comments | 16 Feb 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00021SPANDREL PANEL INSULATION & GLUE | TS - Technical Submittals (TS) | FAC | 03 Apr 2025 | 03 Apr 2025Asite issue | P01 | CRejected | 17 Feb 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-GU-S-11001WHL BIM model submission - Explanatory notes | GU - Guide (GU) | STR | 04 Apr 2025 | 04 Apr 2025Asite issue | P01 | For InformationNo approval required | 04 Apr 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-GU-S-11001WHL BIM model submission - Explanatory notes | GU - Guide (GU) | STR | 04 Apr 2025 | 04 Apr 2025Asite issue | P01 | For InformationNo approval required | 04 Apr 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00018Trade Contractor Weekly Report | RP - Report (RP) | STR | 07 Apr 2025 | 07 Apr 2025Asite issue | C01 | For InformationNo approval required | 08 Apr 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00018Trade Contractor Weekly Report | RP - Report (RP) | STR | 07 Apr 2025 | 07 Apr 2025Asite issue | C01 | For InformationNo approval required | 08 Apr 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00023FL6 FABLOCK FIXING | TS - Technical Submittals (TS) | FAC | 10 Apr 2025 | 10 Apr 2025Asite issue | P01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00211South East core - panel elevations and wind loads | DR - Drawing (DR) | FAC | 11 Apr 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28218Connection No.: 28218 | CA - Calculations (CA) | STR | 11 Apr 2025 | 11 Apr 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28218Connection No.: 28218 | CA - Calculations (CA) | STR | 11 Apr 2025 | 11 Apr 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00019Trade Contractor Weekly Report | RP - Report (RP) | STR | 14 Apr 2025 | 14 Apr 2025Asite issue | C01 | For InformationNo approval required | 15 Apr 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00019Trade Contractor Weekly Report | RP - Report (RP) | STR | 14 Apr 2025 | 14 Apr 2025Asite issue | C01 | For InformationNo approval required | 15 Apr 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00132East elevation lower building - Phase 5 PPC support framing for feature | DR - Drawing (DR) | FAC | 15 Apr 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00133East elevation lower building - Phase 5 support framing for brickslip | DR - Drawing (DR) | FAC | 15 Apr 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00024TOLERANCE CHANNEL STUDY | TS - Technical Submittals (TS) | FAC | 22 Apr 2025 | 22 Apr 2025Asite issue | P01 | CRejected | 03 Feb 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00020Trade Contractor Weekly Report | RP - Report (RP) | STR | 22 Apr 2025 | 22 Apr 2025Asite issue | C01 | For InformationNo approval required | 22 Apr 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00020Trade Contractor Weekly Report | RP - Report (RP) | STR | 22 Apr 2025 | 22 Apr 2025Asite issue | C01 | For InformationNo approval required | 22 Apr 2025 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY10-FKG-DC-XX-SS-X-00013Dust Canopy Sample & Bronze Swatch | SS - Sample Submittal (SS) | FAC | 24 Apr 2025 | 24 Apr 2025Asite issue | P01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY10-FKG-DC-XX-SS-X-00012Dust Canopy Sample & Green Swatches | SS - Sample Submittal (SS) | FAC | 24 Apr 2025 | 24 Apr 2025Asite issue | P01 | CRejected | 03 Feb 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00182Typical large flue - internal panel elevation and wind loads | DR - Drawing (DR) | FAC | 29 Apr 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00186Typical small flue - external panel elevation and wind loads | DR - Drawing (DR) | FAC | 29 Apr 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00181Typical large flue - external panel elevation and wind loads | DR - Drawing (DR) | FAC | 29 Apr 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00200North East core - SFS elevations | DR - Drawing (DR) | FAC | 29 Apr 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00191Typical end flue - external panel elevation and wind loads | DR - Drawing (DR) | FAC | 29 Apr 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00187Typical small flue - internal panel elevation and wind loads | DR - Drawing (DR) | FAC | 29 Apr 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY10-FKG-XX-XX-TW-X-00010MAST CLIMBER TIE DETAIL - STANDARD DETAIL | TW - Temporary Works (TW) | FAC | 29 Apr 2025 | 29 Apr 2025Asite issue | P01 | CancelledWorkflow cancelled | 10 Feb 2026 | Cancelled WorkflowCANCELLED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00192Typical end flue - internal panel elevation and wind loads | DR - Drawing (DR) | FAC | 29 Apr 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00135East elevation lower building - Phase 5 brickslip marks | DR - Drawing (DR) | FAC | 07 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00201North East core - panel elevations and wind loads | DR - Drawing (DR) | FAC | 07 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00134East elevation lower building - Phase 5 PPC panel marks | DR - Drawing (DR) | FAC | 07 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03000Brickslip standard projection specification | DR - Drawing (DR) | FAC | 07 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01094Digital feature capping | DR - Drawing (DR) | FAC | 14 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01100Parapet door jamb (west elevation lower roof) | DR - Drawing (DR) | FAC | 14 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01099Parapet door cill (west elevation lower roof) | DR - Drawing (DR) | FAC | 14 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00230South West core - SFS elevations | DR - Drawing (DR) | FAC | 14 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01095Brickslip external corner | DR - Drawing (DR) | FAC | 14 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01079Parapet cill (cores) | DR - Drawing (DR) | FAC | 14 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01080Parapet internal corner (cores) | DR - Drawing (DR) | FAC | 14 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01098Parapet door head (west elevation lower roof) | DR - Drawing (DR) | FAC | 14 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01078Parapet head (cores) | DR - Drawing (DR) | FAC | 14 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00141West elevation - Phase 6 panel elevation and wind loads | DR - Drawing (DR) | FAC | 15 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28107Connection No.: 28107 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28140Connection No.: 28140 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28143Connection No.: 28143 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28123Connection No.: 28123 | CA - Calculations (CA) | STR | 17 May 2025 | 20 Mar 2026Asite issue | C05 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28137Connection No.: 28137 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28147Connection No.: 28147 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28104Connection No.: 28104 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28100Connection No.: 28100 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28126Connection No.: 28126 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C03 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28102Connection No.: 28102 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C03 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28101Connection No.: 28101 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29102Connection No.: 29102 | CA - Calculations (CA) | STR | 17 May 2025 | 20 Mar 2026Asite issue | C03 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28177Connection No.: 28177 | CA - Calculations (CA) | STR | 17 May 2025 | 20 Mar 2026Asite issue | C04 | AAccepted | 26 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28180Connection No.: 28180 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C03 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29110Connection No.: 29110 | CA - Calculations (CA) | STR | 17 May 2025 | 20 Mar 2026Asite issue | C03 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29114Connection No.: 29114 | CA - Calculations (CA) | STR | 17 May 2025 | 20 Mar 2026Asite issue | C03 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28210Connection No.: 28210 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29111Connection No.: 29111 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29113Connection No.: 29113 | CA - Calculations (CA) | STR | 17 May 2025 | 20 Mar 2026Asite issue | C03 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29122Connection No.: 29122 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28194Connection No.: 28194 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29151Connection No.: 29151 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28208Connection No.: 28208 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28226Connection No.: 28226 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28257Connection No.: 28257 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29144Connection No.: 29144 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29159Connection No.: 29159 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29170Connection No.: 29170 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29194Connection No.: 29194 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28198Connection No.: 28198 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28205Connection No.: 28205 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28223Connection No.: 28223 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29154Connection No.: 29154 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29167Connection No.: 29167 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29180Connection No.: 29180 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28206Connection No.: 28206 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28224Connection No.: 28224 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29155Connection No.: 29155 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29168Connection No.: 29168 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29182Connection No.: 29182 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 05 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28209Connection No.: 28209 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28227Connection No.: 28227 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28239Connection No.: 28239 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28258Connection No.: 28258 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29146Connection No.: 29146 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29161Connection No.: 29161 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28207Connection No.: 28207 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28225Connection No.: 28225 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28256Connection No.: 28256 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29157Connection No.: 29157 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29169Connection No.: 29169 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29190Connection No.: 29190 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28196Connection No.: 28196 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29152Connection No.: 29152 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29165Connection No.: 29165 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29176Connection No.: 29176 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28197Connection No.: 28197 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28204Connection No.: 28204 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28221Connection No.: 28221 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29137Connection No.: 29137 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 17 Apr 2026 | Awaiting Client ReviewCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29153Connection No.: 29153 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29166Connection No.: 29166 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29178Connection No.: 29178 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28229Connection No.: 28229 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28240Connection No.: 28240 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28260Connection No.: 28260 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29136Connection No.: 29136 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 17 Apr 2026 | Awaiting Client ReviewCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29149Connection No.: 29149 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29162Connection No.: 29162 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28251Connection No.: 28251 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28262Connection No.: 28262 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29150Connection No.: 29150 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29163Connection No.: 29163 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29164Connection No.: 29164 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28107Connection No.: 28107 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28140Connection No.: 28140 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28143Connection No.: 28143 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28104Connection No.: 28104 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28100Connection No.: 28100 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28102Connection No.: 28102 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C03 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28147Connection No.: 28147 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28177Connection No.: 28177 | CA - Calculations (CA) | STR | 17 May 2025 | 20 Mar 2026Asite issue | C04 | AAccepted | 26 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29122Connection No.: 29122 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29110Connection No.: 29110 | CA - Calculations (CA) | STR | 17 May 2025 | 20 Mar 2026Asite issue | C03 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29114Connection No.: 29114 | CA - Calculations (CA) | STR | 17 May 2025 | 20 Mar 2026Asite issue | C03 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28101Connection No.: 28101 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28123Connection No.: 28123 | CA - Calculations (CA) | STR | 17 May 2025 | 20 Mar 2026Asite issue | C05 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28137Connection No.: 28137 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29102Connection No.: 29102 | CA - Calculations (CA) | STR | 17 May 2025 | 20 Mar 2026Asite issue | C03 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28126Connection No.: 28126 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C03 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28180Connection No.: 28180 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C03 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29111Connection No.: 29111 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C02 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29113Connection No.: 29113 | CA - Calculations (CA) | STR | 17 May 2025 | 20 Mar 2026Asite issue | C03 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28207Connection No.: 28207 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28198Connection No.: 28198 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28205Connection No.: 28205 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28223Connection No.: 28223 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29154Connection No.: 29154 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29167Connection No.: 29167 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28206Connection No.: 28206 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28224Connection No.: 28224 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28208Connection No.: 28208 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28226Connection No.: 28226 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28257Connection No.: 28257 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29144Connection No.: 29144 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28197Connection No.: 28197 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28209Connection No.: 28209 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28227Connection No.: 28227 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28239Connection No.: 28239 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28210Connection No.: 28210 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28229Connection No.: 28229 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28240Connection No.: 28240 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28260Connection No.: 28260 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29136Connection No.: 29136 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 17 Apr 2026 | Awaiting Client ReviewCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29149Connection No.: 29149 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29162Connection No.: 29162 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28251Connection No.: 28251 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28262Connection No.: 28262 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29150Connection No.: 29150 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29163Connection No.: 29163 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28196Connection No.: 28196 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29152Connection No.: 29152 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29165Connection No.: 29165 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29176Connection No.: 29176 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28194Connection No.: 28194 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29151Connection No.: 29151 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29164Connection No.: 29164 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28204Connection No.: 28204 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28221Connection No.: 28221 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29137Connection No.: 29137 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 17 Apr 2026 | Awaiting Client ReviewCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29153Connection No.: 29153 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29166Connection No.: 29166 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29178Connection No.: 29178 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28225Connection No.: 28225 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28256Connection No.: 28256 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29157Connection No.: 29157 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29169Connection No.: 29169 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29190Connection No.: 29190 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28258Connection No.: 28258 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29146Connection No.: 29146 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29161Connection No.: 29161 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29155Connection No.: 29155 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29168Connection No.: 29168 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29182Connection No.: 29182 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 05 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29159Connection No.: 29159 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29170Connection No.: 29170 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29194Connection No.: 29194 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29180Connection No.: 29180 | CA - Calculations (CA) | STR | 17 May 2025 | 17 May 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00046South elevation - Phase 2 PPC support framing for projecting feature | DR - Drawing (DR) | FAC | 21 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00056North elevation - Phase 3 PPC support projecting feature | DR - Drawing (DR) | FAC | 21 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00076North elevation - Phase 4 PPC support projecting feature | DR - Drawing (DR) | FAC | 21 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00086South elevation - Phase 4 PPC support framing for projecting feature | DR - Drawing (DR) | FAC | 21 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00096North elevation - Phase 5 PPC support projecting feature | DR - Drawing (DR) | FAC | 21 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00106South elevation - Phase 5 PPC support framing for projecting feature | DR - Drawing (DR) | FAC | 21 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00042South elevation - Phase 2 PPC support framing for feature | DR - Drawing (DR) | FAC | 21 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00052North elevation - Phase 3 PPC support framing for feature | DR - Drawing (DR) | FAC | 21 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00072North elevation - Phase 4 PPC support framing for feature | DR - Drawing (DR) | FAC | 21 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00082South elevation - Phase 4 PPC support framing for feature | DR - Drawing (DR) | FAC | 21 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00092North elevation - Phase 5 PPC support framing for feature | DR - Drawing (DR) | FAC | 21 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00102South elevation - Phase 5 PPC support framing for feature | DR - Drawing (DR) | FAC | 21 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00012Grids 14-17, Along F & G, Tolerance Steel Lug Setting Out | DR - Drawing (DR) | FAC | 21 May 2025 | 22 May 2026Asite issue | P02 | AAccepted | 30 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00022South elevation - Phase 1 PPC support framing for feature | DR - Drawing (DR) | FAC | 21 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00026South elevation - Phase 1 PPC support framing for projecting feature | DR - Drawing (DR) | FAC | 21 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01030Feature drip (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01036Feature capping (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01034Brickslip external corner (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01040Brickslip door jamb (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01064Parapet head (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01033Brickslip internal corner (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01039Brickslip door head (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01063Feature cill to parapet upstand (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01029Brickslip drip (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01035Brickslip feature/capping (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01041Brickslip door cill (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01065Parapet cill (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00231South West core - panel elevations and wind loads | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01031Feature horizontal section (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01037Feature external corner (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01067Parapet corner to main building (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01097Feature cruciform (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01032Feature vertical section (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01038Feature internal corner (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01066Parapet internal corner (east lower building) | DR - Drawing (DR) | FAC | 29 May 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01159Curtain wall/glazing detail | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01165Curtain wall/glazing detail | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01158Curtain wall/glazing detail | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01164Curtain wall/glazing detail | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01160Curtain wall/glazing detail | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01166Curtain wall/glazing detail | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00163West elevation office - curtain wall/glazing | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00169West elevation office - curtain wall/glazing | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00165West elevation office - curtain wall/glazing | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00043South elevation - Phase 2 PPC support framing for perforated | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00053North elevation - Phase 3 PPC support framing for perforated | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00083South elevation - Phase 4 PPC support framing for perforated | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00103South elevation - Phase 5 PPC support framing for perforated | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00160West elevation office - curtain wall/glazing | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00166West elevation office - curtain wall/glazing | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00164West elevation office - curtain wall/glazing | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00220North West core - SFS elevations | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00162West elevation office - curtain wall/glazing | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00168West elevation office - curtain wall/glazing | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00167West elevation office - curtain wall/glazing | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01156Curtain wall/glazing detail | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01157Curtain wall/glazing detail | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01163Curtain wall/glazing detail | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01169Curtain wall/glazing detail | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01150Curtain wall/glazing detail | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01161Curtain wall/glazing detail | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01167Curtain wall/glazing detail | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01162Curtain wall/glazing detail | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01168Curtain wall/glazing detail | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00013Grids 12-14 & 17-19, Along F & G, Tolerance Steel Lug Details | DR - Drawing (DR) | FAC | 05 Jun 2025 | 22 May 2026Asite issue | P02 | AAccepted | 30 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00161West elevation office - curtain wall/glazing | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00023South elevation - Phase 1 PPC support framing for perforated | DR - Drawing (DR) | FAC | 05 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01088Flue internal corner (external) | DR - Drawing (DR) | FAC | 12 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01093Flue upper roof abutment (external) | DR - Drawing (DR) | FAC | 12 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01087Flue floor detail (internal) | DR - Drawing (DR) | FAC | 12 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01083Flue internal corner (internal) | DR - Drawing (DR) | FAC | 12 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01089Flue external corner (external) | DR - Drawing (DR) | FAC | 12 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01085Flue base detail (internal) | DR - Drawing (DR) | FAC | 12 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01091Flue head detail (external) | DR - Drawing (DR) | FAC | 12 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01086Flue head detail (internal) | DR - Drawing (DR) | FAC | 12 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01092Flue panel joint detail (external) | DR - Drawing (DR) | FAC | 12 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01084Flue 'T' internal corner (internal) | DR - Drawing (DR) | FAC | 12 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01090Flue base detail (external) | DR - Drawing (DR) | FAC | 12 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01096Feature cruciform | DR - Drawing (DR) | FAC | 12 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00240West core - panel elevations and wind loads | DR - Drawing (DR) | FAC | 19 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00221North West core - panel elevations and wind loads | DR - Drawing (DR) | FAC | 19 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01076Parapet to louvre (lower roof) | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01106Parapet stub penetration | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00024South elevation - Phase 1 PPC panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00044South elevation - Phase 2 PPC panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00054North elevation - Phase 3 PPC panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00074North elevation - Phase 4 PPC panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00084South elevation - Phase 4 PPC panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00094North elevation - Phase 5 PPC panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00104South elevation - Phase 5 PPC panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00025South elevation - Phase 1 PPC perforated panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00045South elevation - Phase 2 PPC perforated panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00055North elevation - Phase 3 PPC perforated panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00075North elevation - Phase 4 PPC perforated panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00085South elevation - Phase 4 PPC perforated panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00095North elevation - Phase 5 PPC perforated panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00105South elevation - Phase 5 PPC perforated panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00073North elevation - Phase 4 PPC support framing for perforated | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00047South elevation - Phase 2 PPC projecting feature panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00077North elevation - Phase 4 PPC projecting feature panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00087South elevation - Phase 4 PPC projecting feature panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00097North elevation - Phase 5 PPC projecting feature panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00107South elevation - Phase 5 PPC projecting feature panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01075Parapet internal corner (lower roof) | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01077Brickclad internal corner to louvre (lower roof) | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01009Capping to column casing | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01073Parapet head (lower roof) | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01010Column casing to louvre cill | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01074Parapet cill (lower roof) | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00015Grids 9,11,13,18,20 & 22, Along F & G, Tolerance Steel Lug Setting Out | DR - Drawing (DR) | FAC | 20 Jun 2025 | 23 Feb 2026Asite issue | P01 | AAccepted | 02 Apr 2026 | MCL Final Status,Subcontractor NotifyRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00014Grids 8,10,12,14,17,19,21 & 23, Along F & G, Tolerance Steel Lug Setting Out | DR - Drawing (DR) | FAC | 20 Jun 2025 | 22 May 2026Asite issue | P02 | AAccepted | 30 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01011Grids 06-24 Rainscreen Cladding GA North Elevation | DR - Drawing (DR) | FAC | 20 Jun 2025 | 25 Jun 2026Asite issue | C02 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01012Grids 06-24 Rainscreen Cladding GA South Elevation | DR - Drawing (DR) | FAC | 20 Jun 2025 | 25 Jun 2026Asite issue | C02 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00027South elevation - Phase 1 PPC projecting feature panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00093North elevation - Phase 5 PPC support framing for perforated | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00057North elevation - Phase 3 PPC projecting feature panel marks | DR - Drawing (DR) | FAC | 20 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00111East elevation GL.B-G - Phase 5 panel elevation and wind loads | DR - Drawing (DR) | FAC | 26 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00121East elevation GL.G-J - Phase 5 panel elevation and wind loads | DR - Drawing (DR) | FAC | 26 Jun 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00212South East core - support work for PPC features | DR - Drawing (DR) | FAC | 10 Jul 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00214South East core - brickslip top hats | DR - Drawing (DR) | FAC | 10 Jul 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00215South East core - brickslip omega rails | DR - Drawing (DR) | FAC | 10 Jul 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00202North East core - support work for PPC features | DR - Drawing (DR) | FAC | 31 Jul 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00204North East core - brickslip top hats | DR - Drawing (DR) | FAC | 31 Jul 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00205North East core - brickslip omega rails | DR - Drawing (DR) | FAC | 31 Jul 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00142West elevation - Phase 6 PPC support framing for feature | DR - Drawing (DR) | FAC | 07 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00151West elevation office - Phase 6 panel elevation and wind loads | DR - Drawing (DR) | FAC | 07 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00146West elevation - Phase 6 PPC support projecting feature | DR - Drawing (DR) | FAC | 07 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00213South East core - PPC features | DR - Drawing (DR) | FAC | 07 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00143West elevation - Phase 6 PPC support framing for perforated | DR - Drawing (DR) | FAC | 14 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00232South West core - support work for PPC features | DR - Drawing (DR) | FAC | 21 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00234South West core - brickslip top hats | DR - Drawing (DR) | FAC | 21 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00203North East core - PPC features | DR - Drawing (DR) | FAC | 21 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00235South West core - brickslip omega rails | DR - Drawing (DR) | FAC | 21 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01082Parapet cill (west elevation lower roof) | DR - Drawing (DR) | FAC | 22 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00144West elevation - Phase 6 PPC panel marks | DR - Drawing (DR) | FAC | 22 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00147West elevation - Phase 6 PPC projecting feature panel marks | DR - Drawing (DR) | FAC | 22 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00145West elevation - Phase 6 PPC perforated panel marks | DR - Drawing (DR) | FAC | 22 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01081Parapet head (west elevation lower roof) | DR - Drawing (DR) | FAC | 22 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01059Louvre cill to capping | DR - Drawing (DR) | FAC | 22 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01061West core feature capping | DR - Drawing (DR) | FAC | 22 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01062Brickslip corner to louvre | DR - Drawing (DR) | FAC | 22 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01060Brickslip cill to capping | DR - Drawing (DR) | FAC | 22 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00122East elevation GL.G-J - Phase 5 PPC support framing for feature | DR - Drawing (DR) | FAC | 29 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00114East elevation GL.B-G - Phase 5 PPC panel marks | DR - Drawing (DR) | FAC | 29 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00115East elevation GL.B-G - Phase 5 PPC perforated panel marks | DR - Drawing (DR) | FAC | 29 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00153West elevation office - Phase 6 support framing for brick slip | DR - Drawing (DR) | FAC | 29 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00155West elevation office - Phase 6 brickslip marks | DR - Drawing (DR) | FAC | 29 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00112East elevation GL.B-G - Phase 5 PPC support framing for feature | DR - Drawing (DR) | FAC | 29 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00154West elevation office - Phase 6 PPC panel marks | DR - Drawing (DR) | FAC | 29 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00152West elevation office - Phase 6 support framing for PPC feature | DR - Drawing (DR) | FAC | 29 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00117East elevation GL.B-G - Phase 5 PPC projecting feature panel marks | DR - Drawing (DR) | FAC | 29 Aug 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00113East elevation GL.B-G - Phase 5 PPC support framing for perforated | DR - Drawing (DR) | FAC | 12 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00126East elevation GL.G-J - Phase 5 PPC support projecting feature | DR - Drawing (DR) | FAC | 12 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00222North West core - support work for PPC features | DR - Drawing (DR) | FAC | 12 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00116East elevation GL.B-G - Phase 5 PPC support projecting feature | DR - Drawing (DR) | FAC | 12 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00224North West core - brickslip top hats | DR - Drawing (DR) | FAC | 12 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00244West core - brickslip omega rails | DR - Drawing (DR) | FAC | 12 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00233South West core - PPC features | DR - Drawing (DR) | FAC | 12 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00243West core - brickslip top hats | DR - Drawing (DR) | FAC | 12 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00225North West core - brickslip omega rails | DR - Drawing (DR) | FAC | 12 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00241West core - support work for PPC features | DR - Drawing (DR) | FAC | 12 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01046Brickslip dock door jamb (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01052Feature capping (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01070Parapet cill (office roof) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01045Brickslip dock door head (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01051Brickslip feature/capping (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01057Feature internal corner to entrance (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01069Parapet head (office roof) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01047Feature vertical section (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01071Parapet internal corner (office roof) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01043Brickslip large door head (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01049Feature external corner (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01055Feature head to curtain wall cill (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01044Brickslip large door jamb (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01050Feature internal corner (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01056Brickslip jamb to curtain wall jamb (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01068Feature cill to parapet upstand (office roof) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01042Brickslip drip (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01048Feature horizontal section (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01054Feature drip (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01072Parapet to main building (office roof) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01053Brickslip/feature to curtain wall jamb (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01058Feature capping to curtain wall head (west office) | DR - Drawing (DR) | FAC | 19 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00123East elevation GL.G-J - Phase 5 PPC support framing for perforated | DR - Drawing (DR) | FAC | 29 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00124East elevation GL.G-J - Phase 5 PPC panel marks | DR - Drawing (DR) | FAC | 29 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00127East elevation GL.G-J - Phase 5 PPC projecting feature panel marks | DR - Drawing (DR) | FAC | 29 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00125East elevation GL.G-J - Phase 5 PPC perforated panel marks | DR - Drawing (DR) | FAC | 29 Sept 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01018Raking horizontal feature section | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01024Brickslip external corner at lower gantry | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01016Large digital feature horizontal section | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01022Brickslip to ground floor louvre jamb | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01028Digital feature head to window | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00223North West core - PPC features | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01015Digital feature drip | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01021Brickslip door jamb | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01027Digital feature jamb to window | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00245West core - brickslip | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01017Small digital feature horizontal section | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01023Brickslip internal corner to office | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01019Raking horizontal feature section | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01025Brickslip feature/capping | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01020Brickslip door head | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01026Digital feature cill to window | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00242West core - PPC features | DR - Drawing (DR) | FAC | 03 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00005Overall roof plan | DR - Drawing (DR) | FAC | 24 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00004West elevation - Overall elevation | DR - Drawing (DR) | FAC | 24 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00003East elevation - Overall elevation | DR - Drawing (DR) | FAC | 24 Oct 2025Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28266Connection No.: 28266 | CA - Calculations (CA) | STR | 31 Dec 2025 | 31 Dec 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28265Connection No.: 28265 | CA - Calculations (CA) | STR | 31 Dec 2025 | 31 Dec 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28265Connection No.: 28265 | CA - Calculations (CA) | STR | 31 Dec 2025 | 31 Dec 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28266Connection No.: 28266 | CA - Calculations (CA) | STR | 31 Dec 2025 | 31 Dec 2025Asite issue | C01 | AAccepted | 01 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28269Connection No.: 28269 | CA - Calculations (CA) | STR | 02 Jan 2026 | 02 Jan 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28268Connection No.: 28268 | CA - Calculations (CA) | STR | 02 Jan 2026 | 06 May 2026Asite issue | C02 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28269Connection No.: 28269 | CA - Calculations (CA) | STR | 02 Jan 2026 | 02 Jan 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28268Connection No.: 28268 | CA - Calculations (CA) | STR | 02 Jan 2026 | 06 May 2026Asite issue | C02 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00022Trade Contractor Weekly Report | RP - Report (RP) | STR | 07 Jan 2026 | 07 Jan 2026Asite issue | C01 | For InformationNo approval required | 07 Jan 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00022Trade Contractor Weekly Report | RP - Report (RP) | STR | 07 Jan 2026 | 07 Jan 2026Asite issue | C01 | For InformationNo approval required | 07 Jan 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00023Trade Contractor Weekly Report | RP - Report (RP) | STR | 13 Jan 2026 | 13 Jan 2026Asite issue | C01 | For InformationNo approval required | 13 Jan 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00023Trade Contractor Weekly Report | RP - Report (RP) | STR | 13 Jan 2026 | 13 Jan 2026Asite issue | C01 | For InformationNo approval required | 13 Jan 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00024Trade Contractor Weekly Report | RP - Report (RP) | STR | 19 Jan 2026 | 19 Jan 2026Asite issue | C01 | For InformationNo approval required | 20 Jan 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-15101Steelwork Plan @+8.940m (L01) - Phase 15 | DR - Drawing (DR) | STR | 19 Jan 2026 | 21 Jan 2026Asite issue | C02 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00024Trade Contractor Weekly Report | RP - Report (RP) | STR | 19 Jan 2026 | 19 Jan 2026Asite issue | C01 | For InformationNo approval required | 20 Jan 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-15101Steelwork Plan @+8.940m (L01) - Phase 15 | DR - Drawing (DR) | STR | 19 Jan 2026 | 21 Jan 2026Asite issue | C02 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99201Temporary Works - TW1-1 – Global Stability | TW - Temporary Works (TW) | STR | 21 Jan 2026 | 17 Mar 2026Asite issue | C02 | QA Accepted | 31 Mar 2026 | MCL For CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99208Design Pack: TW6-0 Edge Protection System | TW - Temporary Works (TW) | STR | 21 Jan 2026 | 17 Mar 2026Asite issue | C02 | AAccepted | 29 Apr 2026 | Design Team - Status ACOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99206Temporary Works – TW4-2 – MEWP and Loading Out on Deck Floors | TW - Temporary Works (TW) | STR | 21 Jan 2026 | 29 May 2026Asite issue | C04 | AAccepted | 18 Aug 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99201Temporary Works - TW1-1 – Global Stability | TW - Temporary Works (TW) | STR | 21 Jan 2026 | 17 Mar 2026Asite issue | C02 | QA Accepted | 31 Mar 2026 | MCL For CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99208Design Pack: TW6-0 Edge Protection System | TW - Temporary Works (TW) | STR | 21 Jan 2026 | 17 Mar 2026Asite issue | C02 | AAccepted | 29 Apr 2026 | Design Team - Status ACOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99206Temporary Works – TW4-2 – MEWP and Loading Out on Deck Floors | TW - Temporary Works (TW) | STR | 21 Jan 2026 | 29 May 2026Asite issue | C04 | AAccepted | 18 Aug 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00025Trade Contractor Weekly Report | RP - Report (RP) | STR | 27 Jan 2026 | 27 Jan 2026Asite issue | C01 | For InformationNo approval required | 27 Jan 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00025Trade Contractor Weekly Report | RP - Report (RP) | STR | 27 Jan 2026 | 27 Jan 2026Asite issue | C01 | For InformationNo approval required | 27 Jan 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00131East elevation lower building - Phase 5 panel elevation and wind loads | DR - Drawing (DR) | FAC | 02 Feb 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 27 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TS-S-00002Shop Weld Book | TS - Technical Submittals (TS) | STR | 03 Feb 2026 | 03 Feb 2026Asite issue | C01 | PendingAwaiting Design Review | 04 Feb 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TS-S-00003Site Weld Book | TS - Technical Submittals (TS) | STR | 03 Feb 2026 | 03 Feb 2026Asite issue | C01 | PendingAwaiting Design Review | 04 Feb 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00026Trade Contractor Weekly Report | RP - Report (RP) | STR | 03 Feb 2026 | 03 Feb 2026Asite issue | C01 | For InformationNo approval required | 03 Feb 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TS-S-00002Shop Weld Book | TS - Technical Submittals (TS) | STR | 03 Feb 2026 | 03 Feb 2026Asite issue | C01 | PendingAwaiting Design Review | 04 Feb 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TS-S-00003Site Weld Book | TS - Technical Submittals (TS) | STR | 03 Feb 2026 | 03 Feb 2026Asite issue | C01 | PendingAwaiting Design Review | 04 Feb 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00026Trade Contractor Weekly Report | RP - Report (RP) | STR | 03 Feb 2026 | 03 Feb 2026Asite issue | C01 | For InformationNo approval required | 03 Feb 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28131Connection No.: 28131 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29101Connection No.: 29101 | CA - Calculations (CA) | STR | 05 Feb 2026 | 19 Feb 2026Asite issue | C03 | AAccepted | 17 Apr 2026 | Awaiting Client ReviewCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28163Connection No.: 28163 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 07 Aug 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28105Connection No.: 28105 | CA - Calculations (CA) | STR | 05 Feb 2026 | 19 Feb 2026Asite issue | C03 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28152Connection No.: 28152 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28108Connection No.: 28108 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28103Connection No.: 28103 | CA - Calculations (CA) | STR | 05 Feb 2026 | 19 Feb 2026Asite issue | C04 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28170Connection No.: 28170 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 10 Jul 2026 | Status B - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28172Connection No.: 28172 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | BAccepted with comments | 07 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28173Connection No.: 28173 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | BAccepted with comments | 07 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28175Connection No.: 28175 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28176Connection No.: 28176 | CA - Calculations (CA) | STR | 05 Feb 2026 | 19 Feb 2026Asite issue | C04 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28178Connection No.: 28178 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28116Connection No.: 28116 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28213Connection No.: 28213 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 14 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29139Connection No.: 29139 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28215Connection No.: 28215 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | BAccepted with comments | 07 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29172Connection No.: 29172 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29173Connection No.: 29173 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28220Connection No.: 28220 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | BAccepted with comments | 07 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29200Connection No.: 29200 | CA - Calculations (CA) | STR | 05 Feb 2026 | 19 Feb 2026Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29140Connection No.: 29140 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29201Connection No.: 29201 | CA - Calculations (CA) | STR | 05 Feb 2026 | 19 Feb 2026Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28217Connection No.: 28217 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 14 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29197Connection No.: 29197 | CA - Calculations (CA) | STR | 05 Feb 2026 | 19 Feb 2026Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29198Connection No.: 29198 | CA - Calculations (CA) | STR | 05 Feb 2026 | 19 Feb 2026Asite issue | C01 | AAccepted | 15 Jul 2026 | Status B - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29199Connection No.: 29199 | CA - Calculations (CA) | STR | 05 Feb 2026 | 19 Feb 2026Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29202Connection No.: 29202 | CA - Calculations (CA) | STR | 05 Feb 2026 | 19 Feb 2026Asite issue | C01 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28131Connection No.: 28131 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29101Connection No.: 29101 | CA - Calculations (CA) | STR | 05 Feb 2026 | 19 Feb 2026Asite issue | C03 | AAccepted | 17 Apr 2026 | Awaiting Client ReviewCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28163Connection No.: 28163 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 07 Aug 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28105Connection No.: 28105 | CA - Calculations (CA) | STR | 05 Feb 2026 | 19 Feb 2026Asite issue | C03 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28152Connection No.: 28152 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28103Connection No.: 28103 | CA - Calculations (CA) | STR | 05 Feb 2026 | 19 Feb 2026Asite issue | C04 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28108Connection No.: 28108 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28170Connection No.: 28170 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 10 Jul 2026 | Status B - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28116Connection No.: 28116 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28173Connection No.: 28173 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | BAccepted with comments | 07 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28176Connection No.: 28176 | CA - Calculations (CA) | STR | 05 Feb 2026 | 19 Feb 2026Asite issue | C04 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28178Connection No.: 28178 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28175Connection No.: 28175 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28172Connection No.: 28172 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | BAccepted with comments | 07 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29139Connection No.: 29139 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29140Connection No.: 29140 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28215Connection No.: 28215 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | BAccepted with comments | 07 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28217Connection No.: 28217 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 14 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28213Connection No.: 28213 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 14 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28220Connection No.: 28220 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | BAccepted with comments | 07 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29173Connection No.: 29173 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29172Connection No.: 29172 | CA - Calculations (CA) | STR | 05 Feb 2026 | 18 Feb 2026Asite issue | C02 | AAccepted | 24 Apr 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-34012Steelwork Elevation on GL 10 Lvl 0 to 4 (South) | DR - Drawing (DR) | STR | 09 Feb 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-34014Steelwork Elevation on GL 11 Lvl 0 to 4 (South) | DR - Drawing (DR) | STR | 09 Feb 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00027Trade Contractor Weekly Report | RP - Report (RP) | STR | 09 Feb 2026 | 09 Feb 2026Asite issue | C01 | For InformationNo approval required | 10 Feb 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-91022MTO Steelwork Plan @+19.940m(L03) - Phases 17 to 22 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 22 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-91023MTO Steelwork Plan @+26.440m(L04) - Phases 17 to 22 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 22 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91025MTO Steelwork Elevation on GL A (GL 18 to 22) Phase 17 to 22 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 22 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-91020MTO Steelwork Plan @+8.940m(L01) - Phases 17 to 22 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 15 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91026MTO Steelwork Elevation on GL K (GL 18 to 22) Phase 17 to 22 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 22 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-91021MTO Steelwork Plan @+13.440m(L02) - Phases 17 to 22 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 22 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-91024MTO Steelwork Plan @+32.940m(L05) - Phases 17 to 22 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 22 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-91130MTO Steelwork Plan @+39.440m(L06) - Phases 57 to 62 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 02 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-91131MTO Steelwork Plan @+45.780m(R01) - Phases 57 to 62 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 30 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-91151MTO Steelwork Plan @+45.940m (R01) - Phases 71 to 76 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 30 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-91150MTO Steelwork Plan @+39.440m (L06) - Phases 71 to 76 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 02 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-34012Steelwork Elevation on GL 10 Lvl 0 to 4 (South) | DR - Drawing (DR) | STR | 09 Feb 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-34014Steelwork Elevation on GL 11 Lvl 0 to 4 (South) | DR - Drawing (DR) | STR | 09 Feb 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00027Trade Contractor Weekly Report | RP - Report (RP) | STR | 09 Feb 2026 | 09 Feb 2026Asite issue | C01 | For InformationNo approval required | 10 Feb 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-91022MTO Steelwork Plan @+19.940m(L03) - Phases 17 to 22 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 22 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-91021MTO Steelwork Plan @+13.440m(L02) - Phases 17 to 22 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 22 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-91023MTO Steelwork Plan @+26.440m(L04) - Phases 17 to 22 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 22 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-91150MTO Steelwork Plan @+39.440m (L06) - Phases 71 to 76 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 02 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-91151MTO Steelwork Plan @+45.940m (R01) - Phases 71 to 76 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 30 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-91130MTO Steelwork Plan @+39.440m(L06) - Phases 57 to 62 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 02 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-91131MTO Steelwork Plan @+45.780m(R01) - Phases 57 to 62 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 30 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-91024MTO Steelwork Plan @+32.940m(L05) - Phases 17 to 22 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 22 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91025MTO Steelwork Elevation on GL A (GL 18 to 22) Phase 17 to 22 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 22 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-91020MTO Steelwork Plan @+8.940m(L01) - Phases 17 to 22 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 15 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91026MTO Steelwork Elevation on GL K (GL 18 to 22) Phase 17 to 22 | DR - Drawing (DR) | STR | 09 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 22 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-IP-X-00001Quality Inspection & Test Plan-Manufacture | IP - Inspection and Test Plan (IP) | STR | 10 Feb 2026 | 10 Feb 2026Asite issue | C01 | For InformationNo approval required | 09 Mar 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-IP-X-00001Quality Inspection & Test Plan-Manufacture | IP - Inspection and Test Plan (IP) | STR | 10 Feb 2026 | 10 Feb 2026Asite issue | C01 | For InformationNo approval required | 09 Mar 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28115Connection No.:28115 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28119Connection No.:28119 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29110Connection No.:29110 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28107Connection No.:28107 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29104Connection No.:29104 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28108Connection No.:28108 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29105Connection No.:29105 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28100Connection No.:28100 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28105Connection No.:28105 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28106Connection No.:28106 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28109Connection No.:28109 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28112Connection No.:28112 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29102Connection No.:29102 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | WithdrawnWithdrawn | 29 Apr 2026 | WithdrawnCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28110Connection No.:28110 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28118Connection No.:28118 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29100Connection No.:29100 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29204Connection No.:29204 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28120Connection No.:28120 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29103Connection No.:29103 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | WithdrawnWithdrawn | 29 Apr 2026 | WithdrawnCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28107Connection No.:28107 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29104Connection No.:29104 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28106Connection No.:28106 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28108Connection No.:28108 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29105Connection No.:29105 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28119Connection No.:28119 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29110Connection No.:29110 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28115Connection No.:28115 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29103Connection No.:29103 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | WithdrawnWithdrawn | 29 Apr 2026 | WithdrawnCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28110Connection No.:28110 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28118Connection No.:28118 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29100Connection No.:29100 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29204Connection No.:29204 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 24 Apr 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28120Connection No.:28120 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28109Connection No.:28109 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28112Connection No.:28112 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29102Connection No.:29102 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | WithdrawnWithdrawn | 29 Apr 2026 | WithdrawnCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28100Connection No.:28100 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28105Connection No.:28105 | CA - Calculations (CA) | STR | 12 Feb 2026 | 13 Feb 2026Asite issue | C01 | AAccepted | 01 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-40031Steelwork Foundation Details - Sheet 1 | DR - Drawing (DR) | STR | 16 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-40033Steelwork Foundation Details - Sheet 3 | DR - Drawing (DR) | STR | 16 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-40032Steelwork Foundation Details - Sheet 2 | DR - Drawing (DR) | STR | 16 Feb 2026 | 18 Feb 2026Asite issue | C01 | AAccepted | 09 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-IP-X-00002Quality Inspection & Test Plan-Construction | IP - Inspection and Test Plan (IP) | STR | 17 Feb 2026 | 17 Feb 2026Asite issue | C01 | For InformationNo approval required | 09 Mar 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-IP-X-00002Quality Inspection & Test Plan-Construction | IP - Inspection and Test Plan (IP) | STR | 17 Feb 2026 | 17 Feb 2026Asite issue | C01 | For InformationNo approval required | 09 Mar 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00028Trade Contractor Weekly Report | RP - Report (RP) | STR | 18 Feb 2026 | 18 Feb 2026Asite issue | C01 | For InformationNo approval required | 20 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00028Trade Contractor Weekly Report | RP - Report (RP) | STR | 18 Feb 2026 | 18 Feb 2026Asite issue | C01 | For InformationNo approval required | 20 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00029Trade Contractor Weekly Report | RP - Report (RP) | STR | 24 Feb 2026 | 24 Feb 2026Asite issue | C01 | For InformationNo approval required | 25 Feb 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00029Trade Contractor Weekly Report | RP - Report (RP) | STR | 24 Feb 2026 | 24 Feb 2026Asite issue | C01 | For InformationNo approval required | 25 Feb 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00018Grid 07, Along F & G, Tolerance Steel Lug Setting Out | DR - Drawing (DR) | FAC | 27 Feb 2026 | 22 May 2026Asite issue | P01 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00017Grids 06 & 08, Along F & G, Tolerance Steel Lug Setting Out | DR - Drawing (DR) | FAC | 27 Feb 2026 | 22 May 2026Asite issue | P01 | BAccepted with comments | 19 Jun 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00019Grids 23-24, Along F & G, Tolerance Steel Lug Details | DR - Drawing (DR) | FAC | 27 Feb 2026 | 05 Jun 2026Asite issue | P02 | BAccepted with comments | 10 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00016Grids 06 & 08, Along F & G, Tolerance Steel Lug Details | DR - Drawing (DR) | FAC | 27 Feb 2026 | 05 Jun 2026Asite issue | P02 | BAccepted with comments | 10 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29000Connection No.:29000 | CA - Calculations (CA) | STR | 27 Feb 2026 | 27 Feb 2026Asite issue | C01 | AAccepted | 07 Apr 2026 | Status A - CMTCANCELLED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29000Connection No.:29000 | CA - Calculations (CA) | STR | 27 Feb 2026 | 27 Feb 2026Asite issue | C01 | AAccepted | 07 Apr 2026 | Status A - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-CA-X-00003TYPICAL KROC KARRIER SUPPORT RAIL & CONNECTIONS | CA - Calculations (CA) | FAC | 02 Mar 2026 | 02 Mar 2026Asite issue | P02 | AAccepted | 14 May 2026 | Status B - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00030Trade Contractor Weekly Report | RP - Report (RP) | STR | 02 Mar 2026 | 02 Mar 2026Asite issue | C01 | For InformationNo approval required | 03 Mar 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00030Trade Contractor Weekly Report | RP - Report (RP) | STR | 02 Mar 2026 | 02 Mar 2026Asite issue | C01 | For InformationNo approval required | 03 Mar 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00031Trade Contractor Weekly Report | RP - Report (RP) | STR | 09 Mar 2026 | 09 Mar 2026Asite issue | C01 | For InformationNo approval required | 10 Mar 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00031Trade Contractor Weekly Report | RP - Report (RP) | STR | 09 Mar 2026 | 09 Mar 2026Asite issue | C01 | For InformationNo approval required | 10 Mar 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TS-S-00004Paint Systems Technical Submittal | TS - Technical Submittals (TS) | STR | 13 Mar 2026 | 04 Jun 2026Asite issue | C02 | AAccepted | 10 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TS-S-00004Paint Systems Technical Submittal | TS - Technical Submittals (TS) | STR | 13 Mar 2026 | 04 Jun 2026Asite issue | C02 | AAccepted | 10 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00032Trade Contractor Weekly Report | RP - Report (RP) | STR | 17 Mar 2026 | 17 Mar 2026Asite issue | C01 | For InformationNo approval required | 17 Mar 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00032Trade Contractor Weekly Report | RP - Report (RP) | STR | 17 Mar 2026 | 17 Mar 2026Asite issue | C01 | For InformationNo approval required | 17 Mar 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02110DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - GL 23 TO 25 ALONG GL A | DR - Drawing (DR) | FAC | 19 Mar 2026 | 19 Mar 2026Asite issue | P01 | AAccepted | 12 Aug 2026 | Status A - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02113DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - GL B TO J ALONG GL 26 | DR - Drawing (DR) | FAC | 19 Mar 2026 | 19 Mar 2026Asite issue | P01 | AAccepted | 12 Aug 2026 | Status A - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02111DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - GL A TO B ALONG GL 25 | DR - Drawing (DR) | FAC | 19 Mar 2026 | 19 Mar 2026Asite issue | P01 | AAccepted | 12 Aug 2026 | Status A - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02114DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - GL J TO K ALONG GL 25 | DR - Drawing (DR) | FAC | 19 Mar 2026 | 19 Mar 2026Asite issue | P01 | AAccepted | 12 Aug 2026 | Status A - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02112DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - GL 25 TO 26 ALONG GL B | DR - Drawing (DR) | FAC | 19 Mar 2026 | 19 Mar 2026Asite issue | P01 | AAccepted | 12 May 2026 | Status A - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02124DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - EAST PLAN LEVEL G2 | DR - Drawing (DR) | FAC | 19 Mar 2026 | 19 Mar 2026Asite issue | P01 | AAccepted | 14 May 2026 | Status B - CMTCANCELLED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02117DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - EAST PLAN LEVEL 01 | DR - Drawing (DR) | FAC | 19 Mar 2026 | 19 Mar 2026Asite issue | P01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02123DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - EAST PLAN LEVEL G1 | DR - Drawing (DR) | FAC | 19 Mar 2026 | 19 Mar 2026Asite issue | P01 | BAccepted with comments | 12 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02119DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - EAST PLAN LEVEL 03 | DR - Drawing (DR) | FAC | 19 Mar 2026 | 19 Mar 2026Asite issue | P01 | BAccepted with comments | 27 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02121DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - EAST PLAN LEVEL 05 | DR - Drawing (DR) | FAC | 19 Mar 2026 | 19 Mar 2026Asite issue | P01 | BAccepted with comments | 27 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02116DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - EAST PLAN LEVEL 00 | DR - Drawing (DR) | FAC | 19 Mar 2026 | 19 Mar 2026Asite issue | P01 | BAccepted with comments | 28 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02122DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - EAST PLAN LEVEL 06 | DR - Drawing (DR) | FAC | 19 Mar 2026 | 19 Mar 2026Asite issue | P01 | BAccepted with comments | 27 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02118DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - EAST PLAN LEVEL 02 | DR - Drawing (DR) | FAC | 19 Mar 2026 | 19 Mar 2026Asite issue | P01 | BAccepted with comments | 27 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02115DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - GL 25 TO 23 ALONG GL K | DR - Drawing (DR) | FAC | 19 Mar 2026 | 19 Mar 2026Asite issue | P01 | AAccepted | 27 Aug 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02120DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - EAST PLAN LEVEL 04 | DR - Drawing (DR) | FAC | 19 Mar 2026 | 19 Mar 2026Asite issue | P01 | BAccepted with comments | 27 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00033Trade Contractor Weekly Report | RP - Report (RP) | STR | 23 Mar 2026 | 23 Mar 2026Asite issue | C01 | For InformationNo approval required | 24 Mar 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00033Trade Contractor Weekly Report | RP - Report (RP) | STR | 23 Mar 2026 | 23 Mar 2026Asite issue | C01 | For InformationNo approval required | 24 Mar 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-30001Steelwork Plan Early Columns - Phase 30 | DR - Drawing (DR) | STR | 27 Mar 2026 | 27 Mar 2026Asite issue | C01 | AAccepted | 28 Jul 2026 | MCL Final Status,Notify WHL of MCL Design Team CommentsRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00039East Elevation Lug Setting 10 | DR - Drawing (DR) | FAC | 30 Mar 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00033East Elevation Lug Setting 4 | DR - Drawing (DR) | FAC | 30 Mar 2026 | 05 Jun 2026Asite issue | P01 | AAccepted | 10 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00037East Elevation Lug Setting 8 | DR - Drawing (DR) | FAC | 30 Mar 2026 | 05 Jun 2026Asite issue | P01 | AAccepted | 10 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00032East Elevation Lug Setting 3 | DR - Drawing (DR) | FAC | 30 Mar 2026 | 05 Jun 2026Asite issue | P01 | AAccepted | 10 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00034East Elevation Lug Setting 5 | DR - Drawing (DR) | FAC | 30 Mar 2026 | 05 Jun 2026Asite issue | P01 | AAccepted | 10 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00035East Elevation Lug Setting 6 | DR - Drawing (DR) | FAC | 30 Mar 2026 | 05 Jun 2026Asite issue | P01 | AAccepted | 10 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00036East Elevation Lug Setting 7 | DR - Drawing (DR) | FAC | 30 Mar 2026 | 05 Jun 2026Asite issue | P01 | BAccepted with comments | 26 Jun 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00038East Elevation Lug Setting 9 | DR - Drawing (DR) | FAC | 30 Mar 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00034Trade Contractor Weekly Report | RP - Report (RP) | STR | 30 Mar 2026 | 30 Mar 2026Asite issue | C01 | For InformationNo approval required | 31 Mar 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00034Trade Contractor Weekly Report | RP - Report (RP) | STR | 30 Mar 2026 | 30 Mar 2026Asite issue | C01 | For InformationNo approval required | 31 Mar 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-91080Olympus - LCY11 22032 - GL 06 - 10 - Phase 37 to 42 MTO Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 30 Mar 2026 | 30 Mar 2026Asite issue | C01 | BAccepted with comments | 18 May 2026 | Status B (Accepted with Comments)CANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-91081Olympus - LCY11 22032 - GL 06 - 10 - Phase 37 to 42 MTO Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 30 Mar 2026 | 30 Mar 2026Asite issue | C01 | BAccepted with comments | 18 May 2026 | Status B (Accepted with Comments)CANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-91160Olympus - LCY11 22032 - GL 06 - 10 - Phase 77 to 82 MTO Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 30 Mar 2026 | 30 Mar 2026Asite issue | C01 | BAccepted with comments | 08 Apr 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-91082Olympus - LCY11 22032 - GL 06 - 10 - Phase 37 to 42 MTO Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 30 Mar 2026 | 30 Mar 2026Asite issue | C01 | BAccepted with comments | 21 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91162Olympus - LCY11 22032 - GL 06 - 10 - Phase 77 to 82 Steelwork Elevation on GL 06 | DR - Drawing (DR) | STR | 30 Mar 2026 | 30 Mar 2026Asite issue | C01 | AAccepted | 07 Aug 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-91083Olympus - LCY11 22032 - GL 06 - 10 - Phase 37 to 42 MTO Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 30 Mar 2026 | 30 Mar 2026Asite issue | C01 | BAccepted with comments | 21 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91089Olympus - LCY11 22032 - GL 06 - 10 - Phase 37 to 42 Steelwork Elevation on GL 06 | DR - Drawing (DR) | STR | 30 Mar 2026 | 30 Mar 2026Asite issue | C01 | BAccepted with comments | 07 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91088Olympus - LCY11 22032 - GL 06 - 10 - Phase 37 to 42 Steelwork Elevation on GL 08 | DR - Drawing (DR) | STR | 30 Mar 2026 | 30 Mar 2026Asite issue | C01 | BAccepted with comments | 07 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91086Olympus - LCY11 22032 - GL 06 - 10 - Phase 37 to 42 Steelwork Elevation on GL K | DR - Drawing (DR) | STR | 30 Mar 2026 | 30 Mar 2026Asite issue | C01 | BAccepted with comments | 07 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91087Olympus - LCY11 22032 - GL 06 - 10 - Phase 37 to 42 Secondary Steelwork Elevation on GL F & G | DR - Drawing (DR) | STR | 30 Mar 2026 | 30 Mar 2026Asite issue | C01 | WithdrawnWithdrawn | 26 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-91161Olympus - LCY11 22032 - GL 06 - 10 - Phase 77 to 82 MTO Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 30 Mar 2026 | 30 Mar 2026Asite issue | C01 | BAccepted with comments | 08 Apr 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91085Olympus - LCY11 22032 - GL 06 - 10 - Phase 37 to 42 Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 30 Mar 2026 | 30 Mar 2026Asite issue | C01 | BAccepted with comments | 07 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-91084Olympus - LCY11 22032 - GL 06 - 10 - Phase 37 to 42 MTO Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 30 Mar 2026 | 30 Mar 2026Asite issue | C01 | BAccepted with comments | 21 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02131DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - GL B TO A ALONG GL 4 | DR - Drawing (DR) | FAC | 31 Mar 2026 | 31 Mar 2026Asite issue | P01 | AAccepted | 11 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02134DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - WEST PLAN LEVEL 00 | DR - Drawing (DR) | FAC | 31 Mar 2026 | 31 Mar 2026Asite issue | P01 | AAccepted | 11 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02137DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - WEST PLAN LEVEL 03 | DR - Drawing (DR) | FAC | 31 Mar 2026 | 31 Mar 2026Asite issue | P01 | AAccepted | 11 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02140DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - WEST PLAN LEVEL 06 | DR - Drawing (DR) | FAC | 31 Mar 2026 | 31 Mar 2026Asite issue | P01 | AAccepted | 11 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02130DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - GL 4 TO 6 ALONG GL A | DR - Drawing (DR) | FAC | 31 Mar 2026 | 31 Mar 2026Asite issue | P01 | AAccepted | 11 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02132DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - GL 7 TO 4 ALONG GL K | DR - Drawing (DR) | FAC | 31 Mar 2026 | 31 Mar 2026Asite issue | P01 | AAccepted | 11 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02133DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - GL K TO J ALONG GL 4 | DR - Drawing (DR) | FAC | 31 Mar 2026 | 31 Mar 2026Asite issue | P01 | AAccepted | 11 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02135DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - WEST PLAN LEVEL 01 | DR - Drawing (DR) | FAC | 31 Mar 2026 | 31 Mar 2026Asite issue | P01 | AAccepted | 11 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02136DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - WEST PLAN LEVEL 02 | DR - Drawing (DR) | FAC | 31 Mar 2026 | 31 Mar 2026Asite issue | P01 | AAccepted | 11 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02138DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - WEST PLAN LEVEL 04 | DR - Drawing (DR) | FAC | 31 Mar 2026 | 31 Mar 2026Asite issue | P01 | AAccepted | 11 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02139DIGITAL LINE STEELWORK SETTING OUT REQUIREMENTS - WEST PLAN LEVEL 05 | DR - Drawing (DR) | FAC | 31 Mar 2026 | 31 Mar 2026Asite issue | P01 | AAccepted | 11 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28289Connection No.: 28289 | CA - Calculations (CA) | STR | 02 Apr 2026 | 02 Apr 2026Asite issue | C01 | AAccepted | 22 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28288Connection No.: 28288 | CA - Calculations (CA) | STR | 02 Apr 2026 | 02 Apr 2026Asite issue | C01 | AAccepted | 22 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28286Connection No.: 28286 | CA - Calculations (CA) | STR | 02 Apr 2026 | 02 Apr 2026Asite issue | C01 | AAccepted | 22 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28287Connection No.: 28287 | CA - Calculations (CA) | STR | 02 Apr 2026 | 02 Apr 2026Asite issue | C01 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28291Connection No.: 28291 | CA - Calculations (CA) | STR | 02 Apr 2026 | 02 Apr 2026Asite issue | C01 | AAccepted | 22 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00035Trade Contractor Weekly Report | RP - Report (RP) | STR | 07 Apr 2026 | 07 Apr 2026Asite issue | C01 | For InformationNo approval required | 08 Apr 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00035Trade Contractor Weekly Report | RP - Report (RP) | STR | 07 Apr 2026 | 07 Apr 2026Asite issue | C01 | For InformationNo approval required | 08 Apr 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29210Connection No.: 29210 | CA - Calculations (CA) | STR | 07 Apr 2026 | 07 Apr 2026Asite issue | C01 | AAccepted | 22 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28279Connection No.: 28279 | CA - Calculations (CA) | STR | 07 Apr 2026 | 07 Apr 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-01-DR-X-02144STEELWORK SETTING OUT REQUIREMENTS - WEST PLAN LEVEL 01 - OFFICE BUILDING | DR - Drawing (DR) | FAC | 09 Apr 2026 | 09 Apr 2026Asite issue | P01 | AAccepted | 04 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-04-DR-X-02147STEELWORK SETTING OUT REQUIREMENTS - WEST PLAN LEVEL 04 - OFFICE BUILDING | DR - Drawing (DR) | FAC | 09 Apr 2026 | 09 Apr 2026Asite issue | P01 | AAccepted | 04 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-00-DR-X-02143STEELWORK SETTING OUT REQUIREMENTS - WEST PLAN LEVEL 00 - OFFICE BUILDING | DR - Drawing (DR) | FAC | 09 Apr 2026 | 09 Apr 2026Asite issue | P01 | AAccepted | 04 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-02-DR-X-02145STEELWORK SETTING OUT REQUIREMENTS - WEST PLAN LEVEL 02 - OFFICE BUILDING | DR - Drawing (DR) | FAC | 09 Apr 2026 | 09 Apr 2026Asite issue | P01 | AAccepted | 04 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-03-DR-X-02146STEELWORK SETTING OUT REQUIREMENTS - WEST PLAN LEVEL 03 - OFFICE BUILDING | DR - Drawing (DR) | FAC | 09 Apr 2026 | 09 Apr 2026Asite issue | P01 | AAccepted | 04 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00036Trade Contractor Weekly Report | RP - Report (RP) | STR | 13 Apr 2026 | 13 Apr 2026Asite issue | C01 | For InformationNo approval required | 14 Apr 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00036Trade Contractor Weekly Report | RP - Report (RP) | STR | 13 Apr 2026 | 13 Apr 2026Asite issue | C01 | For InformationNo approval required | 14 Apr 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02170Built-Up Steelwork Setting Out Requirements - Stair 03 North East | DR - Drawing (DR) | FAC | 14 Apr 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02192Built-Up Steelwork Setting Out Requirements - External Flue Elevation 3 | DR - Drawing (DR) | FAC | 14 Apr 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02175Built-Up Steelwork Setting Out Requirements - Stair 04 North West | DR - Drawing (DR) | FAC | 14 Apr 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02193Built-Up Steelwork Setting Out Requirements - External Flue Elevation 4 | DR - Drawing (DR) | FAC | 14 Apr 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02180Built-Up Steelwork Setting Out Requirements - Lift Core North, East & South | DR - Drawing (DR) | FAC | 14 Apr 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02160Built-Up Steelwork Setting Out Requirements - Stair 01 South West | DR - Drawing (DR) | FAC | 14 Apr 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02190Built-Up Steelwork Setting Out Requirements - External Flue Elevation 1 | DR - Drawing (DR) | FAC | 14 Apr 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02181Built-Up Steelwork Setting Out Requirements - Lift Core West | DR - Drawing (DR) | FAC | 14 Apr 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02165Built-Up Steelwork Setting Out Requirements - Stair 02 South East | DR - Drawing (DR) | FAC | 14 Apr 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02191Built-Up Steelwork Setting Out Requirements - External Flue Elevation 2 | DR - Drawing (DR) | FAC | 14 Apr 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02141Digital Line Steelwork Setting Out Requirements - West Plan Level G1 | DR - Drawing (DR) | FAC | 14 Apr 2026Planned placeholder | —Not issued | P01 | AAccepted | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02142Digital Line Steelwork Setting Out Requirements - West Plan Level G2 | DR - Drawing (DR) | FAC | 14 Apr 2026Planned placeholder | —Not issued | P01 | AAccepted | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-02148Steelwork Setting Out Requirements - West Curtain Wall Elevation | DR - Drawing (DR) | FAC | 14 Apr 2026Planned placeholder | —Not issued | P01 | AAccepted | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99204Design Pack: TW4-0 MEWP Frames System | TW - Temporary Works (TW) | STR | 14 Apr 2026 | 14 Apr 2026Asite issue | C02 | AAccepted | 21 Jul 2026 | MCL For CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99209Temporary Works - TW7-1 - Edge Protection Beam Checks | TW - Temporary Works (TW) | STR | 14 Apr 2026 | 14 Apr 2026Asite issue | C03 | AAccepted | 29 Apr 2026 | MCL For CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99203Design Pack: TW3-0 Trailer edge protection system | TW - Temporary Works (TW) | STR | 14 Apr 2026 | 14 Apr 2026Asite issue | C02 | AAccepted | 21 Jul 2026 | MCL For CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99209Temporary Works - TW7-1 - Edge Protection Beam Checks | TW - Temporary Works (TW) | STR | 14 Apr 2026 | 14 Apr 2026Asite issue | C03 | AAccepted | 29 Apr 2026 | MCL For CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99203Design Pack: TW3-0 Trailer edge protection system | TW - Temporary Works (TW) | STR | 14 Apr 2026 | 14 Apr 2026Asite issue | C02 | AAccepted | 21 Jul 2026 | MCL For CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99204Design Pack: TW4-0 MEWP Frames System | TW - Temporary Works (TW) | STR | 14 Apr 2026 | 14 Apr 2026Asite issue | C02 | AAccepted | 21 Jul 2026 | MCL For CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-IM-S-00001WHL BIM submission plan - Explanatory notes | IM - Information Management (IM) | STR | 14 Apr 2026 | 14 Apr 2026Asite issue | P01 | For InformationNo approval required | 22 Jul 2026 | For InformationCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00037Trade Contractor Weekly Report | RP - Report (RP) | STR | 20 Apr 2026 | 20 Apr 2026Asite issue | C01 | For InformationNo approval required | 22 Apr 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00037Trade Contractor Weekly Report | RP - Report (RP) | STR | 20 Apr 2026 | 20 Apr 2026Asite issue | C01 | For InformationNo approval required | 22 Apr 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-CA-X-00004EAST K-ROC SUBSTRUCTURE REPORT | CA - Calculations (CA) | FAC | 23 Apr 2026 | 23 Apr 2026Asite issue | P01 | AAccepted | 21 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-92002Risersafe Level 5 Grid 12-16 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 24 Apr 2026 | 24 Apr 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-92002Risersafe Level 4 Grid 12-16 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 24 Apr 2026 | 24 Apr 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-92001Risersafe Level 3 Grid 12-16 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 24 Apr 2026 | 24 Apr 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-92001Risersafe Level 4 Grid 12-16 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 24 Apr 2026 | 24 Apr 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-92001Risersafe Level 2 Grid 12-16 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 24 Apr 2026 | 24 Apr 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-92002Risersafe Level 3 Grid 12-16 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 24 Apr 2026 | 24 Apr 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-92000Risersafe Level 5 Grid 12-16 General Arrangement | DR - Drawing (DR) | STR | 24 Apr 2026 | 24 Apr 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-92001Risersafe Level 5 Grid 12-16 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 24 Apr 2026 | 24 Apr 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92001Risersafe Level 6 Grid 12-16 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 24 Apr 2026 | 24 Apr 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-92000Risersafe Level 3 Grid 12-16 General Arrangement | DR - Drawing (DR) | STR | 24 Apr 2026 | 24 Apr 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-92000Risersafe Level 2 Grid 12-16 General Arrangement | DR - Drawing (DR) | STR | 24 Apr 2026 | 24 Apr 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92000Risersafe Level 6 Grid 12-16 General Arrangement | DR - Drawing (DR) | STR | 24 Apr 2026 | 24 Apr 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92002Risersafe Level 6 Grid 12-16 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 24 Apr 2026 | 24 Apr 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-92000Risersafe Level 4 Grid 12-16 General Arrangement | DR - Drawing (DR) | STR | 24 Apr 2026 | 24 Apr 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-TW-S-99201Temporary Works – TW01-01 – Temporary Global Stability | TW - Temporary Works (TW) | STR | 25 Apr 2026 | 25 Apr 2026Asite issue | C01 | Awaiting MCL Review | 05 Aug 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00025TATA TRISOBUILD HW - BUILT-UP SYSTEM | TS - Technical Submittals (TS) | FAC | 27 Apr 2026 | 27 Apr 2026Asite issue | P01 | BAccepted with comments | 14 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00038Trade Contractor Weekly Report | RP - Report (RP) | STR | 28 Apr 2026 | 28 Apr 2026Asite issue | C01 | For InformationNo approval required | 29 Apr 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00038Trade Contractor Weekly Report | RP - Report (RP) | STR | 28 Apr 2026 | 28 Apr 2026Asite issue | C01 | For InformationNo approval required | 29 Apr 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-11040Metal Decking General Notes | DR - Drawing (DR) | STR | 28 Apr 2026 | 28 Apr 2026Asite issue | C02 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00068West Elevation Lug Setting 9 | DR - Drawing (DR) | FAC | 30 Apr 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00069West Elevation Lug Setting 10 | DR - Drawing (DR) | FAC | 30 Apr 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00063West Elevation Lug Setting 4 | DR - Drawing (DR) | FAC | 30 Apr 2026 | 05 Jun 2026Asite issue | P01 | AAccepted | 10 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00064West Elevation Lug Setting 5 | DR - Drawing (DR) | FAC | 30 Apr 2026 | 05 Jun 2026Asite issue | P01 | AAccepted | 10 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00065West Elevation Lug Setting 6 | DR - Drawing (DR) | FAC | 30 Apr 2026 | 05 Jun 2026Asite issue | P01 | AAccepted | 10 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00066West Elevation Lug Setting 7 | DR - Drawing (DR) | FAC | 30 Apr 2026 | 05 Jun 2026Asite issue | P01 | AAccepted | 10 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00067West Elevation Lug Setting 8 | DR - Drawing (DR) | FAC | 30 Apr 2026 | 05 Jun 2026Asite issue | P01 | AAccepted | 15 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00062West Elevation Lug Setting 3 | DR - Drawing (DR) | FAC | 30 Apr 2026 | 05 Jun 2026Asite issue | P01 | BAccepted with comments | 26 Jun 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-DR-S-91517Olympus - LCY18 22035-GL 22 -28 - Phase 13 MTO Steelwork Elevation on GL B | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | BAccepted with comments | 14 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-DR-S-91515Olympus - LCY18 22035-GL 13 - 22 - Phase 11 MTO Steelwork Elevation on GL B | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | BAccepted with comments | 14 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-R1-DR-S-91507Olympus - LCY18 22035-GL 22 -28 - Phase 13 MTO Steelwork Plan on Roof Level | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | AAccepted | 27 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-00-DR-S-91501Olympus - LCY18 22035-GL 13 - 22 - Phase 11 MTO Steelwork Plan on Ground Floor | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | AAccepted | 26 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-DR-S-91521Olympus - LCY18 22035-GL 01 - 06 - Phase 11 MTO Steelwork Elevation on GL 01 | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | AAccepted | 26 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-00-DR-S-91504Olympus - LCY18 22035-GL 01 - 06 - Phase 14 MTO Steelwork Plan on Ground Floor | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-00-DR-S-91503Olympus - LCY18 22035-GL 22 -28 - Phase 13 MTO Steelwork Plan on Ground Floor | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-DR-S-91511Olympus - LCY18 22035-GL 13 - 22 - Phase 11 MTO Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-DR-S-91512Olympus - LCY18 22035-GL 06 -13 - Phase 12 MTO Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-DR-S-91518Olympus - LCY18 22035-GL 01 - 06 - Phase 14 MTO Steelwork Elevation on GL B | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | BAccepted with comments | 14 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-DR-S-91522Olympus - LCY18 22035-GL 22 - 28 - Phase 14 MTO Steelwork Elevation on GL 28 | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | BAccepted with comments | 14 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-DR-S-91516Olympus - LCY18 22035-GL 06 -13 - Phase 12 MTO Steelwork Elevation on GL B | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | BAccepted with comments | 14 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-DR-S-91514Olympus - LCY18 22035-GL 01 - 06 - Phase 14 MTO Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-R1-DR-S-91508Olympus - LCY18 22035-GL 01 - 06 - Phase 14 MTO Steelwork Plan on Roof Level | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | AAccepted | 27 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-R1-DR-S-91506Olympus - LCY18 22035-GL 06 -13 - Phase 12 MTO Steelwork Plan on Roof Level | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-R1-DR-S-91505Olympus - LCY18 22035-GL 13 - 22 - Phase 11 MTO Steelwork Plan on Roof Level | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-DR-S-91513Olympus - LCY18 22035-GL 22 -28 - Phase 13 MTO Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-00-DR-S-91502Olympus - LCY18 22035-GL 06 -13 - Phase 12 MTO Steelwork Plan on Ground Floor | DR - Drawing (DR) | STR | 30 Apr 2026 | 30 Apr 2026Asite issue | C01 | AAccepted | 26 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| YAZU-DEMO-ARC-01General Arrangement Plan | drawing | ARC | 01 May 2026 | 01 Jun 2026Asite issue | P03 | AAccepted | — | Awaiting Design Review | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-92011Risersafe Level 4 Grid 8-12 Plan views Sheet 1 | DR - Drawing (DR) | STR | 04 May 2026 | 04 May 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-92012Risersafe Level 4 Grid 8-12 Plan views Sheet 2 | DR - Drawing (DR) | STR | 04 May 2026 | 04 May 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-92012Risersafe Level 5 Grid 8-12 Plan views Sheet 2 | DR - Drawing (DR) | STR | 04 May 2026 | 04 May 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-92010Risersafe Level 2 Grid 8-12 General Arrangement | DR - Drawing (DR) | STR | 04 May 2026 | 04 May 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-92011Risersafe Level 3 Grid 8-12 Plan views Sheet 1 | DR - Drawing (DR) | STR | 04 May 2026 | 04 May 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-92010Risersafe Level 4 Grid 8-12 General Arrangement | DR - Drawing (DR) | STR | 04 May 2026 | 04 May 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-92011Risersafe Level 2 Grid 8-12 Plan views Sheet 1 | DR - Drawing (DR) | STR | 04 May 2026 | 04 May 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-92010Risersafe Level 3 Grid 8-12 General Arrangement | DR - Drawing (DR) | STR | 04 May 2026 | 04 May 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-92012Risersafe Level 3 Grid 8-12 Plan views Sheet 2 | DR - Drawing (DR) | STR | 04 May 2026 | 04 May 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-92010Risersafe Level 5 Grid 8-12 General Arrangement | DR - Drawing (DR) | STR | 04 May 2026 | 04 May 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-92012Risersafe Level 2 Grid 8-12 Plan views Sheet 2 | DR - Drawing (DR) | STR | 04 May 2026 | 04 May 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-92011Risersafe Level 5 Grid 8-12 Plan views Sheet 1 | DR - Drawing (DR) | STR | 04 May 2026 | 04 May 2026Asite issue | P01 | CRejected | 22 May 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| YAZU-DEMO-ARC-02Room Data Sheet | schedule | ARC | 05 May 2026 | 08 Jun 2026Asite issue | P04 | BAccepted with comments | — | Awaiting Design Review | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29203Connection No.:29203 | CA - Calculations (CA) | STR | 05 May 2026 | 05 May 2026Asite issue | C02 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29203Connection No.:29203 | CA - Calculations (CA) | STR | 05 May 2026 | 05 May 2026Asite issue | C02 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28295Connection No.: 28295 | CA - Calculations (CA) | STR | 05 May 2026 | 05 May 2026Asite issue | C01 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29216Connection No.:29216 | CA - Calculations (CA) | STR | 05 May 2026 | 05 May 2026Asite issue | C01 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28296Connection No.: 28296 | CA - Calculations (CA) | STR | 05 May 2026 | 05 May 2026Asite issue | C01 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29218Connection No.:29218 | CA - Calculations (CA) | STR | 05 May 2026 | 05 May 2026Asite issue | C01 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29215Connection No.:29215 | CA - Calculations (CA) | STR | 05 May 2026 | 05 May 2026Asite issue | C01 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29217Connection No.:29217 | CA - Calculations (CA) | STR | 05 May 2026 | 05 May 2026Asite issue | C01 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00039Trade Contractor Weekly Report | RP - Report (RP) | STR | 06 May 2026 | 06 May 2026Asite issue | C01 | For InformationNo approval required | 06 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TS-S-00005Omega Riser Technical Submission | TS - Technical Submittals (TS) | STR | 06 May 2026 | 06 May 2026Asite issue | C01 | AAccepted | 04 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28117Connection No.: 28117 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C04 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28125Connection No.: 28125 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C03 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28138Connection No.: 28138 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C05 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28142Connection No.: 28142 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C03 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28127Connection No.: 28127 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C05 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28169Connection No.: 28169 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C03 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29130Connection No.: 29130 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29134Connection No.:29134 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28189Connection No.:28189 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 10 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28111Connection No.:28111 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29101Connection No.:29101 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28104Connection No.:28104 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29107Connection No.:29107 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28116Connection No.:28116 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29108Connection No.:29108 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 30 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28101Connection No.:28101 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28103Connection No.:28103 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29106Connection No.:29106 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28113Connection No.:28113 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 30 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28117Connection No.:28117 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29109Connection No.:29109 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00039Trade Contractor Weekly Report | RP - Report (RP) | STR | 06 May 2026 | 06 May 2026Asite issue | C01 | For InformationNo approval required | 06 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TS-S-00005Omega Riser Technical Submission | TS - Technical Submittals (TS) | STR | 06 May 2026 | 06 May 2026Asite issue | C01 | AAccepted | 04 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28138Connection No.: 28138 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C05 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28125Connection No.: 28125 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C03 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28127Connection No.: 28127 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C05 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28117Connection No.: 28117 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C04 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28169Connection No.: 28169 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C03 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28142Connection No.: 28142 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C03 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29130Connection No.: 29130 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28189Connection No.:28189 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 10 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29134Connection No.:29134 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 10 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28104Connection No.:28104 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29107Connection No.:29107 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28101Connection No.:28101 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28111Connection No.:28111 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29101Connection No.:29101 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29109Connection No.:29109 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28113Connection No.:28113 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 30 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28117Connection No.:28117 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28103Connection No.:28103 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29106Connection No.:29106 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28116Connection No.:28116 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29108Connection No.:29108 | CA - Calculations (CA) | STR | 06 May 2026 | 06 May 2026Asite issue | C02 | AAccepted | 30 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-28301Steelwork Plan @+19.940m (L03) - Phase 28 | DR - Drawing (DR) | STR | 07 May 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-29301Steelwork Plan @+19.940m (L03) - Phase 29 | DR - Drawing (DR) | STR | 07 May 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-28401Steelwork Plan @+26.440m (L04) - Phase 28 | DR - Drawing (DR) | STR | 07 May 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-54701OLYMPUS - LCY11 22031 - GL 14-18 - Phase 54 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 27 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-51701OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 27 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-55701OLYMPUS - LCY11 22031 - GL 14-18 - Phase 55 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 27 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-07-DR-S-51721Olympus - LCY11 22031 - GL 14-18 - Phases 51 to 56 Cellsheild Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | For InformationNo approval required | 21 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-51618OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL F | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 04 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-52615OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL 15 (GL H to K) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 04 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-53616OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL 15 (GL A to E) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 04 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-56601OLYMPUS - LCY11 22031 - GL 14-18 - Phase 56 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 27 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-29501Steelwork Plan @+32.940m (L05) - Phase 29 | DR - Drawing (DR) | STR | 07 May 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-55610OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL 17 (GL H to K) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | BAccepted with comments | 22 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-53601OLYMPUS - LCY11 22031 - GL 14-18 - Phase 53 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 27 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-54610OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL 17 (GL E to H) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 04 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-51722Olympus - LCY11 22031 - GL 14-18 - Phases 51 to 56 Cell Sheild Pots @+45.940m (LR01) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C01 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-51623Olympus - LCY11 22031 - GL 14-18 - Phases 51 to 56 Cellsheild Pots @+39.440m (L06) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C01 | For InformationNo approval required | 21 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-51621Olympus - LCY11 22031 - GL 14-18 - Phases 51 to 56 Cellsheild Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | For InformationNo approval required | 21 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-56611OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL 18 (GL A to E) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | BAccepted with comments | 22 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-53617OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL 16 (GL A to E) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 04 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-23012Steelwork Elevation on GL 23 Lvl 0 to 4 (South) | DR - Drawing (DR) | STR | 07 May 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-23014Steelwork Elevation on GL 24 Lvl 0 to 4 (South) | DR - Drawing (DR) | STR | 07 May 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-52616OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL 16 (GL H to K) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 04 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-51619OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL G | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 04 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-56610OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL 17 (GL A to E) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | BAccepted with comments | 22 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-23012Steelwork Elevation on GL 23 Lvl 0 to 4 (South) | DR - Drawing (DR) | STR | 07 May 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-56701OLYMPUS - LCY11 22031 - GL 14-18 - Phase 56 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 27 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-52601OLYMPUS - LCY11 22031 - GL 14-18 - Phase 52 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 27 May 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-54611OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL 18 (GL E to H) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 04 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-23014Steelwork Elevation on GL 24 Lvl 0 to 4 (South) | DR - Drawing (DR) | STR | 07 May 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-55611OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL 18 (GL A to E) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | BAccepted with comments | 22 May 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-28301Steelwork Plan @+19.940m (L03) - Phase 28 | DR - Drawing (DR) | STR | 07 May 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-53611OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 04 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-51611OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL 14 (GL E to H) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 04 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-52613OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL K | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 04 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-29301Steelwork Plan @+19.940m (L03) - Phase 29 | DR - Drawing (DR) | STR | 07 May 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-28401Steelwork Plan @+26.440m (L04) - Phase 28 | DR - Drawing (DR) | STR | 07 May 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-55601OLYMPUS - LCY11 22031 - GL 14-18 - Phase 55 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 27 May 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-29401Steelwork Plan @+26.440m (L04) - Phase 29 | DR - Drawing (DR) | STR | 07 May 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-51613OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL 16 (GL E to H) | DR - Drawing (DR) | STR | 07 May 2026 | 07 May 2026Asite issue | C02 | AAccepted | 04 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28000Connection No.:28000 | CA - Calculations (CA) | STR | 08 May 2026 | 08 May 2026Asite issue | C02 | AAccepted | 11 May 2026 | Awaiting Design ReviewCANCELLED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28102Connection No.:28102 | CA - Calculations (CA) | STR | 08 May 2026 | 08 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28114Connection No.:28114 | CA - Calculations (CA) | STR | 08 May 2026 | 08 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28000Connection No.:28000 | CA - Calculations (CA) | STR | 08 May 2026 | 08 May 2026Asite issue | C02 | AAccepted | 11 May 2026 | Awaiting Design ReviewCANCELLED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28114Connection No.:28114 | CA - Calculations (CA) | STR | 08 May 2026 | 08 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28102Connection No.:28102 | CA - Calculations (CA) | STR | 08 May 2026 | 08 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| YAZU-DEMO-STR-01Transfer Beam Detail | drawing | STR | 10 May 2026 | 10 Jun 2026Asite issue | P03 | AAccepted | — | Awaiting Design Review | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00040Trade Contractor Weekly Report | RP - Report (RP) | STR | 11 May 2026 | 11 May 2026Asite issue | C01 | For InformationNo approval required | 12 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00040Trade Contractor Weekly Report | RP - Report (RP) | STR | 11 May 2026 | 11 May 2026Asite issue | C01 | For InformationNo approval required | 12 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| YAZU-DEMO-STR-02Foundation Calculation | calculation | STR | 12 May 2026 | 25 May 2026Asite issue | P02 | AAccepted | — | Status A | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TS-S-00006Metal Grating Technical Submittal | TS - Technical Submittals (TS) | STR | 12 May 2026 | 30 Jul 2026Asite issue | C03 | BAccepted with comments | 31 Jul 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TS-S-00006Metal Grating Technical Submittal | TS - Technical Submittals (TS) | STR | 12 May 2026 | 30 Jul 2026Asite issue | C03 | BAccepted with comments | 31 Jul 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29113Connection No.: 29113 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28280Connection No.: 28280 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29214Connection No.: 29214 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28293Connection No.: 28293 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29114Connection No.: 29114 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28113Connection No.: 28113 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29115Connection No.: 29115 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C01 | AAccepted | 19 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28267Connection No.: 28267 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C02 | AAccepted | 13 May 2026 | Awaiting Design ReviewCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28284Connection No.:28284 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28267Connection No.: 28267 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C02 | AAccepted | 13 May 2026 | Awaiting Design ReviewCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28113Connection No.: 28113 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29212Connection No.: 29212 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29213Connection No.: 29213 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-28121Connection No.: 28121 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28283Connection No.: 28283 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28285Connection No.:28285 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28182Connection No.: 28182 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28281Connection No.: 28281 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28182Connection No.: 28182 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28282Connection No.: 28282 | CA - Calculations (CA) | STR | 13 May 2026 | 13 May 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| YAZU-DEMO-MEP-01Mechanical Plantroom Layout | drawing | MEP | 15 May 2026 | 12 Jun 2026Asite issue | P03 | BAccepted with comments | — | Awaiting Design Review | A0 · R0 · !0 |
| YAZU-DEMO-MEP-02Electrical Load Schedule | schedule | MEP | 18 May 2026 | 30 May 2026Asite issue | P02 | BAccepted with comments | — | Status B | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03002Cladding Details 3 | DR - Drawing (DR) | FAC | 19 May 2026 | 31 Jul 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99202Temporary Works – TW2-1 – Freestanding L00 Columns | TW - Temporary Works (TW) | STR | 19 May 2026 | 29 May 2026Asite issue | C04 | AAccepted | 21 Jul 2026 | Status A (Accepted)FAILED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03009Cladding Details 10 | DR - Drawing (DR) | FAC | 19 May 2026 | 07 Sept 2026Asite issue | C03 | AAccepted | 07 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03000Cladding Details 1 | DR - Drawing (DR) | FAC | 19 May 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03004Cladding Details 5 | DR - Drawing (DR) | FAC | 19 May 2026 | 07 Sept 2026Asite issue | C02 | AAccepted | 07 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99202Temporary Works – TW2-1 – Freestanding L00 Columns | TW - Temporary Works (TW) | STR | 19 May 2026 | 29 May 2026Asite issue | C04 | AAccepted | 21 Jul 2026 | Status A (Accepted)FAILED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-01000Cladding GA Elevation 1 | DR - Drawing (DR) | FAC | 19 May 2026 | 31 Jul 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03003Cladding Details 4 | DR - Drawing (DR) | FAC | 19 May 2026 | 31 Jul 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-01003Cladding GA Elevation 4 | DR - Drawing (DR) | FAC | 19 May 2026 | 31 Jul 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-01005Cladding GA Elevation 6 | DR - Drawing (DR) | FAC | 19 May 2026 | 31 Jul 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-01002Cladding GA Elevation 3 | DR - Drawing (DR) | FAC | 19 May 2026 | 31 Jul 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03010Cladding Details 11 | DR - Drawing (DR) | FAC | 19 May 2026 | 07 Sept 2026Asite issue | C02 | AAccepted | 07 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03007Cladding Details 8 | DR - Drawing (DR) | FAC | 19 May 2026 | 07 Sept 2026Asite issue | C02 | AAccepted | 07 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-01001Cladding GA Elevation 2 | DR - Drawing (DR) | FAC | 19 May 2026 | 31 Jul 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03006Cladding Details 7 | DR - Drawing (DR) | FAC | 19 May 2026 | 07 Sept 2026Asite issue | C02 | AAccepted | 07 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03008Cladding Details 9 | DR - Drawing (DR) | FAC | 19 May 2026 | 07 Sept 2026Asite issue | C02 | AAccepted | 07 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00041Contractor Weekly Report | RP - Report (RP) | STR | 19 May 2026 | 19 May 2026Asite issue | C01 | For InformationNo approval required | 19 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-01102Cladding GA Section 2 | DR - Drawing (DR) | FAC | 19 May 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03001Cladding Details 2 | DR - Drawing (DR) | FAC | 19 May 2026 | 31 Jul 2026Asite issue | C01 | AAccepted | 19 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-01101Cladding GA Section 1 | DR - Drawing (DR) | FAC | 19 May 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-01004Cladding GA Elevation 5 | DR - Drawing (DR) | FAC | 19 May 2026 | 31 Jul 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00041Contractor Weekly Report | RP - Report (RP) | STR | 19 May 2026 | 19 May 2026Asite issue | C01 | For InformationNo approval required | 19 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-01007Cladding GA Elevation 8 | DR - Drawing (DR) | FAC | 19 May 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01255South Area 2 - Grids 14-18 Elevation & Sections Rainscreen Panels | DR - Drawing (DR) | FAC | 20 May 2026 | 25 Jun 2026Asite issue | C01 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01655South Area 6 - Grids 22-24 Elevation & Sections Rainscreen Panels | DR - Drawing (DR) | FAC | 20 May 2026 | 25 Jun 2026Asite issue | C01 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01605North Area 6 - Grids 22-24 Elevation & Sections Rainscreen Panels | DR - Drawing (DR) | FAC | 20 May 2026 | 25 Jun 2026Asite issue | C01 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01355South Area 3 - Grids 06-10 Elevation & Sections Rainscreen Panels | DR - Drawing (DR) | FAC | 20 May 2026 | 25 Jun 2026Asite issue | C01 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01155South Area 1 - Grids 10-14 Elevation & Sections Rainscreen Panels | DR - Drawing (DR) | FAC | 20 May 2026 | 25 Jun 2026Asite issue | C01 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03015North & South Rainscreen Details 15 | DR - Drawing (DR) | FAC | 20 May 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01205North Area 2 - Grids 14-18 Elevation & Sections Rainscreen Panels | DR - Drawing (DR) | FAC | 20 May 2026 | 25 Jun 2026Asite issue | C01 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01105North Area 1 - Grids 10-14 Elevation & Sections Rainscreen Panels | DR - Drawing (DR) | FAC | 20 May 2026 | 25 Jun 2026Asite issue | C01 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01305North Area 3 - Grids 06-10 Elevation & Sections Rainscreen Panels | DR - Drawing (DR) | FAC | 20 May 2026 | 25 Jun 2026Asite issue | C01 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01405North Area 4 - Grids 18-22 Elevation & Sections Rainscreen Panels | DR - Drawing (DR) | FAC | 20 May 2026 | 25 Jun 2026Asite issue | C01 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01455South Area 4 - Grids 18-22 Elevation & Sections Rainscreen Panels | DR - Drawing (DR) | FAC | 20 May 2026 | 25 Jun 2026Asite issue | C01 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-32301Olympus - LCY11 22032 - GL 10 - 14 - Phase 32 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-34101Olympus - LCY11 22032 - GL 10 - 14 - Phase 34 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31016Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL F | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-35401Olympus - LCY11 22032 - GL 10 - 14 - Phase 35 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-33401Olympus - LCY11 22032 - GL 10 - 14 - Phase 33 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-31401Olympus - LCY11 22032 - GL 10 - 14 - Phase 31 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-31521Olympus - LCY11 22032 - GL 10 -14 - Phases 31 To 36 Cell shield Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | For InformationNo approval required | 21 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31018Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL H | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31018Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL H | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-32014Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL 12 (GL H to K) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | BAccepted with comments | 19 Jun 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-34101Olympus - LCY11 22032 - GL 10 - 14 - Phase 34 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-32101Olympus - LCY11 22032 - GL 10 - 14 - Phase 32 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 09 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-33016Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL 13 (GL A to E) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-33030Olympus - LCY11 22032 - GL 08 -14 - Phase 33 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-32015Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL 13 (GL H to K) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-35301Olympus - LCY11 22032 - GL 10 - 14 - Phase 35 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-31033Olympus - LCY11 22032 - GL 08 -14 - Phase 31 to 39 Steelwork Foundation Detail - Sheet 2 | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-34013Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL 11 (GL E to H) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-35501Olympus - LCY11 22032 - GL 10 - 14 - Phase 35 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-33301Olympus - LCY11 22032 - GL 10 - 14 - Phase 33 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-31222Olympus - LCY11 22032 - GL 10 - 14 - Phase 31 to 36 Cell Sheild Pots @+13.440m (L02) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C01 | For InformationNo approval required | 21 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-35101Olympus - LCY11 22032 - GL 10 - 14 - Phase 35 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | BAccepted with comments | 19 Jun 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-33101Olympus - LCY11 22032 - GL 10 - 14 - Phase 33 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 09 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-31101Olympus - LCY11 22032 - GL 10 - 14 - Phase 31 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-33031Olympus - LCY11 22032 - GL 10 -14 - Phase 33 Steelwork Selection & Detail Views | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-31301Olympus - LCY11 22032 - GL 10 - 14 - Phase 31 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-31201Olympus - LCY11 22032 - GL 10 - 14 - Phase 31 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-36011Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL 10 (GL A to E) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | BAccepted with comments | 19 Jun 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-35201Olympus - LCY11 22032 - GL 10 - 14 - Phase 35 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-31030Olympus - LCY11 22032 - GL 08 -14 - Phase 31 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-35401Olympus - LCY11 22032 - GL 10 - 14 - Phase 35 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-34011Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL 10 (GL E to H) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-31001Olympus - LCY11 22032 - GL 08 - 14 - Phase 31 to 39 Steelwork Foundation Plan (GL H to K) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-35201Olympus - LCY11 22032 - GL 10 - 14 - Phase 35 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-33201Olympus - LCY11 22032 - GL 10 - 14 - Phase 33 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-32013Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL K | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-32030Olympus - LCY11 22032 - GL 08 -14 - Phase 32 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-33401Olympus - LCY11 22032 - GL 10 - 14 - Phase 33 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-34401Olympus - LCY11 22032 - GL 10 - 14 - Phase 34 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-31401Olympus - LCY11 22032 - GL 10 - 14 - Phase 31 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-31003Steelwork Foundation Plan on GL08 to 14 (GL E to H) | DR - Drawing (DR) | STR | 21 May 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-36501Olympus - LCY11 22032 - GL 10 - 14 - Phase 36 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-31001Olympus - LCY11 22032 - GL 08 - 14 - Phase 31 to 39 Steelwork Foundation Plan (GL H to K) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-34501Olympus - LCY11 22032 - GL 10 - 14 - Phase 34 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-33011Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-32501Olympus - LCY11 22032 - GL 10 - 14 - Phase 32 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31011Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL 12 (GL E to H) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-36401Olympus - LCY11 22032 - GL 10 - 14 - Phase 36 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-32031Olympus - LCY11 22032 - GL 10 -14 - Phase 32 Steelwork Selection & Detail Views | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-31101Olympus - LCY11 22032 - GL 10 - 14 - Phase 31 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31013Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL 13 (GL E to H) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 30 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31017Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL G | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-31221Olympus - LCY11 22032 - GL 10 -14 - Phases 31 To 36 Cell shield Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | For InformationNo approval required | 21 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31013Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL 13 (GL E to H) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 30 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-31421Olympus - LCY11 22032 - GL 10 -14 - Phases 31 To 36 Cell shield Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | For InformationNo approval required | 21 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-32201Olympus - LCY11 22032 - GL 10 - 14 - Phase 32 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-35030Olympus - LCY11 22032 - GL 08 -14 - Phase 35 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-36401Olympus - LCY11 22032 - GL 10 - 14 - Phase 36 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-34401Olympus - LCY11 22032 - GL 10 - 14 - Phase 34 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-35301Olympus - LCY11 22032 - GL 10 - 14 - Phase 35 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-34201Olympus - LCY11 22032 - GL 10 - 14 - Phase 34 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-33301Olympus - LCY11 22032 - GL 10 - 14 - Phase 33 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-36010Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL 11 (GL A to E) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31017Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL G | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-31301Olympus - LCY11 22032 - GL 10 - 14 - Phase 31 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-36201Olympus - LCY11 22032 - GL 10 - 14 - Phase 36 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-36301Olympus - LCY11 22032 - GL 10 - 14 - Phase 36 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-34013Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL 11 (GL E to H) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-34301Olympus - LCY11 22032 - GL 10 - 14 - Phase 34 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-31422Olympus - LCY11 22032 - GL 10 - 14 - Phase 31 to 36 Cell Sheild Pots @+26.440m (L04) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C01 | For InformationNo approval required | 21 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-32301Olympus - LCY11 22032 - GL 10 - 14 - Phase 32 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-33011Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31011Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL 12 (GL E to H) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-36301Olympus - LCY11 22032 - GL 10 - 14 - Phase 36 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-31321Olympus - LCY11 22032 - GL 10 -14 - Phases 31 To 36 Cell shield Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | For InformationNo approval required | 21 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-31322Olympus - LCY11 22032 - GL 10 - 14 - Phase 31 to 36 Cell Sheild Pots @+19.940m (L03) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C01 | For InformationNo approval required | 21 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31016Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL F | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-35501Olympus - LCY11 22032 - GL 10 - 14 - Phase 35 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-33501Olympus - LCY11 22032 - GL 10 - 14 - Phase 33 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-31501Olympus - LCY11 22032 - GL 10 - 14 - Phase 31 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-34301Olympus - LCY11 22032 - GL 10 - 14 - Phase 34 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-31031Olympus - LCY11 22032 - GL 10 -14 - Phase 31 Steelwork Selection & Detail Views | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-35010Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL 11 (GL H to K) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-31522Olympus - LCY11 22032 - GL 10 - 14 - Phase 31 to 36 Cell Sheild Pots @+32.940m (L05) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C01 | For InformationNo approval required | 21 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-34011Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL 10 (GL E to H) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-36501Olympus - LCY11 22032 - GL 10 - 14 - Phase 36 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-34501Olympus - LCY11 22032 - GL 10 - 14 - Phase 34 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-32501Olympus - LCY11 22032 - GL 10 - 14 - Phase 32 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-32101Olympus - LCY11 22032 - GL 10 - 14 - Phase 32 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 09 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-35101Olympus - LCY11 22032 - GL 10 - 14 - Phase 35 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | BAccepted with comments | 19 Jun 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-31201Olympus - LCY11 22032 - GL 10 - 14 - Phase 31 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-31501Olympus - LCY11 22032 - GL 10 - 14 - Phase 31 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-36201Olympus - LCY11 22032 - GL 10 - 14 - Phase 36 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-34201Olympus - LCY11 22032 - GL 10 - 14 - Phase 34 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-32201Olympus - LCY11 22032 - GL 10 - 14 - Phase 32 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-35011Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL 10 (GL H to K) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | BAccepted with comments | 19 Jun 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-31032Olympus - LCY11 22032 - GL 08 - 14 - Phase 31 to 39 Steelwork Foundation Details - Sheet 1 | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-33501Olympus - LCY11 22032 - GL 10 - 14 - Phase 33 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-33015Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL 12 (GL A to E) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | BAccepted with comments | 19 Jun 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-34030Olympus - LCY11 22032 - GL 08 -14 - Phase 34 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-36101Olympus - LCY11 22032 - GL 10 - 14 - Phase 36 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | BAccepted with comments | 19 Jun 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-36101Olympus - LCY11 22032 - GL 10 - 14 - Phase 36 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | BAccepted with comments | 19 Jun 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-31003Steelwork Foundation Plan on GL08 to 14 (GL E to H) | DR - Drawing (DR) | STR | 21 May 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-36030Olympus - LCY11 22032 - GL 08 -14 - Phase 36 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-33101Olympus - LCY11 22032 - GL 10 - 14 - Phase 33 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 09 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-33201Olympus - LCY11 22032 - GL 10 - 14 - Phase 33 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-32013Olympus - LCY11 22032 - GL 10 -14 - Phase 31 to 36 Steelwork Elevation on GL K | DR - Drawing (DR) | STR | 21 May 2026 | 21 May 2026Asite issue | C02 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-XX-DR-S-11001Olympus - LCY18 22035 - GL 13 - 22 - Phase 11 Steelwork Isometric View | DR - Drawing (DR) | STR | 26 May 2026 | 26 May 2026Asite issue | C01 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-RF-DR-S-11003Olympus - LCY18 22035 - GL 13 - 22 - Phase 11 Steelwork Roof Level Plan at EL+8.422m | DR - Drawing (DR) | STR | 26 May 2026 | 26 May 2026Asite issue | C01 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-XX-DR-S-14501Olympus - LCY18 22035 - GL 01 - 06 - Phase 14 Cell Sheild Panels & Pot GA at EL+8.422m | DR - Drawing (DR) | STR | 26 May 2026 | 26 May 2026Asite issue | C01 | For InformationNo approval required | 27 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99210Temporary Works – TW11-01 – HAKI Stairs | TW - Temporary Works (TW) | STR | 26 May 2026 | 27 May 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-XX-DR-S-12501Olympus - LCY18 22035 - GL 06 - 13 - Phase 12 Cell Sheild Panels & Pot GA at EL+8.422m | DR - Drawing (DR) | STR | 26 May 2026 | 26 May 2026Asite issue | C01 | For InformationNo approval required | 27 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-XX-DR-S-14001Olympus - LCY18 22035 - GL 01 - 06 - Phase 14 Steelwork Isometric View | DR - Drawing (DR) | STR | 26 May 2026 | 26 May 2026Asite issue | C01 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99000Temporary Works Register | TW - Temporary Works (TW) | STR | 26 May 2026 | 27 May 2026Asite issue | C04 | For InformationNo approval required | 28 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-XX-DR-S-12001Olympus - LCY18 22035 - GL 06 -13 - Phase 12 Steelwork Isometric View | DR - Drawing (DR) | STR | 26 May 2026 | 26 May 2026Asite issue | C01 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-XX-DR-S-13001Olympus - LCY18 22035 - GL 22 - 28 - Phase 13 Steelwork Isometric View | DR - Drawing (DR) | STR | 26 May 2026 | 26 May 2026Asite issue | C01 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99000Temporary Works Register | TW - Temporary Works (TW) | STR | 26 May 2026 | 27 May 2026Asite issue | C04 | For InformationNo approval required | 28 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-XX-DR-S-11501Olympus - LCY18 22035 - GL 13 - 22 - Phase 11 Cell Sheild Panels & Pot GA at EL+8.422m | DR - Drawing (DR) | STR | 26 May 2026 | 26 May 2026Asite issue | C01 | For InformationNo approval required | 27 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-XX-DR-S-13501Olympus - LCY18 22035 - GL 22 - 28 - Phase 13 Cell Sheild Panels & Pot GA at EL+8.422m | DR - Drawing (DR) | STR | 26 May 2026 | 26 May 2026Asite issue | C01 | For InformationNo approval required | 27 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-XX-DR-S-10101Olympus - LCY18 22035 - GL 01 - 28 - Phase 11 to 14 Temporary Steelwork Plan | DR - Drawing (DR) | STR | 26 May 2026 | 26 May 2026Asite issue | C01 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00042Trade Contractor Weekly Report | RP - Report (RP) | STR | 27 May 2026 | 27 May 2026Asite issue | C01 | For InformationNo approval required | 28 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00042Trade Contractor Weekly Report | RP - Report (RP) | STR | 27 May 2026 | 27 May 2026Asite issue | C01 | For InformationNo approval required | 28 May 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28255Connection No.: 28255 | CA - Calculations (CA) | STR | 29 May 2026 | 29 May 2026Asite issue | C04 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28271Connection No.: 28271 | CA - Calculations (CA) | STR | 29 May 2026 | 29 May 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-54601Olympus - LCY11 22031 - GL 14-18 - Phase 54 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 29 May 2026 | 29 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28164Connection No.: 28164 | CA - Calculations (CA) | STR | 29 May 2026 | 29 May 2026Asite issue | C04 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28166Connection No.: 28166 | CA - Calculations (CA) | STR | 29 May 2026 | 29 May 2026Asite issue | C04 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28119Connection No.: 28119 | CA - Calculations (CA) | STR | 29 May 2026 | 29 May 2026Asite issue | C06 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DS-S-00001Connection Design Brief | DS - Design Statement (DS) | STR | 29 May 2026 | 29 May 2026Asite issue | C04 | BAccepted with comments | 29 May 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28271Connection No.: 28271 | CA - Calculations (CA) | STR | 29 May 2026 | 29 May 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92023Omegariser Level 6 grid 18-22 Plan Views | DR - Drawing (DR) | STR | 29 May 2026 | 29 May 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28120Connection No.: 28120 | CA - Calculations (CA) | STR | 29 May 2026 | 29 May 2026Asite issue | C06 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28166Connection No.: 28166 | CA - Calculations (CA) | STR | 29 May 2026 | 29 May 2026Asite issue | C04 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28255Connection No.: 28255 | CA - Calculations (CA) | STR | 29 May 2026 | 29 May 2026Asite issue | C04 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92022RiserSafe Level 6 Grid 18-22 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 29 May 2026 | 29 May 2026Asite issue | P02 | CRejected | 26 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28168Connection No.: 28168 | CA - Calculations (CA) | STR | 29 May 2026 | 29 May 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DS-S-00001Connection Design Brief | DS - Design Statement (DS) | STR | 29 May 2026 | 29 May 2026Asite issue | C04 | BAccepted with comments | 29 May 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28119Connection No.: 28119 | CA - Calculations (CA) | STR | 29 May 2026 | 29 May 2026Asite issue | C06 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28272Connection No.: 28272 | CA - Calculations (CA) | STR | 29 May 2026 | 29 May 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-52701Olympus - LCY11 22031 - GL 14-18 - Phase 52 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 29 May 2026 | 29 May 2026Asite issue | C03 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28164Connection No.: 28164 | CA - Calculations (CA) | STR | 29 May 2026 | 29 May 2026Asite issue | C04 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92020RiserSafe Level 6 Grid 18-22 General Arrangement | DR - Drawing (DR) | STR | 29 May 2026 | 29 May 2026Asite issue | P02 | CRejected | 26 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28168Connection No.: 28168 | CA - Calculations (CA) | STR | 29 May 2026 | 29 May 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92021RiserSafe Level 6 Grid 18-22 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 29 May 2026 | 29 May 2026Asite issue | P02 | CRejected | 26 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28272Connection No.: 28272 | CA - Calculations (CA) | STR | 29 May 2026 | 29 May 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28120Connection No.: 28120 | CA - Calculations (CA) | STR | 29 May 2026 | 29 May 2026Asite issue | C06 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99001Temporary Works – TW00-01 – Temporary Works Procedures and Appointment | TW - Temporary Works (TW) | STR | 01 Jun 2026 | 06 Jul 2026Asite issue | C03 | QA Accepted | 06 Jul 2026 | QA AcceptedCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-32401Steelwork Plan @+26.440m (L04) - Phase 32 | DR - Drawing (DR) | STR | 01 Jun 2026 | 01 Jun 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-32401Steelwork Plan @+26.440m (L04) - Phase 32 | DR - Drawing (DR) | STR | 01 Jun 2026 | 01 Jun 2026Asite issue | C03 | AAccepted | 25 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29100Connection No.: 29100 | CA - Calculations (CA) | STR | 01 Jun 2026 | 01 Jun 2026Asite issue | C05 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29112Connection No.: 29112 | CA - Calculations (CA) | STR | 01 Jun 2026 | 01 Jun 2026Asite issue | C04 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00043Trade Contractor Weekly Report | RP - Report (RP) | STR | 01 Jun 2026 | 01 Jun 2026Asite issue | C01 | For InformationNo approval required | 04 Jun 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28290Connection No.: 28290 | CA - Calculations (CA) | STR | 01 Jun 2026 | 01 Jun 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99001Temporary Works – TW00-01 – Temporary Works Procedures and Appointment | TW - Temporary Works (TW) | STR | 01 Jun 2026 | 06 Jul 2026Asite issue | C03 | QA Accepted | 06 Jul 2026 | QA AcceptedCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29112Connection No.: 29112 | CA - Calculations (CA) | STR | 01 Jun 2026 | 01 Jun 2026Asite issue | C04 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| YAZU-DEMO-ARC-03Door Schedule | schedule | ARC | 01 Jun 2026 | 14 Jun 2026Asite issue | P02 | CRejected | — | Status C | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29196Connection No.: 29196 | CA - Calculations (CA) | STR | 01 Jun 2026 | 01 Jun 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29100Connection No.: 29100 | CA - Calculations (CA) | STR | 01 Jun 2026 | 01 Jun 2026Asite issue | C05 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29196Connection No.: 29196 | CA - Calculations (CA) | STR | 01 Jun 2026 | 01 Jun 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00043Trade Contractor Weekly Report | RP - Report (RP) | STR | 01 Jun 2026 | 01 Jun 2026Asite issue | C01 | For InformationNo approval required | 04 Jun 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-CA-X-00006CLADDING WIND LOAD REPORT | CA - Calculations (CA) | FAC | 02 Jun 2026 | 02 Jun 2026Asite issue | P01 | BAccepted with comments | 26 Jun 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-CA-X-00005K-ROC - CARRIER SUPPORT RAIL & CONNECTIONS AT WEST FACADE | CA - Calculations (CA) | FAC | 02 Jun 2026 | 02 Jun 2026Asite issue | P01 | BAccepted with comments | 10 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-RG-X-90000VMU CHANGE TRACKER | RG - Register (RG) | FAC | 04 Jun 2026 | 04 Jun 2026Asite issue | P01 | BAccepted with comments | 10 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00020Grids 23-24, Along F & G, Tolerance Steel Lug Setting Out | DR - Drawing (DR) | FAC | 04 Jun 2026 | 04 Jun 2026Asite issue | P01 | BAccepted with comments | 10 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-43014Steelwork Elevation on GL 5 Lvl 0 to 4 (South) | DR - Drawing (DR) | STR | 05 Jun 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00061WEST ELEVATION LUG SETTING 2 | DR - Drawing (DR) | FAC | 05 Jun 2026 | 05 Jun 2026Asite issue | P01 | AAccepted | 10 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| YAZU-DEMO-STR-03Steel Connection Design | calculation | STR | 05 Jun 2026 | 18 Jun 2026Asite issue | P01 | PendingAwaiting Design Review | — | Awaiting Design Review | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00031EAST ELEVATION LUG SETTING 2 | DR - Drawing (DR) | FAC | 05 Jun 2026 | 05 Jun 2026Asite issue | P01 | AAccepted | 10 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00030EAST ELEVATION LUG SETTING 1 | DR - Drawing (DR) | FAC | 05 Jun 2026 | 05 Jun 2026Asite issue | P01 | BAccepted with comments | 26 Jun 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-43012Steelwork Elevation on GL 4 Lvl 0 to 4 (South) | DR - Drawing (DR) | STR | 05 Jun 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-43014Steelwork Elevation on GL 5 Lvl 0 to 4 (South) | DR - Drawing (DR) | STR | 05 Jun 2026Planned placeholder | —Not issued | C01 | PrepublishedNot issued | 19 Feb 2025 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-00060WEST ELEVATION LUG SETTING 1 | DR - Drawing (DR) | FAC | 05 Jun 2026 | 05 Jun 2026Asite issue | P01 | BAccepted with comments | 26 Jun 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91603Olympus - LCY11 22033 - GL 14 - 20 - Phase 12 to 17 MTO Steelwork Elevation on GL G | DR - Drawing (DR) | STR | 08 Jun 2026 | 08 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91606Olympus - LCY11 22033 - GL 14 - 20 - Phase 12 to 17 MTO Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 08 Jun 2026 | 08 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-91101Olympus - LCY11 22033 - GL 14 - 20 - Phase 12 to 17 MTO Steelwork Plan @+48.360m (G1) | DR - Drawing (DR) | STR | 08 Jun 2026 | 08 Jun 2026Asite issue | C01 | AAccepted | 30 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91602Olympus - LCY11 22033 - GL 14 - 20 - Phase 12 to 17 MTO Steelwork Elevation on GL J | DR - Drawing (DR) | STR | 08 Jun 2026 | 08 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92013Omegariser Level 6 Grid 8-12 Plan Views | DR - Drawing (DR) | STR | 08 Jun 2026 | 08 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| YAZU-DEMO-MEP-03Fire Alarm Cause and Effect | report | MEP | 08 Jun 2026 | 20 Jun 2026Asite issue | P03 | AAccepted | — | Awaiting Design Review | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-91106Olympus - LCY11 22033 - GL 14 - 20 - Phase 12 to 17 MTO Steelwork Plan @+57.440m (Int G2) | DR - Drawing (DR) | STR | 08 Jun 2026 | 08 Jun 2026Asite issue | C01 | AAccepted | 29 Jun 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-91104Olympus - LCY11 22033 - GL 14 - 20 - Phase 12 to 17 MTO Steelwork Plan @+54.440m (G2) | DR - Drawing (DR) | STR | 08 Jun 2026 | 08 Jun 2026Asite issue | C01 | BAccepted with comments | 19 Jun 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-91103Olympus - LCY11 22033 - GL 14 - 20 - Phase 12 to 17 MTO Steelwork Plan @+54.440m (G2) | DR - Drawing (DR) | STR | 08 Jun 2026 | 08 Jun 2026Asite issue | C01 | AAccepted | 30 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91604Olympus - LCY11 22033 - GL 14 - 20 - Phase 12 to 17 MTO Steelwork Elevation on GL F | DR - Drawing (DR) | STR | 08 Jun 2026 | 08 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-91105Olympus - LCY11 22033 - GL 14 - 20 - Phase 12 to 17 MTO Steelwork Plan @+57.440m (Int G2) | DR - Drawing (DR) | STR | 08 Jun 2026 | 08 Jun 2026Asite issue | C01 | AAccepted | 30 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-91108Olympus - LCY11 22033 - GL 14 - 20 - Phase 12 to 17 MTO Steelwork Plan @+60.440m (R3) | DR - Drawing (DR) | STR | 08 Jun 2026 | 08 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-91109Olympus - LCY11 22033 - GL 14 - 20 - Phase 12 to 17 MTO Steelwork Plan @+63.700m (TOP PARRAPET) | DR - Drawing (DR) | STR | 08 Jun 2026 | 08 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91601Olympus - LCY11 22033 - GL 14 - 20 - Phase 12 to 17 MTO Steelwork Elevation on GL K | DR - Drawing (DR) | STR | 08 Jun 2026 | 08 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91605Olympus - LCY11 22033 - GL 14 - 20 - Phase 12 to 17 MTO Steelwork Elevation on GL B | DR - Drawing (DR) | STR | 08 Jun 2026 | 08 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-91107Olympus - LCY11 22033 - GL 14 - 20 - Phase 12 to 17 MTO Steelwork Plan @+60.440m (R3) | DR - Drawing (DR) | STR | 08 Jun 2026 | 08 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-91102Olympus - LCY11 22033 - GL 14 - 20 - Phase 12 to 17 MTO Steelwork Plan @+48.360m (G1) | DR - Drawing (DR) | STR | 08 Jun 2026 | 08 Jun 2026Asite issue | C01 | AAccepted | 30 Jun 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-00002Steelwork Requirements 2 | DR - Drawing (DR) | FAC | 10 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-00001Steelwork Requirements 1 | DR - Drawing (DR) | FAC | 10 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-00003Steelwork Requirements 3 | DR - Drawing (DR) | FAC | 10 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| YAZU-DEMO-ARC-04Finishes Specification | specification | ARC | 10 Jun 2026 | 22 Jun 2026Asite issue | P03 | BAccepted with comments | — | Awaiting Design Review | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-00004Steelwork Requirements 4 | DR - Drawing (DR) | FAC | 10 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-92032Omegariser Level 4 Grid 4-8 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-92031Omegariser Level 4 Grid 4-8 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-91123Olympus - LCY11 22034 - GL 8 - 14 - Phase 31 to 36 MTO Steelwork Plan @+54.440m (G2) | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-92032Omegariser Level 5 Grid 4-8 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01624Area 6 - Grids E-H K-ROC GA East Elevation | DR - Drawing (DR) | FAC | 15 Jun 2026 | 26 Jun 2026Asite issue | P01 | BAccepted with comments | 28 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01623Area 6 - Grids B-E K-ROC GA East Elevation | DR - Drawing (DR) | FAC | 15 Jun 2026 | 26 Jun 2026Asite issue | P01 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91625Olympus - LCY11 22034 - GL 8 - 14 - Phase 31 to 36 MTO Steelwork Elevation on GL B | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91623Olympus - LCY11 22034 - GL 8 - 14 - Phase 31 to 36 MTO Steelwork Elevation on GL G | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01625Area 6 - Grids H-J K-ROC GA East Elevation | DR - Drawing (DR) | FAC | 15 Jun 2026 | 26 Jun 2026Asite issue | P01 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-91127Olympus - LCY11 22034 - GL 8 - 14 - Phase 31 to 36 MTO Steelwork Plan @+60.440m (R3) | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92031Omegariser Level 6 Grid 4-8 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92032Omegariser Level 6 Grid 4-8 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-91121Olympus - LCY11 22034 - GL 8 - 14 - Phase 31 to 36 MTO Steelwork Plan @+48.360m (G1) | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-92030Omegariser Level 5 Grid 4-8 General Arrangement | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-92030Omegariser Level 1 Grid 4-8 General Arrangement | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-91124Olympus - LCY11 22034 - GL 8 - 14 - Phase 31 to 36 MTO Steelwork Plan @+54.440m (G2) | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01674Area 6 - Grids E-H K-ROC Lower Building GA East Elevation | DR - Drawing (DR) | FAC | 15 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-92032Omegariser Level 3 Grid 4-8 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-92030Omegariser Level 3 Grid 4-8 General Arrangement | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01506Area 5 - Grids H-J K-ROC GA West Elevation | DR - Drawing (DR) | FAC | 15 Jun 2026 | 26 Jun 2026Asite issue | P01 | BAccepted with comments | 28 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01504Area 5 - Grids B-E K-ROC GA West Elevation | DR - Drawing (DR) | FAC | 15 Jun 2026 | 26 Jun 2026Asite issue | P01 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-92030Omegariser Level 4 Grid 4-8 General Arrangement | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | P01 | PendingAwaiting Design Review | 22 Jul 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-91125Olympus - LCY11 22034 - GL 8 - 14 - Phase 31 to 36 MTO Steelwork Plan @+57.440m (Int G2) | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91624Olympus - LCY11 22034 - GL 8 - 14 - Phase 31 to 36 MTO Steelwork Elevation on GL F | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-91122Olympus - LCY11 22034 - GL 8 - 14 - Phase 31 to 36 MTO Steelwork Plan @+48.360m (G1) | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01505Area 5 - Grids E-H K-ROC GA West Elevation | DR - Drawing (DR) | FAC | 15 Jun 2026 | 26 Jun 2026Asite issue | P01 | BAccepted with comments | 28 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-91126Olympus - LCY11 22034 - GL 8 - 14 - Phase 31 to 36 MTO Steelwork Plan @+57.440m (Int G2) | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-92031Omegariser Level 3 Grid 4-8 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-92031Omegariser Level 1 Grid 4-8 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91621Olympus - LCY11 22034 - GL 8 - 14 - Phase 31 to 36 MTO Steelwork Elevation on GL K | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-91128Olympus - LCY11 22034 - GL 8 - 14 - Phase 31 to 36 MTO Steelwork Plan @+60.440m (R3) | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91622Olympus - LCY11 22034 - GL 8 - 14 - Phase 31 to 36 MTO Steelwork Elevation on GL J | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01673Area 6 - Grids B-E K-ROC Lower Building GA East Elevation | DR - Drawing (DR) | FAC | 15 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-92031Omegariser Level 5 Grid 4-8 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91626Olympus - LCY11 22034 - GL 8 - 14 - Phase 31 to 36 MTO Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-91129Olympus - LCY11 22034 - GL 8 - 14 - Phase 31 to 36 MTO Steelwork Plan @+63.700m (TOP PARRAPET) | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92030Omegariser Level 6 Grid 4-8 General Arrangement | DR - Drawing (DR) | STR | 15 Jun 2026 | 15 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01675Area 6 - Grids H-J K-ROC Lower Building GA East Elevation | DR - Drawing (DR) | FAC | 15 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-20034Olympus - LCY11 22031 - GL 23-26 - Phases 23 to 29 Steelwork Foundation Details - Sheet 4 | DR - Drawing (DR) | STR | 16 Jun 2026 | 16 Jun 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-40034Olympus - LCY11 22032 - GL 01-06 - Phases 43 TO 47 Steelwork Foundation Details - Sheet 4 | DR - Drawing (DR) | STR | 16 Jun 2026 | 16 Jun 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-40035Olympus - LCY11 22032 - GL 01-06 - Phases 43 TO 47 Steelwork Foundation Details - Sheet 5 | DR - Drawing (DR) | STR | 16 Jun 2026 | 16 Jun 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00045Trade Contractor Weekly Report | RP - Report (RP) | STR | 16 Jun 2026 | 16 Jun 2026Asite issue | C01 | For InformationNo approval required | 18 Jun 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-20036Olympus - LCY11 22031 - GL 23-26 - Phases 23 to 29 Steelwork Foundation Details - Sheet 6 | DR - Drawing (DR) | STR | 16 Jun 2026 | 16 Jun 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-20035Olympus - LCY11 22031 - GL 23-26 - Phases 23 to 29 Steelwork Foundation Details - Sheet 5 | DR - Drawing (DR) | STR | 16 Jun 2026 | 16 Jun 2026Asite issue | C01 | BAccepted with comments | 07 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00045Trade Contractor Weekly Report | RP - Report (RP) | STR | 16 Jun 2026 | 16 Jun 2026Asite issue | C01 | For InformationNo approval required | 18 Jun 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-04000Dust Canopy Cladding Specification Drawing | DR - Drawing (DR) | FAC | 17 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03206Internal Flue Details 7 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 16 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01923Internal Flue - K-ROC GA Elevation 4 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 09 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03210Internal Flue Details 11 | DR - Drawing (DR) | FAC | 22 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03201Internal Flue Details 2 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 16 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03209Internal Flue Details 10 | DR - Drawing (DR) | FAC | 22 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03202Internal Flue Details 3 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 16 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01927Internal Flue - K-ROC GA Elevation 8 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 09 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01921Internal Flue - K-ROC GA Elevation 2 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 09 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03204Internal Flue Details 5 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 16 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03207Internal Flue Details 8 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 16 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03203Internal Flue Details 4 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 16 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03200Internal Flue Details 1 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 09 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01922Internal Flue - K-ROC GA Elevation 3 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 09 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03205Internal Flue Details 6 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 16 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01925Internal Flue - K-ROC GA Elevation 6 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 09 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01926Internal Flue - K-ROC GA Elevation 7 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 09 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01920Internal Flue - K-ROC GA Elevation 1 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 09 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01924Internal Flue - K-ROC GA Elevation 5 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 09 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03208Internal Flue Details 9 | DR - Drawing (DR) | FAC | 22 Jun 2026 | 16 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01928Internal Flue - K-ROC GA Elevation 9 | DR - Drawing (DR) | FAC | 22 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-92041Omegariser Level 5 Grid 22-25 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 23 Jun 2026 | 23 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-92042Omegariser Level 5 Grid 22-25 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 23 Jun 2026 | 23 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92042Omegariser Level 6 Grid 22-25 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 23 Jun 2026 | 23 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-92041Omegariser Level 4 Grid 22-25 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 23 Jun 2026 | 23 Jun 2026Asite issue | P01 | CRejected | 28 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92040Omegariser Level 6 Grid 22-25 General Arrangement | DR - Drawing (DR) | STR | 23 Jun 2026 | 23 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-92042Omegariser Level 4 Grid 22-25 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 23 Jun 2026 | 23 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92041Omegariser Level 6 Grid 22-25 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 23 Jun 2026 | 23 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-92040Omegariser Level 4 Grid 22-25 General Arrangement | DR - Drawing (DR) | STR | 23 Jun 2026 | 23 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-92040Omegariser Level 3 Grid 22-25 General Arrangement | DR - Drawing (DR) | STR | 23 Jun 2026 | 23 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-92041Omegariser Level 3 Grid 22-25 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 23 Jun 2026 | 23 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-92042Omegariser Level 3 Grid 22-25 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 23 Jun 2026 | 23 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-92040Omegariser Level 5 Grid 22-25 General Arrangement | DR - Drawing (DR) | STR | 23 Jun 2026 | 23 Jun 2026Asite issue | P01 | CRejected | 29 Jun 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-22501Olympus - LCY11 22031 - GL 18-22 - Phase 22 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91616Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-04004PERFORATED PLANK SPECIFICATION | DR - Drawing (DR) | FAC | 24 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-2314122031 - GL 22-26 - Phases 23 to 27 ComFlor 80 and Shear Stud Layout to L01 | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-91119Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Plan @+63.700m (Top Parrapet) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-22501Olympus - LCY11 22031 - GL 18-22 - Phase 22 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-04002TYPICAL K-ROC SPECIFICATION (INTERNAL FLUE) | DR - Drawing (DR) | FAC | 24 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91613Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Elevation on GL G | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91618Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Elevation on GL 25 | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91614Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Elevation on GL F | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-21401Olympus - LCY11 22031 - GL 18-22 - Phase 21 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 05 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-21201Olympus - LCY11 22031 - GL 18-22 - Phase 21 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 05 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91617Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Elevation on GL 23 | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-91111Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Plan @+48.360m (G1) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-19301Olympus - LCY11 22031 - GL 18-22 - Phase 19 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-21201Olympus - LCY11 22031 - GL 18-22 - Phase 21 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 05 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-91112Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Plan @+48.360m (G1) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-22101Olympus - LCY11 22031 - GL 18-22 - Phase 22 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-20031Olympus - LCY11 22031 - GL 20-26 - Phases 20 to 29 Steelwork Foundation Details - Sheet 1 | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91620Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Elevation on Stair Plan | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 22 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91615Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Elevation on GL B | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-20033Olympus - LCY11 22031 - GL 20-26 - Phases 20 to 29 Steelwork Foundation Details - Sheet 3 | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-1754522031 - GL 18-22 - Phases 17 to 22 ComFlor 80 and Shear Stud Layout to L05 | DR - Drawing (DR) | STR | 24 Jun 2026 | 30 Jun 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-19201Olympus - LCY11 22031 - GL 18-22 - Phase 19 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-1744422031 - GL 18-22 - Phases 17 to 22 ComFlor 80 and Shear Stud Layout to L04 | DR - Drawing (DR) | STR | 24 Jun 2026 | 30 Jun 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-91118Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Plan @+60.440m (R3) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-91114Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Plan @+54.440m (G2) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-19101Olympus - LCY11 22031 - GL 18-22 - Phase 19 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-1734322031 - GL 18-22 - Phases 17 to 22 ComFlor 80 and Shear Stud Layout to L03 | DR - Drawing (DR) | STR | 24 Jun 2026 | 30 Jun 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-21501Olympus - LCY11 22031 - GL 18-22 - Phase 21 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-18201Olympus - LCY11 22031 - GL 18-22 - Phase 18 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-19301Olympus - LCY11 22031 - GL 18-22 - Phase 19 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-20033Olympus - LCY11 22031 - GL 20-26 - Phases 20 to 29 Steelwork Foundation Details - Sheet 3 | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-20101Olympus - LCY11 22031 - GL 18-22 - Phase 20 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-20101Olympus - LCY11 22031 - GL 18-22 - Phase 20 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-21301Olympus - LCY11 22031 - GL 18-22 - Phase 21 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-19401Olympus - LCY11 22031 - GL 18-22 - Phase 19 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-20032Olympus - LCY11 22031 - GL 20-26 - Phases 20 to 29 Steelwork Foundation Details - Sheet 2 | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91619Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Elevation on GL 25 | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-91116Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Plan @+57.440m (Int G2) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-91113Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Plan @+54.440m (G2) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-0400377mm BRICKCLAD SPECIFICATION | DR - Drawing (DR) | FAC | 24 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-21501Olympus - LCY11 22031 - GL 18-22 - Phase 21 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-20031Olympus - LCY11 22031 - GL 20-26 - Phases 20 to 29 Steelwork Foundation Details - Sheet 1 | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-22401Olympus - LCY11 22031 - GL 18-22 - Phase 22 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-18301Olympus - LCY11 22031 - GL 18-22 - Phase 18 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-22301Olympus - LCY11 22031 - GL 18-22 - Phase 22 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-19401Olympus - LCY11 22031 - GL 18-22 - Phase 19 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-18401Olympus - LCY11 22031 - GL 18-22 - Phase 18 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 05 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-18401Olympus - LCY11 22031 - GL 18-22 - Phase 18 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 05 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-22401Olympus - LCY11 22031 - GL 18-22 - Phase 22 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91611Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Elevation on GL K | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-22101Olympus - LCY11 22031 - GL 18-22 - Phase 22 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-21301Olympus - LCY11 22031 - GL 18-22 - Phase 21 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-20032Olympus - LCY11 22031 - GL 20-26 - Phases 20 to 29 Steelwork Foundation Details - Sheet 2 | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-17101Olympus - LCY11 22031 - GL 18-22 - Phase 17 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-04006DIGITAL LINE SPECIFICATION | DR - Drawing (DR) | FAC | 24 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-91117Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Plan @+60.440m (R3) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91612Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Elevation on GL J | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-18301Olympus - LCY11 22031 - GL 18-22 - Phase 18 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-04005300mm DEEP RAINSCREEN SPECIFICATION | DR - Drawing (DR) | FAC | 24 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-19201Olympus - LCY11 22031 - GL 18-22 - Phase 19 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-91115Olympus - LCY11 22033 - GL 20 - 26- Phase 18 to 23 MTO Steelwork Plan @+57.440m (Int G2) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-18201Olympus - LCY11 22031 - GL 18-22 - Phase 18 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-19101Olympus - LCY11 22031 - GL 18-22 - Phase 19 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-22301Olympus - LCY11 22031 - GL 18-22 - Phase 22 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-17101Olympus - LCY11 22031 - GL 18-22 - Phase 17 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-21401Olympus - LCY11 22031 - GL 18-22 - Phase 21 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 24 Jun 2026 | 24 Jun 2026Asite issue | C03 | AAccepted | 05 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-91138Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Plan @+60.440m (R3) | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-91137Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Plan @+60.440m (R3) | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-91136Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Plan @+57.440m (Int G2) | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-91133Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Plan @+54.440m (G2) | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-91135Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Plan @+57.440m (Int G2) | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91632Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Elevation on GL J | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28305Connection No.: 28305 | CA - Calculations (CA) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28203Connection No.: 28203 | CA - Calculations (CA) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-91139Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Plan @+63.700m (TOP PARRAPET) | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91631Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Elevation on GL K | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28310Connection No.: 28310 | CA - Calculations (CA) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91634Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Elevation on GL F | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91639Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Elevation on GL 4 | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91633Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Elevation on GL G | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91636Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-91134Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Plan @+54.440m (G2) | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91637Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Elevation on GL 4 | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28203Connection No.: 28203 | CA - Calculations (CA) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29135Connection No.: 29135 | CA - Calculations (CA) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91638Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Elevation on GL 4 | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-91131Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Plan @+48.360m (G1) | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-91132Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Plan @+48.360m (G1) | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29135Connection No.: 29135 | CA - Calculations (CA) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91640Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Stair Plan | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 07 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-91635Olympus - LCY11 22033 - GL1 - 8- Phase 37 to 40 MTO Steelwork Elevation on GL B | DR - Drawing (DR) | STR | 25 Jun 2026 | 25 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28634Connection No.: 28634 | CA - Calculations (CA) | STR | 27 Jun 2026 | 27 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-5774722031 - GL 18-22 - Phases 57 to 62 ComFlor 80 and Shear Stud Layout to R01 | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-7774722032 - GL 06-10 - Phases 77 to 82 ComFlor 80 and Shear Stud Layout to R1 | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-85620Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Temporary Steelwork Elevation on GL 05 | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28631Connection No.: 28631 | CA - Calculations (CA) | STR | 27 Jun 2026 | 27 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28627Connection No.: 28627 | CA - Calculations (CA) | STR | 27 Jun 2026 | 27 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-83701Olympus - LCY11 22032 - GL 02-06 - Phase 83 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28633Connection No.: 28633 | CA - Calculations (CA) | STR | 27 Jun 2026 | 27 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-83601Olympus - LCY11 22032 - GL 02-06 - Phase 83 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28636Connection No.: 28636 | CA - Calculations (CA) | STR | 27 Jun 2026 | 27 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28626Connection No.: 28626 | CA - Calculations (CA) | STR | 27 Jun 2026 | 27 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28641Connection No.: 28641 | CA - Calculations (CA) | STR | 27 Jun 2026 | 27 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28639Connection No.: 28639 | CA - Calculations (CA) | STR | 27 Jun 2026 | 27 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28630Connection No.: 28630 | CA - Calculations (CA) | STR | 27 Jun 2026 | 27 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28635Connection No.: 28635 | CA - Calculations (CA) | STR | 27 Jun 2026 | 27 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28629Connection No.: 28629 | CA - Calculations (CA) | STR | 27 Jun 2026 | 27 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-83611Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Steelwork Elevation on GL F | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28640Connection No.: 28640 | CA - Calculations (CA) | STR | 27 Jun 2026 | 27 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-83621Olympus - LCY11 22032 - GL 02-06 - Phase 83 to 85 Cell Sheild Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C01 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-84610Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Steelwork Elevation on GL I | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28632Connection No.: 28632 | CA - Calculations (CA) | STR | 27 Jun 2026 | 27 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-83622Olympus - LCY11 22032 - GL 02-06 - Phase 83 to 85 Cell Sheild Pots @+39.440m (L06) | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C01 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-85612Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Steelwork Elevation on GL C | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28638Connection No.: 28638 | CA - Calculations (CA) | STR | 27 Jun 2026 | 27 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-83614Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Steelwork Elevation on GL 05 (GL E TO H) | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-83722Olympus - LCY11 22032 - GL 02-06 - Phase 83 to 85 Cellshield Pot @ +45.940m (R01) | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C01 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-83616Olympus - LCY11 22032 - GL 02-06 - Phases 83 Steelwork Section View | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-83612Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Steelwork Elevation on GL G | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28628Connection No.: 28628 | CA - Calculations (CA) | STR | 27 Jun 2026 | 27 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-85613Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Steelwork Elevation on GL D | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-83613Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Steelwork Elevation on GL H | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-83721Olympus - LCY11 22032 - GL 02-06 - Phase 83 to 85 Cellshield Plan @ +45.940m (R01) | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C01 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-83615Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Steelwork Elevation on GL 04 (GL E TO H) | DR - Drawing (DR) | STR | 27 Jun 2026 | 28 Jun 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28637Connection No.: 28637 | CA - Calculations (CA) | STR | 27 Jun 2026 | 27 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28304Connection No.: 28304 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28300Connection No.: 28300 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29231Connection No.: 29231 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29230Connection No.: 29230 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29233Connection No.: 29233 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29229Connection No.: 29229 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28297Connection No.: 28297 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99211Temporary Works – TW10-01 – G1/G2 Leave Out Steel | TW - Temporary Works (TW) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | PendingAwaiting Design Review | 07 Aug 2026 | Awaiting Design ReviewFAILED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28303Connection No.: 28303 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29227Connection No.: 29227 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29211Connection No.: 29211 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29224Connection No.: 29224 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29257Connection No.: 29257 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29124Connection No.: 29124 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C05 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29225Connection No.: 29225 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28299Connection No.: 28299 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29256Connection No.: 29256 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29228Connection No.: 29228 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29255Connection No.: 29255 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29124Connection No.: 29124 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C05 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29219Connection No.: 29219 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28302Connection No.: 28302 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29254Connection No.: 29254 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28301Connection No.: 28301 | CA - Calculations (CA) | STR | 29 Jun 2026 | 29 Jun 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05304Gantry Louvres South Details 4 | DR - Drawing (DR) | FAC | 30 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05305Gantry Louvres South Details 5 | DR - Drawing (DR) | FAC | 30 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-G1-DR-X-00039East Elevation Lug Setting 10 | DR - Drawing (DR) | FAC | 30 Jun 2026 | 16 Jun 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-G2-DR-X-00071West Elevation Lug Setting 12 | DR - Drawing (DR) | FAC | 30 Jun 2026 | 16 Jun 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05105Gantry Louvres South GA Section 5 | DR - Drawing (DR) | FAC | 30 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-G2-DR-X-00041East Elevation Lug Setting 12 | DR - Drawing (DR) | FAC | 30 Jun 2026 | 16 Jun 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05004Gantry Louvres South GA Elevation 4 | DR - Drawing (DR) | FAC | 30 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-G2-DR-X-00040East Elevation Lug Setting 11 | DR - Drawing (DR) | FAC | 30 Jun 2026 | 16 Jun 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05005Gantry Louvres South GA Elevation 5 | DR - Drawing (DR) | FAC | 30 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00047Trade Contractor Weekly Report | RP - Report (RP) | STR | 30 Jun 2026 | 30 Jun 2026Asite issue | C01 | For InformationNo approval required | 30 Jun 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-G2-DR-X-00070West Elevation Lug Setting 11 | DR - Drawing (DR) | FAC | 30 Jun 2026 | 16 Jun 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-G1-DR-X-00038East Elevation Lug Setting 9 | DR - Drawing (DR) | FAC | 30 Jun 2026 | 16 Jun 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05104Gantry Louvres South GA Section 4 | DR - Drawing (DR) | FAC | 30 Jun 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00047Trade Contractor Weekly Report | RP - Report (RP) | STR | 30 Jun 2026 | 30 Jun 2026Asite issue | C01 | For InformationNo approval required | 30 Jun 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-G1-DR-X-00069West Elevation Lug Setting 10 | DR - Drawing (DR) | FAC | 30 Jun 2026 | 16 Jun 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-G1-DR-X-00068West Elevation Lug Setting 9 | DR - Drawing (DR) | FAC | 30 Jun 2026 | 16 Jun 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-38014Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL 08 (GL H to K) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-40011Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL 06 (GL E to H) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-37013Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL 09 (GL E to H) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-42501Olympus - LCY11 22032 - GL 06-10 - Phase 42 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-41301Olympus - LCY11 22032 - GL 06-10 - Phase 41 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-39201Olympus - LCY11 22032 - GL 06-10 - Phase 39 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-42501Olympus - LCY11 22032 - GL 06-10 - Phase 42 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-41301Olympus - LCY11 22032 - GL 06-10 - Phase 41 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-39301Olympus - LCY11 22032 - GL 06-10 - Phase 39 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-37017Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL G | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-37301Olympus - LCY11 22032 - GL 06-10 - Phase 37 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-38301Olympus - LCY11 22032 - GL 06-10 - Phase 38 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-38201Olympus - LCY11 22032 - GL 06-10 - Phase 38 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28326Connection No.: 28326 | CA - Calculations (CA) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28651Connection No.: 28651 | CA - Calculations (CA) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-42301Olympus - LCY11 22032 - GL 06-10 - Phase 42 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-40301Olympus - LCY11 22032 - GL 06-10 - Phase 40 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-38301Olympus - LCY11 22032 - GL 06-10 - Phase 38 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-34421Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Cell Shield Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | For InformationNo approval required | 01 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-40301Olympus - LCY11 22032 - GL 06-10 - Phase 40 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-34221Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Cell Shield Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | For InformationNo approval required | 01 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-72701Steelwork Plan @+45.940m (R01) - Phase 72 | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-40014Olympus - LCY11 22032 - GL 06-10 - Phase 40 Temporary Steelwork Elevation on GL 6 | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 05 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-76611Steelwork Elevation on GL 10 LVL 6 to R1 (GL A to E) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-39501Olympus - LCY11 22032 - GL 06-10 - Phase 39 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-40201Olympus - LCY11 22032 - GL 06-10 - Phase 40 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-37501Olympus - LCY11 22032 - GL 06-10 - Phase 37 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-40013Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL 07 (GL E to H) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-76601Steelwork Plan @+39.440m (L06) - Phase 76 | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-38013Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL 09 (GL H to K) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-37101Olympus - LCY11 22032 - GL 06-10 - Phase 37 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-40012Olympus - LCY11 22032 - GL 06-10 - Phase 40 Temporary Steelwork Elevation on GL 7 | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-38501Olympus - LCY11 22032 - GL 06-10 - Phase 38 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29253Connection No.: 29253 | CA - Calculations (CA) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-37501Olympus - LCY11 22032 - GL 06-10 - Phase 37 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29246Connection No.: 29246 | CA - Calculations (CA) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28323Connection No.: 28323 | CA - Calculations (CA) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28324Connection No.: 28324 | CA - Calculations (CA) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-75701Steelwork Plan @+45.940m (R01) - Phase 75 | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-41401Olympus - LCY11 22032 - GL 06-10 - Phase 41 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-39401Olympus - LCY11 22032 - GL 06-10 - Phase 39 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-37401Olympus - LCY11 22032 - GL 06-10 - Phase 37 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-42301Olympus - LCY11 22032 - GL 06-10 - Phase 42 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-41501Olympus - LCY11 22032 - GL 06-10 - Phase 41 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-39014Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL 09 (GL A to E) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-38101Olympus - LCY11 22032 - GL 06-10 - Phase 38 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | BAccepted with comments | 20 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-37301Olympus - LCY11 22032 - GL 06-10 - Phase 37 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-34422Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Cell Shield Pots @+26.440m (L04) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | For InformationNo approval required | 01 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-37016Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL F | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-39015Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL 08 (GL A to E) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-39101Olympus - LCY11 22032 - GL 06-10 - Phase 39 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | BAccepted with comments | 20 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-38101Olympus - LCY11 22032 - GL 06-10 - Phase 38 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | BAccepted with comments | 20 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-40013Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL 07 (GL E to H) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-37401Olympus - LCY11 22032 - GL 06-10 - Phase 37 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-40012Olympus - LCY11 22032 - GL 06-10 - Phase 40 Temporary Steelwork Elevation on GL 7 | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-38501Olympus - LCY11 22032 - GL 06-10 - Phase 38 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28325Connection No.: 28325 | CA - Calculations (CA) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-42101Olympus - LCY11 22032 - GL 06-10 - Phase 42 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-41101Olympus - LCY11 22032 - GL 06-10 - Phase 41 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-42010Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL 07 (GL A to E) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-73701Steelwork Plan @+45.940m (R01) - Phase 73 | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-34222Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Cell Shield Pots @+13.440m (L02) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | For InformationNo approval required | 01 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-39201Olympus - LCY11 22032 - GL 06-10 - Phase 39 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-37201Olympus - LCY11 22032 - GL 06-10 - Phase 37 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-41101Olympus - LCY11 22032 - GL 06-10 - Phase 41 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-34321Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Cell Shield Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | For InformationNo approval required | 01 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-41010Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL 07 (GL H to K) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-34322Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Cell Shield Pots @+19.940m (L03) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | For InformationNo approval required | 01 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-38401Olympus - LCY11 22032 - GL 06-10 - Phase 38 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-40401Olympus - LCY11 22032 - GL 06-10 - Phase 40 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-76701Steelwork Plan @+45.940m (R01) - Phase 76 | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-42401Olympus - LCY11 22032 - GL 06-10 - Phase 42 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-39101Olympus - LCY11 22032 - GL 06-10 - Phase 39 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | BAccepted with comments | 20 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-37011Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL 08 (GL E to H) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-72601Steelwork Plan @+39.440m (L06) - Phase 72 | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-40201Olympus - LCY11 22032 - GL 06-10 - Phase 40 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-38201Olympus - LCY11 22032 - GL 06-10 - Phase 38 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-38012Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL K | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-39401Olympus - LCY11 22032 - GL 06-10 - Phase 39 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-39010Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-75601Steelwork Plan @+39.440m (L06) - Phase 75 | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-73601Steelwork Plan @+39.440m (L06) - Phase 73 | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-37101Olympus - LCY11 22032 - GL 06-10 - Phase 37 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-39501Olympus - LCY11 22032 - GL 06-10 - Phase 39 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-40011Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL 06 (GL E to H) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-37013Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL 09 (GL E to H) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-41501Olympus - LCY11 22032 - GL 06-10 - Phase 41 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-42101Olympus - LCY11 22032 - GL 06-10 - Phase 42 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-39016Olympus - LCY11 22032 - GL 06-10 - Phase 39 Temporary Steelwork Elevation on GL 8 & 9 | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-40014Olympus - LCY11 22032 - GL 06-10 - Phase 40 Temporary Steelwork Elevation on GL 6 | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 05 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-71701Steelwork Plan @+45.940m (R01) - Phase 71 | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-37201Olympus - LCY11 22032 - GL 06-10 - Phase 37 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-41401Olympus - LCY11 22032 - GL 06-10 - Phase 41 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-37011Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL 08 (GL E to H) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-42401Olympus - LCY11 22032 - GL 06-10 - Phase 42 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-40401Olympus - LCY11 22032 - GL 06-10 - Phase 40 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-38401Olympus - LCY11 22032 - GL 06-10 - Phase 38 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-37019Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation & Detail Views | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-39301Olympus - LCY11 22032 - GL 06-10 - Phase 39 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 01 Jul 2026 | 01 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-92020RiserSafe Level 4 Grid 18-22 General Arrangement | DR - Drawing (DR) | STR | 02 Jul 2026 | 02 Jul 2026Asite issue | C01 | CRejected | 06 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-92021RiserSafe Level 2 Grid 18-22 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 02 Jul 2026 | 02 Jul 2026Asite issue | C01 | CRejected | 06 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-92023Omegariser Level 5 grid 18-22 Plan Views | DR - Drawing (DR) | STR | 02 Jul 2026 | 02 Jul 2026Asite issue | C01 | CRejected | 28 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-92021RiserSafe Level 4 Grid 18-22 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 02 Jul 2026 | 02 Jul 2026Asite issue | C01 | CRejected | 06 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-92020RiserSafe Level 3 Grid 18-22 General Arrangement | DR - Drawing (DR) | STR | 02 Jul 2026 | 02 Jul 2026Asite issue | C01 | CRejected | 06 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-92020RiserSafe Level 2 Grid 18-22 General Arrangement | DR - Drawing (DR) | STR | 02 Jul 2026 | 02 Jul 2026Asite issue | C01 | CRejected | 06 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-92022RiserSafe Level 2 Grid 18-22 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 02 Jul 2026 | 02 Jul 2026Asite issue | C01 | CRejected | 06 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-92023Omegariser Level 3 grid 18-22 Plan Views | DR - Drawing (DR) | STR | 02 Jul 2026 | 02 Jul 2026Asite issue | C01 | CRejected | 28 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-92020RiserSafe Level 5 Grid 18-22 General Arrangement | DR - Drawing (DR) | STR | 02 Jul 2026 | 02 Jul 2026Asite issue | C01 | CRejected | 06 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-92021RiserSafe Level 3 Grid 18-22 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 02 Jul 2026 | 02 Jul 2026Asite issue | C01 | CRejected | 06 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-92023Omegariser Level 4 grid 18-22 Plan Views | DR - Drawing (DR) | STR | 02 Jul 2026 | 02 Jul 2026Asite issue | C01 | CRejected | 28 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-92022RiserSafe Level 3 Grid 18-22 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 02 Jul 2026 | 02 Jul 2026Asite issue | C01 | CRejected | 06 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-92022RiserSafe Level 5 Grid 18-22 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 02 Jul 2026 | 02 Jul 2026Asite issue | C01 | CRejected | 06 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-92021RiserSafe Level 5 Grid 18-22 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 02 Jul 2026 | 02 Jul 2026Asite issue | C01 | CRejected | 06 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-92022RiserSafe Level 4 Grid 18-22 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 02 Jul 2026 | 02 Jul 2026Asite issue | C01 | CRejected | 06 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29001CMP Connection No.:29001 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C05 | For InformationNo approval required | 06 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-11343ComFlor 80 and Shear Stud Layout to Third Floor - GL 14-18 - Phases 11-16 | DR - Drawing (DR) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-11242ComFlor 80 and Shear Stud Layout to Second Floor - GL 14-18 - Phases 11-16 | DR - Drawing (DR) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29109Connection No.: 29109 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29120Connection No.: 29120 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C04 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29109Connection No.: 29109 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29121Connection No.: 29121 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29121Connection No.: 29121 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-31002Steelwork Foundation Plan on GL08 to 14 (GL A to E) | DR - Drawing (DR) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-5174722031 - GL 14-18 - Phases 51 to 56 ComFlor 80 and Shear Stud Layout to R01 | DR - Drawing (DR) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29127Connection No.: 29127 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-ZZ-CA-S-29001CMP Connection No.:29001 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C05 | For InformationNo approval required | 06 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29127Connection No.: 29127 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29128Connection No.: 29128 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-31002Steelwork Foundation Plan on GL08 to 14 (GL A to E) | DR - Drawing (DR) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29128Connection No.: 29128 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29116Connection No.: 29116 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29118Connection No.: 29118 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29120Connection No.: 29120 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C04 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-11444ComFlor 80 and Shear Stud Layout to Fourth Floor - GL 14-18 - Phases 11-16 | DR - Drawing (DR) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28109Connection No.: 28109 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-51601OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29118Connection No.: 29118 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29208Connection No.: 29208 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-5164622031 - GL 14-18 - Phases 51 to 56 ComFlor 80 and Shear Stud Layout to L06 | DR - Drawing (DR) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29209Connection No.: 29209 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29116Connection No.: 29116 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28109Connection No.: 28109 | CA - Calculations (CA) | STR | 04 Jul 2026 | 05 Jul 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29132Connection No.: 29132 | CA - Calculations (CA) | STR | 05 Jul 2026 | 03 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29132Connection No.: 29132 | CA - Calculations (CA) | STR | 05 Jul 2026 | 03 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00048Trade Contractor Weekly Report | RP - Report (RP) | STR | 06 Jul 2026 | 06 Jul 2026Asite issue | C01 | For InformationNo approval required | 07 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92010Risersafe Level 6 Grid 8-12 General Arrangement | DR - Drawing (DR) | STR | 06 Jul 2026 | 06 Jul 2026Asite issue | P02 | CRejected | 06 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-CA-X-00009K-ROC Karrier Support Rail & Connections at Internal Flues | CA - Calculations (CA) | FAC | 06 Jul 2026 | 06 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-CA-X-00007RS-2 Facade Perforated plank structural analysis | CA - Calculations (CA) | FAC | 06 Jul 2026 | 06 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92011Risersafe Level 6 Grid 8-12 Plan views Sheet 1 | DR - Drawing (DR) | STR | 06 Jul 2026 | 06 Jul 2026Asite issue | P02 | CRejected | 06 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00048Trade Contractor Weekly Report | RP - Report (RP) | STR | 06 Jul 2026 | 06 Jul 2026Asite issue | C01 | For InformationNo approval required | 07 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-92012Risersafe Level 6 Grid 8-12 Plan views Sheet 2 | DR - Drawing (DR) | STR | 06 Jul 2026 | 06 Jul 2026Asite issue | P02 | CRejected | 06 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-CA-X-00010K-ROC Karrier Support Rail & Connections at Staircores | CA - Calculations (CA) | FAC | 06 Jul 2026 | 06 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-20013Steelwork Elevation on GL 22 Lvl 0 TO 5 (GL E TO H) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-22010Steelwork Elevation on GL 21 Lvl 0 TO 5 (GL A TO E) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-21010Steelwork Elevation on GL 21 Lvl 0 TO 5 (GL H TO K) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-17017Steelwork Elevation on GL G Lvl 0 TO 5 (GL 18 TO 22) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-21011Steelwork Elevation on GL 22 LVL 0 TO 5 (GL H TO K) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-17030Steelwork Foundation Plan - Coupler Setting Out - Phase 17 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-17521Cellshield Plan @+32.940m (L05) Phases 17 To 22 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-17019Steelwork Section & Detail Views - 17 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-21030Steelwork Foundation Plan - Coupler Setting Out - Phase 21 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-22030Steelwork Foundation Plan - Coupler Setting Out - Phase 22 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-19016Temporary Steelwork Elevation on GL 19 & 20 Lvl 0 to 5 (GL C to E) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | CancelledWorkflow cancelled | 07 Jul 2026 | Cancelled WorkflowCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-18014Steelwork Elevation on GL 20 Lvl 0 TO 5 (GL H TO K) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-19014Steelwork Elevation on GL 19 Lvl 0 TO 5 (GL A TO E) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-17016Steelwork Elevation on GL F Lvl 0 TO 5 (GL 18 TO 22) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-18013Steelwork Elevation on GL 19 Lvl 0 To 5 (GL H To K) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-22012Temporary Steelwork Elevation on GL 21 & 22 Lvl 0 to 5 (GL C to E) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | CancelledWorkflow cancelled | 07 Jul 2026 | Cancelled WorkflowCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-17322Cell Shield Pots GA @+19.940m (L03) Phase 17 To 22 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-18030Steelwork Foundation Plan - Coupler Setting Out - Phase 18 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-20011Steelwork Elevation on GL 21 Lvl 0 TO 5 (GL E TO H) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-19015Steelwork Elevation on GL 20 Lvl 0 TO 5 (GL A TO E) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-22011Steelwork Elevation on 22 Lvl 0 TO 5 (GL A TO E) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-26011Olympus - LCY11 22031 - GL 22-26 - Phase 23 to 29 Steelwork Elevation on GL 25 (GL F to K) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-19030Steelwork Foundation Plan - Coupler Setting Out - Phase 19 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-17221Cellshield Plan @+13.440m (L02) Phases 17 To 22 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-17222Cell Shield Pots GA @+13.440m (L02) Phase 17 To 22 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-17422Cell Shield Pots GA @+26.440m (L04) Phase 17 To 22 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | QA Accepted | 30 Jul 2026 | QA AcceptedCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-17321Cellshield Plan @+19.940m (L03) Phases 17 To 22 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-20030Steelwork Foundation Plan - Coupler Setting Out - Phase 20 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-17522Cell Shield Pots GA @+32.940m (L05) Phase 17 To 22 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | QA Accepted | 30 Jul 2026 | QA AcceptedCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-17421Cellshield Plan @+26.440m (L04) Phases 17 To 22 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-17401Steelwork Plan @+26.440m (L04) - Phase 17 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-CA-S-28012CMP Level 6 (Zone A) Plan +39.440 SSL | CA - Calculations (CA) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C08 | For InformationNo approval required | 07 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-20201Steelwork Plan @+13.440m (L02) - Phase 20 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-17201Steelwork Plan @+13.440m (L02) - Phase 17 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-22201Steelwork Plan @+13.440m (L02) - Phase 22 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-18101Steelwork Plan @+8.940m (L01) - Phase 18 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-CA-S-28013CMP Level 6 (Zone B) Plan +39.440 SSL | CA - Calculations (CA) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C09 | For InformationNo approval required | 07 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-21101Steelwork Plan @+8.940m (L01) - Phase 21 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-20401Steelwork Plan @+26.440m (L04) - Phase 20 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 05 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-17501Steelwork Plan @+32.940m (L05) - Phase 17 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-19501Steelwork Plan @+32.940m (L05) - Phase 19 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-28011Olympus - LCY11 22031 - GL 22-26 - Phase 23 to 29 Steelwork Elevation on GL 26 (GL F to K) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-18501Steelwork Plan @+32.940m (L05) - Phase 18 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-20501Steelwork Plan @+32.940m (L05) - Phase 20 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-17013Steelwork Elevation on GL 20 Lvl 0 TO 5 (GL E TO H) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-17301Steelwork Plan @+19.940m (L03) - Phase 17 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-20301Steelwork Plan @+19.940m (L03) - Phase 20 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-17011Steelwork Elevation on GL 19 Lvl 0 TO 5 (GL E To H) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-26011Olympus - LCY11 22031 - GL 22-26 - Phase 23 to 29 Steelwork Elevation on GL 25 (GL F to K) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-20013Steelwork Elevation on GL 22 Lvl 0 TO 5 (GL E TO H) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29258Connection No.: 29258 | CA - Calculations (CA) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C01 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-28011Olympus - LCY11 22031 - GL 22-26 - Phase 23 to 29 Steelwork Elevation on GL 26 (GL F to K) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03039East Rainscreen Details 10 | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03065West Rainscreen Details 6 | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-17013Steelwork Elevation on GL 20 Lvl 0 TO 5 (GL E TO H) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29264Connection No.: 29264 | CA - Calculations (CA) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28242Connection No.: 28242 | CA - Calculations (CA) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29260Connection No.: 29260 | CA - Calculations (CA) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01631Area 6 - Grids H-J 300mm Deep Rainscreen Backing Grid GA East Elevation | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01512Area 5 - Grids H-J 300mm Deep Rainscreen Backing Grid GA West Elevation | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01629Area 6 - Grids B-E 300mm Deep Rainscreen Backing Grid GA East Elevation | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01510Area 5 - Grids B-E 300mm Deep Rainscreen Backing Grid GA West Elevation | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01630Area 6 - Grids E-H 300mm Deep Rainscreen Backing Grid GA East Elevation | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01511Area 5 - Grids E-H 300mm Deep Rainscreen Backing Grid GA West Elevation | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01628Area 6 - Grids H-J Perforated Plank Backing Grid GA East Elevation | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-06-CA-S-28012CMP Level 6 (Zone A) Plan +39.440 SSL | CA - Calculations (CA) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C08 | For InformationNo approval required | 07 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-20201Steelwork Plan @+13.440m (L02) - Phase 20 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01522Area 5 - Lift Core Built-Up GA Elevation 3 | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01509Area 5 - Grids H-J Perforated Plank Backing Grid GA West Elevation | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01627Area 6 - Grids E-H Perforated Plank Backing Grid GA East Elevation | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01521Area 5 - Lift Core Built-Up GA Elevation 2 | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01508Area 5 - Grids E-H Perforated Plank Backing Grid GA West Elevation | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-17011Steelwork Elevation on GL 19 Lvl 0 TO 5 (GL E To H) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-20011Steelwork Elevation on GL 21 Lvl 0 TO 5 (GL E TO H) | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01626Area 6 - Grids B-E Perforated Plank Backing Grid GA East Elevation | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01520Area 5 - Lift Core Built-Up GA Elevation 1 | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01507Area 5 - Grids B-E Perforated Plank Backing Grid GA West Elevation | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03066West Rainscreen Details 7 | DR - Drawing (DR) | FAC | 07 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-18501Steelwork Plan @+32.940m (L05) - Phase 18 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-20501Steelwork Plan @+32.940m (L05) - Phase 20 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-CA-S-28013CMP Level 6 (Zone B) Plan +39.440 SSL | CA - Calculations (CA) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C09 | For InformationNo approval required | 07 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-21101Steelwork Plan @+8.940m (L01) - Phase 21 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-17201Steelwork Plan @+13.440m (L02) - Phase 17 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-22201Steelwork Plan @+13.440m (L02) - Phase 22 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-17501Steelwork Plan @+32.940m (L05) - Phase 17 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-19501Steelwork Plan @+32.940m (L05) - Phase 19 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-20301Steelwork Plan @+19.940m (L03) - Phase 20 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-20401Steelwork Plan @+26.440m (L04) - Phase 20 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 05 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-18101Steelwork Plan @+8.940m (L01) - Phase 18 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-17401Steelwork Plan @+26.440m (L04) - Phase 17 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-17301Steelwork Plan @+19.940m (L03) - Phase 17 | DR - Drawing (DR) | STR | 07 Jul 2026 | 07 Jul 2026Asite issue | C03 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03004Guard House Details 5 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-01003SIP Panel GA Elevation 4 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-01041BrickClad GA Elevation 2 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03003Guard House Details 4 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03010Guard House Details 11 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03016Guard House Details 17 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03009Guard House Details 10 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03015Guard House Details 16 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-01000SIP Panel GA Elevation 1 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03018Guard House Details 19 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-01021Feature Panel GA Elevation 1 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-01043BrickClad GA Elevation 4 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03005Guard House Details 6 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03011Guard House Details 12 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03017Guard House Details 18 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-01040BrickClad GA Elevation 1 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03002Guard House Details 3 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03008Guard House Details 9 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03014Guard House Details 15 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-01020Feature Panel GA Elevation 1 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-01042BrickClad GA Elevation 3 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-01001SIP Panel GA Elevation 2 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-01023Feature Panel GA Elevation 1 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03001Guard House Details 2 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03007Guard House Details 8 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03013Guard House Details 14 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03019Guard House Details 20 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03013Cladding Details 14 | DR - Drawing (DR) | FAC | 08 Jul 2026 | 07 Sept 2026Asite issue | C02 | AAccepted | 07 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03011Cladding Details 12 | DR - Drawing (DR) | FAC | 08 Jul 2026 | 07 Sept 2026Asite issue | C02 | AAccepted | 07 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03012Cladding Details 13 | DR - Drawing (DR) | FAC | 08 Jul 2026 | 07 Sept 2026Asite issue | C02 | AAccepted | 07 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-01022Feature Panel GA Elevation 1 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03000Guard House Details 1 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-01002SIP Panel GA Elevation 3 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03006Guard House Details 7 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-03012Guard House Details 13 | DR - Drawing (DR) | FAC | 08 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28249Connection No.: 28249 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28264Connection No.: 28264 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29175Connection No.: 29175 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28311Connection No.: 28311 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C01 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28315Connection No.: 28315 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28313Connection No.: 28313 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29141Connection No.: 29141 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29141Connection No.: 29141 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28252Connection No.: 28252 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C01 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28320Connection No.: 28320 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28316Connection No.: 28316 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28312Connection No.: 28312 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29175Connection No.: 29175 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29268Connection No.: 29268 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28241Connection No.: 28241 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29267Connection No.: 29267 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C01 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28317Connection No.: 28317 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29272Connection No.: 29272 | CA - Calculations (CA) | STR | 09 Jul 2026 | 09 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-59701Olympus - LCY11 22031 - GL 18-22 - Phase 59 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-59601Olympus - LCY11 22031 - GL 18-22 - Phase 59 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-14809Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Plan @ 63.700m (R03-Parapet) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13056Olympus - LCY11 22033 - GL 14-16 - Phase 13 Steelwork Girt Elevation on GL B (GL 14 to 16) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | BAccepted with comments | 07 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-14055Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Elevation on GL K (GL 16 to 18) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 24 Jul 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-15802Olympus - LCY11 22033 - GL 16-18 - Phase 15 Steelwork Plan @ 48.300m (G01-Lower Gantry) Sheet 02 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01970External Flue - Built-Up GA Elevation 1 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01976External Flue - Built-Up GA Elevation 7 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03253External Flue Details 4 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-61601Olympus - LCY11 22031 - GL 18-22 - Phase 61 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-61611Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Steelwork Elevation on GL 22 (GL H to K) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03260External Flue Details 11 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03259External Flue Details 10 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-62611Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Steelwork Elevation on GL 22 (GL A to E) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03304Built-Up Details 5 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-62612Olympus - LCY11 22031 - GL 18-22 - Phase 62 Temporary Steelwork Elevation on GL 21&22 | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03310Built-Up Details 11 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03316Built-Up Details 17 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03322Built-Up Details 23 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-15055Olympus - LCY11 22033 - GL 16-18 - Phase 15 Steelwork Girt Elevation on GL B (GL 16 to 18) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | BAccepted with comments | 07 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-15901Olympus - LCY11 22033 - GL 16-18 - Phase 15 Temporary Steelwork Plan @ 48.300m (G01) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03312Built-Up Details 13 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03313Built-Up Details 14 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03318Built-Up Details 19 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-15053Olympus - LCY11 22033 - GL 16-18 - Phase 15 Steelwork Elevation on GL B (GL 16 to 18) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 24 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-12809Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Plan @ +63.700m (R03-Parapet) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03317Built-Up Details 18 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03319Built-Up Details 20 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03321Built-Up Details 22 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-15805Olympus - LCY11 22033 - GL 16-18 - Phase 15 Steelwork Plan @ 57.770m (G02-Intermediate) Sheet 01 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-57615Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Steelwork Elevation on GL 20 (GL E to H) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-B1-DR-S-57722Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Cell Shield Pot Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-61610Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Steelwork Elevation on GL 21 (GL H to K) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-58614Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Steelwork Elevation on GL 20 (GL H to K) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-B1-DR-S-57622Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Cell Shield Pot Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-13808Olympus - LCY11 22033 - GL 14-16 - Phase 13 Steelwork Plan @ 59.657m (R03) Sheet 02 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 23 Jul 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12901Olympus - LCY11 22033 - GL 14-16 - Phase 12 Temporary Steelwork Plan @ 48.300m (G01) & 54.380m (G02) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 24 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-14052Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Elevation on GL F (GL 16 to 18) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 28 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-57614Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Steelwork Elevation on GL 19 (GL E to H) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-14056Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Girt Elevation on GL J (GL 16 to 18) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 24 Jul 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-14901Olympus - LCY11 22033 - GL 16-18 - Phase 14 Temporary Steelwork Plan @ 48.300m (G01) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-12808Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Plan @ 59.657m (R03) Sheet 02 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 23 Jul 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-13807Olympus - LCY11 22033 - GL 14-16 - Phase 13 Steelwork Plan @ 59.657m (R03) Sheet 01 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 23 Jul 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12057Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Girt Elevation on GL J (GL 14 to 16) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 24 Jul 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-15050Olympus - LCY11 22033 - GL 16-18 - Phase 15 Steelwork Elevation on GL17 (GL A to F) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 28 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-58701Olympus - LCY11 22031 - GL 18-22 - Phase 58 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-14804Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Plan @ 54.380m (G02-Upper Gantry) Sheet 02 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-12803Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Plan @ 54.380m (G02-Upper Gantry) Sheet 01 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13052Olympus - LCY11 22033 - GL 14-16 - Phase 13 Steelwork Elevation on GL 16 (GL A to F) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 24 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-15807Olympus - LCY11 22033 - GL 16-18 - Phase 15 Steelwork Plan @ 59.657m (R03) Sheet 01 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 23 Jul 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-14805Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Plan @ 57.770m (G02-Intermediate) Sheet 01 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-12805Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Plan @ 57.770m (G02-Intermediate) Sheet 01 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13055Olympus - LCY11 22033 - GL 14-16 - Phase 13 Steelwork Elevation on GL A (GL 14 to 16) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 24 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-60611Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Steelwork Elevation on GL 22 (GL E to H) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-B1-DR-S-57721Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Cell Shield Panel Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-59616Olympus - LCY11 22031 - GL 18-22 - Phase 59 Temporary Steelwork Elevation on GL 19&20 | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-62701Olympus - LCY11 22031 - GL 18-22 - Phase 62 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-61701Olympus - LCY11 22031 - GL 18-22 - Phase 61 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-60701Olympus - LCY11 22031 - GL 18-22 - Phase 60 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-59614Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Steelwork Elevation on GL 19 (GL A to E) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-57611Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Steelwork Elevation on GL F | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-60610Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Steelwork Elevation on GL 21 (GL E to H) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-B1-DR-S-57621Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Cell Shield Panel Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-14808Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Plan @ 59.657m (R03) Sheet 02 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 23 Jul 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-58613Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Steelwork Elevation on GL 19 (GL H to K) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03254External Flue Details 5 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-15808Olympus - LCY11 22033 - GL 16-18 - Phase 15 Steelwork Plan @ 59.657m (R03) Sheet 02 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 23 Jul 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01977External Flue - Built-Up GA Elevation 8 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01971External Flue - Built-Up GA Elevation 2 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01954External Flue - Tolerance Channel GA Elevation 4 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-57612Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Steelwork Elevation on GL G | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-14801Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Plan @ 48.300m (G01-Lower Gantry) Sheet 01 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-14054Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Elevation on GL J (GL 16 to 18) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 27 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12053Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Elevation on GL F (GL 14 to 16) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 28 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-12807Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Plan @ 59.657m (R03) Sheet 01 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 28 Jul 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-14803Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Plan @ 54.380m (G02-Upper Gantry) Sheet 01 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-15803Olympus - LCY11 22033 - GL 16-18 - Phase 15 Steelwork Plan @ 54.380m (G02-Upper Gantry) Sheet 01 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01955External Flue - Tolerance Channel GA Elevation 5 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01972External Flue - Built-Up GA Elevation 3 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03255External Flue Details 6 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03300Built-Up Details 1 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-13805Olympus - LCY11 22033 - GL 14-16 - Phase 13 Steelwork Plan @ 57.770m (G02-Intermediate) Sheet 01 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-15806Olympus - LCY11 22033 - GL 16-18 - Phase 15 Steelwork Plan @ 57.770m (G02-Intermediate) Sheet 02 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-14053Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Elevation on GL G (GL 16 to 18) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 28 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-12802Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Plan @ 48.300m (G01-Lower Gantry) Sheet 02 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-14807Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Plan @ 59.657m (R03) Sheet 01 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-15804Olympus - LCY11 22033 - GL 16-18 - Phase 15 Steelwork Plan @ 54.380m (G02-Upper Gantry) Sheet 02 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13051Olympus - LCY11 22033 - GL 14-16 - Phase 13 Steelwork Elevation on GL 15 (GL A to F) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 28 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12054Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Elevation on GL G (GL 14 to 16) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-13802Olympus - LCY11 22033 - GL 14-16 - Phase 13 Steelwork Plan @ 48.300m (G01-Lower Gantry) Sheet 02 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-13801Olympus - LCY11 22033 - GL 14-16 - Phase 13 Steelwork Plan @ 48.300m (G01-Lower Gantry) Sheet 01 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-62601Olympus - LCY11 22031 - GL 18-22 - Phase 62 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-13806Olympus - LCY11 22033 - GL 14-16 - Phase 13 Steelwork Plan @ 57.770m (G02-Intermediate) Sheet 02 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01953External Flue - Tolerance Channel GA Elevation 3 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01973External Flue - Built-Up GA Elevation 4 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01956External Flue - Tolerance Channel GA Elevation 6 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03250External Flue Details 1 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03256External Flue Details 7 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12058Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Girt Elevation on GL K (GL 14 to 16) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | BAccepted with comments | 07 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-57701Olympus - LCY11 22031 - GL 18-22 - Phase 57 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13054Olympus - LCY11 22033 - GL 14-16 - Phase 13 Steelwork Elevation on GL B (GL 14 to 16) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 24 Jul 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03301Built-Up Details 2 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03307Built-Up Details 8 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-15054Olympus - LCY11 22033 - GL 16-18 - Phase 15 Steelwork Girt Elevation on GL A (GL 16 to 18) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | BAccepted with comments | 07 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-15801Olympus - LCY11 22033 - GL 16-18 - Phase 15 Steelwork Plan @ 48.300m (G01-Lower Gantry) Sheet 01 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-15052Olympus - LCY11 22033 - GL 16-18 - Phase 15 Steelwork Elevation on GL A (GL 16 to 18) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 28 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-12804Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Plan @ 54.380m (G02-Upper Gantry) Sheet 02 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-12806Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Plan @ 57.770m (G02-Intermediate) Sheet 02 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-13804Olympus - LCY11 22033 - GL 14-16 - Phase 13 Steelwork Plan @ 54.380m (G02-Upper Gantry) Sheet 02 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-13803Olympus - LCY11 22033 - GL 14-16 - Phase 13 Steelwork Plan @ 54.380m (G02-Upper Gantry) Sheet 01 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-14806Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Plan @ 57.770m (G02-Intermediate) Sheet 02 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03315Built-Up Details 16 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-14057Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Girt Elevation on GL K (GL 16 to 18) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | BAccepted with comments | 07 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12056Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Elevation on GL K (GL 14 to 16) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 24 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-12801Olympus - LCY11 22033 - GL 14-16 - Phase 15 Steelwork Plan @ 48.300m (G01-Lower Gantry) Sheet 01 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 28 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12051Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Elevation on GL 15 (GL F to K) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13050Olympus - LCY11 22033 - GL 14-16 - Phase 13 Steelwork Elevation on GL 14 (GL A to F) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 24 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-14050Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Elevation on GL 17 (GL F to K) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 28 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-15051Olympus - LCY11 22033 - GL 16-18 - Phase 15 Steelwork Elevation on GL18 (GL A to F) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 28 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01952External Flue - Tolerance Channel GA Elevation 2 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01958External Flue - Tolerance Channel GA Elevation 8 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01975External Flue - Built-Up GA Elevation 6 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03252External Flue Details 3 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03258External Flue Details 9 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03303Built-Up Details 4 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-58601Olympus - LCY11 22031 - GL 18-22 - Phase 58 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03305Built-Up Details 6 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03309Built-Up Details 10 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-14051Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Elevation on GL 18 (GL F to K) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 28 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03306Built-Up Details 7 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12052Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Elevation on GL 16 (GL F to K) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 31 Jul 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01951External Flue - Tolerance Channel GA Elevation 1 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01957External Flue - Tolerance Channel GA Elevation 7 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01974External Flue - Built-Up GA Elevation 5 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03251External Flue Details 2 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12050Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Elevation on GL 14 (GL F to K) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 28 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-59615Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Steelwork Elevation on GL 20 (GL A to E) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13901Olympus - LCY11 22033 - GL 14-16 - Phase 13 Temporary Steelwork Plan @ 48.300m (G01) & 54.380m (G02) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 27 Jul 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03257External Flue Details 8 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12055Olympus - LCY11 22033 - GL 14-16 - Phase 12 Steelwork Elevation on GL J (GL 14 to 16) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 24 Jul 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03302Built-Up Details 3 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-62610Olympus - LCY11 22031 - GL 18-22 - Phase 57 to 62 Steelwork Elevation on GL 21 (GL A to E) | DR - Drawing (DR) | STR | 10 Jul 2026 | 10 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03311Built-Up Details 12 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03308Built-Up Details 9 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-14802Olympus - LCY11 22033 - GL 16-18 - Phase 14 Steelwork Plan @ 48.300m (G01-Lower Gantry) Sheet 02 | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03314Built-Up Details 15 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03320Built-Up Details 21 | DR - Drawing (DR) | FAC | 10 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13053Olympus - LCY11 22033 - GL 14-16 - Phase 13 Steelwork Elevation on GL A (GL 14 to 16) | DR - Drawing (DR) | STR | 10 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 24 Jul 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-32055Olympus - LCY11 22034 - GL 12-14 - Phase 32 Steelwork Girt Elevation on GL B (GL 12 to 14) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01671Area 6 - Grids E-H Tolerance Channel Lower Building GA East Elevation | DR - Drawing (DR) | FAC | 13 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01672Area 6 - Grids H-J Tolerance Channel Lower Building GA East Elevation | DR - Drawing (DR) | FAC | 13 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01502Area 5 - Grids E-H Tolerance Channel GA West Elevation | DR - Drawing (DR) | FAC | 13 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01531Area 5 - Grids E-H Tolerance Channel Office Building GA East Elevation | DR - Drawing (DR) | FAC | 13 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01621Area 6 - Grids E-H Tolerance Channel GA East Elevation | DR - Drawing (DR) | FAC | 13 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01530Area 5 - Grids B-E Tolerance Channel Office Building GA East Elevation | DR - Drawing (DR) | FAC | 13 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01620Area 6 - Grids B-E Tolerance Channel GA East Elevation | DR - Drawing (DR) | FAC | 13 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01503Area 5 - Grids H-J Tolerance Channel GA West Elevation | DR - Drawing (DR) | FAC | 13 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01532Area 5 - Grids H-J Tolerance Channel Office Building GA East Elevation | DR - Drawing (DR) | FAC | 13 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01622Area 6 - Grids H-J Tolerance Channel GA East Elevation | DR - Drawing (DR) | FAC | 13 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01670Area 6 - Grids B-E Tolerance Channel Lower Building GA East Elevation | DR - Drawing (DR) | FAC | 13 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01501Area 5 - Grids B-E Tolerance Channel GA West Elevation | DR - Drawing (DR) | FAC | 13 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29003CMP ALIGN G & H (axes 1 to 26) | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C17 | PendingAwaiting Design Review | 13 Jul 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29003CMP ALIGN G & H (axes 1 to 26) | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C17 | PendingAwaiting Design Review | 13 Jul 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28717Connection No.: 28717 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28736Connection No.: 28736 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28701Connection No.: 28701 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28708Connection No.: 28708 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-34052Olympus - LCY11 22034 - GL 10-12 - Phase 34 Steelwork Elevation on GL A (GL 10 to 12) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-33802Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet 02 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-34804Olympus - LCY11 22034 - GL 10-12 - Phase 34 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet 02 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 05 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-33806Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Plan @+57.770m (G02-Intermediate) Sheet 02 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28719Connection No.: 28719 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28704Connection No.: 28704 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28734Connection No.: 28734 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-33054Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Elevation on GL J (GL 10 to 12) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-33053Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Elevation on GL G (GL 10 to 12) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-31807Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Plan @+59.657m (R03) Sheet 01 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-33050Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Elevation on GL 10 (GL F to K) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 05 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28727Connection No.: 28727 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28713Connection No.: 28713 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-32805Olympus - LCY11 22034 - GL 12-14 - Phase 32 Steelwork Plan @+57.770m (G02-Intermediate) Sheet 01 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-33805Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Plan @+57.770m (G02-Intermediate) Sheet 01 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-33051Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Elevation on GL 11 (GL F to K) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 05 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28718Connection No.: 28718 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28714Connection No.: 28714 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28715Connection No.: 28715 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28716Connection No.: 28716 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-34051Olympus - LCY11 22034 - GL 10-12 - Phase 34 Steelwork Elevation on GL 11 (GL A to F) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-34055Olympus - LCY11 22034 - GL 10-12 - Phase 34 Steelwork Girt Elevation on GL B (GL 10 to 12) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | BAccepted with comments | 20 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-33056Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Girt Elevation on GL J (GL 10 to 12) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-33803Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet 01 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-32054Olympus - LCY11 22034 - GL 12-14 - Phase 32 Steelwork Girt Elevation on GL A (GL 12 to 14) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-34808Olympus - LCY11 22034 - GL 10-12 - Phase 34 Steelwork Plan @+59.657m (R03) Sheet 02 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28705Connection No.: 28705 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28737Connection No.: 28737 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28732Connection No.: 28732 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-33055Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Elevation on GL K (GL 10 to 12) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28730Connection No.: 28730 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-34805Olympus - LCY11 22034 - GL 10-12 - Phase 34 Steelwork Plan @+57.770m (G02-Intermediate) Sheet 01 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 05 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28733Connection No.: 28733 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-34801Olympus - LCY11 22034 - GL 10-12 - Phase 34 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet 01 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-34054Olympus - LCY11 22034 - GL 10-12 - Phase 34 Steelwork Girt Elevation on GL A (GL 10 to 12) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-33807Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Plan @+59.657m (R03) Sheet 01 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-33809Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Plan @+63.700m (R03-Parapet) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 05 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-31805Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Plan @+57.770m (G02-Intermediate) Sheet 01 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28703Connection No.: 28703 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-34050Olympus - LCY11 22034 - GL 10-12 - Phase 34 Steelwork Elevation on GL 10 (GL A to F) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28724Connection No.: 28724 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-32807Olympus - LCY11 22034 - GL 12-14 - Phase 32 Steelwork Plan @+59.657m (R03) Sheet 01 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-33808Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Plan @+59.657m (R03) Sheet 02 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-33052Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Elevation on GL F (GL 10 to 12) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28702Connection No.: 28702 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-34053Olympus - LCY11 22034 - GL 10-12 - Phase 34 Steelwork Elevation on GL B (GL 10 to 12) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-33801Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet 01 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-32806Olympus - LCY11 22034 - GL 12-14 - Phase 32 Steelwork Plan @+57.770m (G02-Intermediate) Sheet 02 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status C - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31056Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Girt Elevation on GL J (GL 12 to 14) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28731Connection No.: 28731 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28711Connection No.: 28711 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29604Connection No.: 29604 | CA - Calculations (CA) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-34802Olympus - LCY11 22034 - GL 10-12 - Phase 34 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet 02 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-31806Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Plan @+57.770m (G02-Intermediate) Sheet 02 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-34803Olympus - LCY11 22034 - GL 10-12 - Phase 34 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet 01 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-32808Olympus - LCY11 22034 - GL 12-14 - Phase 32 Steelwork Plan @+59.657m (R03) Sheet 02 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31057Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Girt Elevation on GL K (GL 12 to 14) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-33057Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Girt Elevation on GL K (GL 10 to 12) | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | BAccepted with comments | 03 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-34806Olympus - LCY11 22034 - GL 10-12 - Phase 34 Steelwork Plan @+57.770m (G02-Intermediate) Sheet 02 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-31808Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Plan @+59.657m (R03) Sheet 02 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-33804Olympus - LCY11 22034 - GL 10-12 - Phase 33 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet 02 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-34807Olympus - LCY11 22034 - GL 10-12 - Phase 34 Steelwork Plan @+59.657m (R03) Sheet 01 | DR - Drawing (DR) | STR | 13 Jul 2026 | 13 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-CA-S-28021CMP Stairways 02 | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C02 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28318Connection No.: 28318 | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29273Connection No.: 29273 | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C01 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-CA-S-28008CMP Level 4 (Zone A) Plan +26.440 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C14 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-CA-S-28014CMP Level R01 (Zone A) Plan +45.940 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C10 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29269Connection No.: 29269 | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29271Connection No.: 29271 | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-CA-S-28009CMP Level 4 (Zone B) Plan +26.440 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C14 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28321Connection No.: 28321 | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29270Connection No.: 29270 | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-RF-TW-S-99205Temporary Works – TW06-00 – Edge Protection System | TW - Temporary Works (TW) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C01 | BAccepted with comments | 21 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28314Connection No.: 28314 | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-6374722031 - GL 22-26 - Phases 63 to 67 ComFlor 80 and Shear Stud Layout to R01 | DR - Drawing (DR) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05024Gantry Louvres North GA Elevation 5 | DR - Drawing (DR) | FAC | 14 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05320Gantry Louvres North Details 1 | DR - Drawing (DR) | FAC | 14 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-73616Olympus - LCY11 22032 - GL 10 -14 - Phases 71 to 76 Steelwork Elevation on GL 12 (GL A to E) | DR - Drawing (DR) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05121Gantry Louvres North GA Section 2 | DR - Drawing (DR) | FAC | 14 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-05-CA-S-28011CMP Level 5 (Zone B) Plan +32.940 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C14 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-CA-S-28008CMP Level 4 (Zone A) Plan +26.440 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C14 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05022Gantry Louvres North GA Elevation 3 | DR - Drawing (DR) | FAC | 14 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-CA-S-28014CMP Level R01 (Zone A) Plan +45.940 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C10 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-CA-S-28018CMP Level G1 (Zone A) (Gridlines A To F) Plan +48.360 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C05 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-CA-S-28601CMP Level G2 (Zone A) | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C07 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05321Gantry Louvres North Details 2 | DR - Drawing (DR) | FAC | 14 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-04-CA-S-28009CMP Level 4 (Zone B) Plan +26.440 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C14 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05122Gantry Louvres North GA Section 3 | DR - Drawing (DR) | FAC | 14 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05023Gantry Louvres North GA Elevation 4 | DR - Drawing (DR) | FAC | 14 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05120Gantry Louvres North GA Section 1 | DR - Drawing (DR) | FAC | 14 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05021Gantry Louvres North GA Elevation 2 | DR - Drawing (DR) | FAC | 14 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29006CMP AXES 4, 6, 23, 25 | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C17 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29004CMP Align I & J (axes 1 to 26) | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C14 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-CA-S-28017CMP Level G1 (Zone B) (Gridlines F to K) Plan +48.360 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C05 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-CA-S-28019CMP Level G1 (Zone B) (Gridlines A To F) Plan +48.360 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C05 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-CA-S-28005CMP LEVEL 2 (ZONE B) PLAN +13.440 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C17 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-CA-S-28016CMP Level G1 (Zone A) (Gridlines F to K) Plan +48.360 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C05 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-72615Olympus - LCY11 22032 - GL 10 -14 - Phases 71 to 76 Steelwork Elevation on GL 12 (GL H to K) | DR - Drawing (DR) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05124Gantry Louvres North GA Section 5 | DR - Drawing (DR) | FAC | 14 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05323Gantry Louvres North Details 4 | DR - Drawing (DR) | FAC | 14 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-72614Olympus - LCY11 22032 - GL 10 -14 - Phases 71 to 76 Steelwork Elevation on GL 13 (GL H to K) | DR - Drawing (DR) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29001CMP Align C & D (axes 1 to 26) | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C13 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-CA-S-28020CMP Stairways 01 | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C02 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-CA-S-28006CMP LEVEL 3 (ZONE A) PLAN +19.940 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C15 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29001CMP Align C & D (axes 1 to 26) | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C13 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29004CMP Align I & J (axes 1 to 26) | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C14 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05020Gantry Louvres North GA Elevation 1 | DR - Drawing (DR) | FAC | 14 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29006CMP AXES 4, 6, 23, 25 | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C17 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-CA-S-28006CMP LEVEL 3 (ZONE A) PLAN +19.940 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C15 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05322Gantry Louvres North Details 3 | DR - Drawing (DR) | FAC | 14 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-53615OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL 14 (GL A to E) | DR - Drawing (DR) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-52614OLYMPUS - LCY11 22031 - GL 14-18 - Phase 51 to 56 Steelwork Elevation on GL 14 (GL H to K) | DR - Drawing (DR) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-CA-S-28002CMP LEVEL 1 (ZONE A) PLAN +8.940 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C12 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-CA-S-28005CMP LEVEL 2 (ZONE B) PLAN +13.440 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C17 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-CA-S-28010CMP Level 5 (Zone A) Plan +32.940 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C14 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-CA-S-28602CMP Level G2 (Zone B) | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C07 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-CA-S-28011CMP Level 5 (Zone B) Plan +32.940 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C14 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-CA-S-28002CMP LEVEL 1 (ZONE A) PLAN +8.940 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C12 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29275Connection No.: 29275 | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-6364622031 - GL 22-26 - Phases 63 to 67 ComFlor 80 and Shear Stud Layout to L06 | DR - Drawing (DR) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28319Connection No.: 28319 | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-CA-S-28010CMP Level 5 (Zone A) Plan +32.940 SSL | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C14 | For InformationNo approval required | 14 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29274Connection No.: 29274 | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28322Connection No.: 28322 | CA - Calculations (CA) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C01 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05123Gantry Louvres North GA Section 4 | DR - Drawing (DR) | FAC | 14 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-73615Olympus - LCY11 22032 - GL 10 -14 - Phases 71 to 76 Steelwork Elevation on GL 13 (GL A to E) | DR - Drawing (DR) | STR | 14 Jul 2026 | 14 Jul 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05324Gantry Louvres North Details 5 | DR - Drawing (DR) | FAC | 14 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-73617Olympus -LCY11 22032 - GL 10-14 - Phase 73 Temporary Steelwork Elevation on GL 12 & 13 | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | AAccepted | 22 Jul 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-74612Olympus -LCY11 22032 - GL 10-14 - Phase 76 Temporary Steelwork Elevation on GL 10 & 11 | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | AAccepted | 22 Jul 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-71610Olympus -LCY11 22032 - GL 10-14 - Phase 71 to 76 Steelwork Elevation on GL 12 (GL E to H) | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01534Area 5 - Grids E-H K-ROC Office Building GA East Elevation | DR - Drawing (DR) | FAC | 15 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01533Area 5 - Grids B-E K-ROC Officer Building GA East Elevation | DR - Drawing (DR) | FAC | 15 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-03-CA-S-28007CMP LEVEL 3 (ZONE B) PLAN +19.940 SSL | CA - Calculations (CA) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C15 | For InformationNo approval required | 15 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-CA-S-28004CMP LEVEL 2 (ZONE A) PLAN +13.440 SSL | CA - Calculations (CA) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C18 | For InformationNo approval required | 15 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-75611Olympus -LCY11 22032 - GL 10-14 - Phase 71 to 76 Steelwork Elevation on GL 10 (GL H to K) | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-74701Olympus -LCY11 22032 - GL 10-14 - Phase 74 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-CA-S-28004CMP LEVEL 2 (ZONE A) PLAN +13.440 SSL | CA - Calculations (CA) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C18 | For InformationNo approval required | 15 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-76610Olympus -LCY11 22032 - GL 10-14 - Phase 71 to 76 Steelwork Elevation on GL 11 (GL A to E) | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-71721Olympus -LCY11 22032 - GL 10-14 - Phase 71 to 76 Cell Shield Plan @+45.780m (R01) | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | For InformationNo approval required | 15 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-CA-S-28007CMP LEVEL 3 (ZONE B) PLAN +19.940 SSL | CA - Calculations (CA) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C15 | For InformationNo approval required | 15 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-71616Olympus -LCY11 22032 - GL 10-14 - Phase 71 to 76 Steelwork Elevation on GL F (GL 10 to 14) | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-71621Olympus - LCY11 22032 - GL 10-14 - Phase 71 to 76 Cell Shield Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | For InformationNo approval required | 15 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-71722Olympus -LCY11 22032 - GL 10-14 - Phases 71 to 76 Cell Shield Pots @+45.780m (R01) | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | For InformationNo approval required | 15 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29000CMP ALIGN A & B (axes 1 to 26) | CA - Calculations (CA) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C21 | For InformationNo approval required | 16 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29000CMP ALIGN A & B (axes 1 to 26) | CA - Calculations (CA) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C21 | For InformationNo approval required | 16 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-71617Olympus -LCY11 22032 - GL 10-14 - Phase 71 to 76 Steelwork Elevation on GL G (GL 10 to 14) | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-74611Olympus -LCY11 22032 - GL 10-14 - Phase 71 to 76 Steelwork Elevation on GL 10 (GL E to H) | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-74601Olympus -LCY11 22032 - GL 10-14 - Phase 74 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01535Area 5 - Grids H-J K-ROC Office Building GA East Elevation | DR - Drawing (DR) | FAC | 15 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-71622Olympus -LCY11 22032 - GL 10-14 - Phase 71 to 76 Cell Shield Pots @+39.280m (L06) | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | For InformationNo approval required | 15 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-75610Olympus -LCY11 22032 - GL 10-14 - Phase 71 to 76 Steelwork Elevation on GL 11 (GL H to K) | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-71611Olympus -LCY11 22032 - GL 10-14 - Phase 71 to 76 Steelwork Elevation on GL 13 (GL E to H) | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-71601Olympus -LCY11 22032 - GL 10-14 - Phase 71 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-74610Olympus -LCY11 22032 - GL 10-14 - Phase 71 to 76 Steelwork Elevation on GL 11 (GL E to H) | DR - Drawing (DR) | STR | 15 Jul 2026 | 15 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-40001Olympus - LCY11 22032 - GL 01-08 - Phases 40 to 47 Steelwork Foundation Plan on GL H to K | DR - Drawing (DR) | STR | 16 Jul 2026 | 16 Jul 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93003Stair 4 3d Views | DR - Drawing (DR) | STR | 16 Jul 2026 | 16 Jul 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93006Stair 4 Section Views Sheet 1 | DR - Drawing (DR) | STR | 16 Jul 2026 | 16 Jul 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93007Stair 4 Section Views Sheet 2 | DR - Drawing (DR) | STR | 16 Jul 2026 | 16 Jul 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-40003Olympus - LCY11 22032 - GL 01-08 - Phases 40 to 47 Steelwork Foundation Plan on GL E to H | DR - Drawing (DR) | STR | 16 Jul 2026 | 16 Jul 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01351Area 3 - Grids 06-10 Tolerance Channel GA South Elevation | DR - Drawing (DR) | FAC | 16 Jul 2026 | 16 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-40003Olympus - LCY11 22032 - GL 01-08 - Phases 40 to 47 Steelwork Foundation Plan on GL E to H | DR - Drawing (DR) | STR | 16 Jul 2026 | 16 Jul 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01451Area 4 - Grids 18-22 Tolerance Channel GA South Elevation | DR - Drawing (DR) | FAC | 16 Jul 2026 | 16 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01251Area 2 - Grids 14-18 Tolerance Channel GA South Elevation | DR - Drawing (DR) | FAC | 16 Jul 2026 | 16 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-40002Olympus - LCY11 22032 - GL 01-08 - Phases 40 to 47 Steelwork Foundation Plan on GL A to E | DR - Drawing (DR) | STR | 16 Jul 2026 | 16 Jul 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01151Area 1 - Grids 10-14 Tolerance Channel GA South Elevation | DR - Drawing (DR) | FAC | 16 Jul 2026 | 16 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-40002Olympus - LCY11 22032 - GL 01-08 - Phases 40 to 47 Steelwork Foundation Plan on GL A to E | DR - Drawing (DR) | STR | 16 Jul 2026 | 16 Jul 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00026ROCKWOOL FIRE & CAVITY BARRIERS | TS - Technical Submittals (TS) | FAC | 16 Jul 2026 | 16 Jul 2026Asite issue | P01 | CRejected | 06 Aug 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93004Stair 4 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 16 Jul 2026 | 16 Jul 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-40001Olympus - LCY11 22032 - GL 01-08 - Phases 40 to 47 Steelwork Foundation Plan on GL H to K | DR - Drawing (DR) | STR | 16 Jul 2026 | 16 Jul 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01651Area 6 - Grids 22-24 Tolerance Channel GA South Elevation | DR - Drawing (DR) | FAC | 16 Jul 2026 | 16 Jul 2026Asite issue | P01 | BAccepted with comments | 30 Jul 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93005Stair 4 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 16 Jul 2026 | 16 Jul 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-77622Olympus - LCY11 22032 - GL 06-10 - Phase 77 to 82 CellSheild Pot @+39.440m (L06) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28155Connection No.: 28155 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-11201Olympus-LCY11 22031 - GL 14-18 - Phase 11 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C04 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-14301Olympus-LCY11 22031 - GL 14-18 - Phase 14 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C04 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-11401Olympus-LCY11 22031 - GL 14-18 - Phase 11 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C04 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28156Connection No.: 28156 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-11101Olympus-LCY11 22031 - GL 14-18 - Phase 11 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C04 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28185Connection No.: 28185 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-11301Olympus-LCY11 22031 - GL 14-18 - Phase 11 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C04 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29125Connection No.: 29125 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C03 | BAccepted with comments | 20 Jul 2026 | Awaiting Design ReviewCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-16101Olympus-LCY11 22031 - GL 14-18 - Phase 16 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C04 | BAccepted with comments | 07 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-11501Olympus-LCY11 22031 - GL 14-18 - Phase 11 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C04 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29005CMP ALIGN K; Align Between E-F & G-H (axes 1 to 26) | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C23 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-36022Olympus - LCY11 22032 - GL 10-14 - Phases 31 to 36 Temporary Steelwork Elevation on GL 10 & 11 | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 22 Jul 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-53623Olympus - LCY11 22031 - GL 14-18 - Phases 51 to 56 Temporary Steelwork Elevation on GL 14 & 15 | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 22 Jul 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-56622Olympus - LCY11 22031 - GL 14-18 - Phases 51 to 56 Temporary Steelwork Elevation on GL 18 | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 22 Jul 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-53624Olympus - LCY11 22031 - GL 14-18 - Phases 51 to 56 Temporary Steelwork Elevation on GL 16 & 17 | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 22 Jul 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-53622Olympus - LCY11 22031 - GL 14-18 - Phases 51 to 56 Temporary Steelwork Elevation on GL B & C | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 22 Jul 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-52622Olympus - LCY11 22031 - GL 14-18 - Phases 51 to 56 Temporary Steelwork Elevation on GL I & J | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 22 Jul 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-51622Olympus - LCY11 22031 - GL 14-18 - Phases 51 to 56 Temporary Steelwork Elevation on GL E & H | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 22 Jul 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-36023Olympus - LCY11 22032 - GL 10-14 - Phases 31 to 36 Temporary Steelwork Elevation on GL 12 & 13 | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 22 Jul 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28185Connection No.: 28185 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-11501Olympus-LCY11 22031 - GL 14-18 - Phase 11 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C04 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-11401Olympus-LCY11 22031 - GL 14-18 - Phase 11 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C04 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-11201Olympus-LCY11 22031 - GL 14-18 - Phase 11 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C04 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-16101Olympus-LCY11 22031 - GL 14-18 - Phase 16 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C04 | BAccepted with comments | 07 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29125Connection No.: 29125 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C03 | BAccepted with comments | 20 Jul 2026 | Awaiting Design ReviewCANCELLED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-14301Olympus-LCY11 22031 - GL 14-18 - Phase 14 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C04 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-11301Olympus-LCY11 22031 - GL 14-18 - Phase 11 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C04 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-11101Olympus-LCY11 22031 - GL 14-18 - Phase 11 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C04 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29252Connection No.: 29252 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29238Connection No.: 29238 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29242Connection No.: 29242 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28156Connection No.: 28156 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C03 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28155Connection No.: 28155 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-77612Olympus -LCY11 22032 -GL 06-10 - Phase 77 to 82 Steelwork Elevation on GL G | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29220Connection No.: 29220 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29005CMP ALIGN K; Align Between E-F & G-H (axes 1 to 26) | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C23 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28307Connection No.: 28307 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29221Connection No.: 29221 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29222Connection No.: 29222 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28263Connection No.: 28263 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29247Connection No.: 29247 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29249Connection No.: 29249 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-77615Olympus -LCY11 22032 -GL 06-10 - Phase 77 to 82 Steelwork Elevation on GL 08 (GL E to H) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29262Connection No.: 29262 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29243Connection No.: 29243 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29261Connection No.: 29261 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-80701Olympus -LCY11 22032 -GL 06-10 - Phase 80 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-77614Olympus -LCY11 22032 -GL 06-10 - Phase 77 to 82 Steelwork Elevation on GL 09 (GL E to H) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29259Connection No.: 29259 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29241Connection No.: 29241 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29223Connection No.: 29223 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29236Connection No.: 29236 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-04007BUILT-UP SPECIFICATION | DR - Drawing (DR) | FAC | 17 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29232Connection No.: 29232 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-7174722032 - GL 10-14 - Phases 71 to 76 ComFlor 80 and Shear Stud Layout to R01 | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-04009CURTAIN WALL SPECIFICATION | DR - Drawing (DR) | FAC | 17 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-82701Olympus -LCY11 22032 -GL 06-10 - Phase 82 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-79701Olympus -LCY11 22032 -GL 06-10 - Phase 79 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29244Connection No.: 29244 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 17 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-04008STEEL-LOOK PANEL SPECIFICATION | DR - Drawing (DR) | FAC | 17 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28277Connection No.: 28277 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-80610Olympus -LCY11 22032 -GL 06-10 - Phase 77 to 82 Steelwork Elevation on GL 07 (GL E to H) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-81701Olympus -LCY11 22032 -GL 06-10 - Phase 81 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | BAccepted with comments | 07 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-79615Olympus -LCY11 22032 -GL 06-10 - Phase 77 to 82 Steelwork Elevation on GL 08 (GL A to E) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-81601Olympus -LCY11 22032 -GL 06-10 - Phase 81 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-78701Olympus -LCY11 22032 -GL 06-10 - Phase 78 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28278Connection No.: 28278 | CA - Calculations (CA) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-77601Olympus -LCY11 22032 -GL 06-10 - Phase 77 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-80601Olympus -LCY11 22032 -GL 06-10 - Phase 80 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-82610Olympus -LCY11 22032 -GL 06-10 - Phase 77 to 82 Steelwork Elevation on GL 07 (GL A to E) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-77722Olympus - LCY11 22032 - GL 06-10 - Phase 77 to 82 CellSheild Pot @+45.940m (R01) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-79601Olympus -LCY11 22032 -GL 06-10 - Phase 79 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-77611Olympus -LCY11 22032 -GL 06-10 - Phase 77 to 82 Steelwork Elevation on GL F | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-77621Olympus - LCY11 22032 - GL 06-10 - Phase 77 to 82 CellSheild Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-81610Olympus -LCY11 22032 -GL 06-10 - Phase 77 to 82 Steelwork Elevation on GL 07 (GL H to K) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-79614Olympus -LCY11 22032 -GL 06-10 - Phase 77 to 82 Steelwork Elevation on GL 09 (GL A to E) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-79617Olympus - LCY11 22032 - GL 06-10 - Phase 77 to 82 Temporary Steelwork Elevation on GL 09 | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-82601Olympus -LCY11 22032 -GL 06-10 - Phase 82 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-79616Olympus - LCY11 22032 - GL 06-10 - Phase 77 to 82 Temporary Steelwork Elevation on GL 07 & 08 | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-78613Olympus -LCY11 22032 -GL 06-10 - Phase 77 to 82 Steelwork Elevation on GL 09 (GL H to K) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-77701Olympus -LCY11 22032 -GL 06-10 - Phase 77 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-78614Olympus -LCY11 22032 -GL 06-10 - Phase 77 to 82 Steelwork Elevation on GL 08 (GL H to K) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-77721Olympus - LCY11 22032 - GL 06-10 - Phase 77 to 82 CellSheild Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | For InformationNo approval required | 20 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-78601Olympus -LCY11 22032 -GL 06-10 - Phase 78 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 17 Jul 2026 | 17 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-RF-DR-S-1040222035 - GL 13-28 - Phases 11 and 13 ComFlor 60 Layout to Roof Level | DR - Drawing (DR) | STR | 20 Jul 2026 | 20 Jul 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28276Connection No.: 28276 | CA - Calculations (CA) | STR | 20 Jul 2026 | 20 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01901Internal Flue - Tolerance Channel GA Elevation 1 | DR - Drawing (DR) | FAC | 20 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01906Internal Flue - Tolerance Channel GA Elevation 6 | DR - Drawing (DR) | FAC | 20 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY18-WHL-DC-RF-DR-S-1040122035 - GL 01-13 - Phases 12 and 14 ComFlor 60 Layout to Roof Level | DR - Drawing (DR) | STR | 20 Jul 2026 | 20 Jul 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93011Stair 2 Section Views Sheet 1 | DR - Drawing (DR) | STR | 20 Jul 2026 | 20 Jul 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93012Stair 2 Section Views Sheet 2 | DR - Drawing (DR) | STR | 20 Jul 2026 | 20 Jul 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01903Internal Flue - Tolerance Channel GA Elevation 3 | DR - Drawing (DR) | FAC | 20 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01908Internal Flue - Tolerance Channel GA Elevation 8 | DR - Drawing (DR) | FAC | 20 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-4354522032 - GL 03-06 - Phases 43 to 47 ComFlor 80 and Shear Stud Layout to L05 | DR - Drawing (DR) | STR | 20 Jul 2026 | 20 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-4324222032 - GL 02-06 - Phases 43 to 47 ComFlor 80 and Shear Stud Layout to L02 | DR - Drawing (DR) | STR | 20 Jul 2026 | 20 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-4314122032 - GL 01-06 - Phases 43 to 47 ComFlor 80 and Shear Stud Layout to L01 | DR - Drawing (DR) | STR | 20 Jul 2026 | 20 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01905Internal Flue - Tolerance Channel GA Elevation 5 | DR - Drawing (DR) | FAC | 20 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-4334322032 - GL 03-06 - Phases 43 to 47 ComFlor 80 and Shear Stud Layout to L03 | DR - Drawing (DR) | STR | 20 Jul 2026 | 20 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93010Stair 2 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 20 Jul 2026 | 20 Jul 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-4344422032 - GL 03-06 - Phases 43 to 47 ComFlor 80 and Shear Stud Layout to L04 | DR - Drawing (DR) | STR | 20 Jul 2026 | 20 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01904Internal Flue - Tolerance Channel GA Elevation 4 | DR - Drawing (DR) | FAC | 20 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01907Internal Flue - Tolerance Channel GA Elevation 7 | DR - Drawing (DR) | FAC | 20 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28275Connection No.: 28275 | CA - Calculations (CA) | STR | 20 Jul 2026 | 20 Jul 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-5764622031 - GL 18-22 - Phases 57 to 62 ComFlor 80 and Shear Stud Layout to L06 | DR - Drawing (DR) | STR | 20 Jul 2026 | 20 Jul 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01902Internal Flue - Tolerance Channel GA Elevation 2 | DR - Drawing (DR) | FAC | 20 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93009Stair 2 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 20 Jul 2026 | 20 Jul 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93008Stair 2 3d Views | DR - Drawing (DR) | STR | 20 Jul 2026 | 20 Jul 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00050Trade Contractors Weekly Report | RP - Report (RP) | STR | 21 Jul 2026 | 21 Jul 2026Asite issue | C01 | For InformationNo approval required | 21 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00050Trade Contractors Weekly Report | RP - Report (RP) | STR | 21 Jul 2026 | 21 Jul 2026Asite issue | C01 | For InformationNo approval required | 21 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03012North & South Rainscreen Details 12 | DR - Drawing (DR) | FAC | 22 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03013North & South Rainscreen Details 13 | DR - Drawing (DR) | FAC | 22 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03008North & South Rainscreen Details 8 | DR - Drawing (DR) | FAC | 22 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-CA-S-28003CMP LEVEL 1 (ZONE B) PLAN +8.940 SSL | CA - Calculations (CA) | STR | 22 Jul 2026 | 22 Jul 2026Asite issue | C12 | For InformationNo approval required | 22 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03004North & South Rainscreen Details 4 | DR - Drawing (DR) | FAC | 22 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03011North & South Rainscreen Details 11 | DR - Drawing (DR) | FAC | 22 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03003North & South Rainscreen Details 3 | DR - Drawing (DR) | FAC | 22 Jul 2026 | 28 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-CA-S-28015CMP Level R01 (Zone B) Plan +45.940 SSL | CA - Calculations (CA) | STR | 22 Jul 2026 | 22 Jul 2026Asite issue | C10 | For InformationNo approval required | 22 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03005North & South Rainscreen Details 5 | DR - Drawing (DR) | FAC | 22 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03009North & South Rainscreen Details 9 | DR - Drawing (DR) | FAC | 22 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03002North & South Rainscreen Details 2 | DR - Drawing (DR) | FAC | 22 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-CA-S-28015CMP Level R01 (Zone B) Plan +45.940 SSL | CA - Calculations (CA) | STR | 22 Jul 2026 | 22 Jul 2026Asite issue | C10 | For InformationNo approval required | 22 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03007North & South Rainscreen Details 7 | DR - Drawing (DR) | FAC | 22 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-CA-S-28003CMP LEVEL 1 (ZONE B) PLAN +8.940 SSL | CA - Calculations (CA) | STR | 22 Jul 2026 | 22 Jul 2026Asite issue | C12 | For InformationNo approval required | 22 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03001North & South Rainscreen Details 1 | DR - Drawing (DR) | FAC | 22 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03010North & South Rainscreen Details 10 | DR - Drawing (DR) | FAC | 22 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03014North & South Rainscreen Details 14 | DR - Drawing (DR) | FAC | 22 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03006North & South Rainscreen Details 6 | DR - Drawing (DR) | FAC | 22 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-7364622032 - GL 03-06 - Phases 43 to 47 ComFlor 80 and Shear Stud Layout to L06 | DR - Drawing (DR) | STR | 23 Jul 2026 | 23 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-7374722032 - GL 03-06 - Phases 43 to 47 ComFlor 80 and Shear Stud Layout to R01 | DR - Drawing (DR) | STR | 23 Jul 2026 | 23 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-00-TW-S-99203Temporary Works – TW03-00 – Trailer Offloading Edge Protection | TW - Temporary Works (TW) | STR | 26 Jul 2026 | 27 Jul 2026Asite issue | C01 | AAccepted | 04 Aug 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05140Gantry Louvres West GA Section 1 | DR - Drawing (DR) | FAC | 27 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-19802Olympus - LCY11 22033 - GL 20-22 - Phase 19 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet-02 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-18802Olympus - LCY11 22033 - GL 20-22 - Phase 18 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet-02 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-16802Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet-02 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05040Gantry Louvres West GA Elevation 1 | DR - Drawing (DR) | FAC | 27 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05340Gantry Louvres West Details 1 | DR - Drawing (DR) | FAC | 27 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05042Gantry Louvres West GA Elevation 3 | DR - Drawing (DR) | FAC | 27 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05141Gantry Louvres West GA Section 2 | DR - Drawing (DR) | FAC | 27 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05344Gantry Louvres West Details 5 | DR - Drawing (DR) | FAC | 27 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-94002Gratings Phase 31/33 - G1 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | P02 | CRejected | 27 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05044Gantry Louvres West GA Elevation 5 | DR - Drawing (DR) | FAC | 27 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05143Gantry Louvres West GA Section 4 | DR - Drawing (DR) | FAC | 27 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05342Gantry Louvres West Details 3 | DR - Drawing (DR) | FAC | 27 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-18801Olympus - LCY11 22033 - GL 20-22 - Phase 18 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet-01 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-16805Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Plan @+57.770m (G02-Intermediate) Sheet-01 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05043Gantry Louvres West GA Elevation 4 | DR - Drawing (DR) | FAC | 27 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05041Gantry Louvres West GA Elevation 2 | DR - Drawing (DR) | FAC | 27 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05343Gantry Louvres West Details 4 | DR - Drawing (DR) | FAC | 27 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05142Gantry Louvres West GA Section 3 | DR - Drawing (DR) | FAC | 27 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05144Gantry Louvres West GA Section 5 | DR - Drawing (DR) | FAC | 27 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05341Gantry Louvres West Details 2 | DR - Drawing (DR) | FAC | 27 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-16804Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet-02 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-16803Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet-01 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | C01 | AAccepted | 11 Sept 2026 | Notify S5RUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-16806Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Plan @+57.770m (G02-Intermediate) Sheet-02 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-16801Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet-01 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-94004Gratings Phase 32/34 - G1 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | P02 | CRejected | 27 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-17802Olympus - LCY11 22033 - GL 18-20 - Phase 17 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet-02 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-17803Olympus - LCY11 22033 - GL 18-20 - Phase 17 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet-01 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | C01 | AAccepted | 11 Sept 2026 | Notify S5RUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-19801Olympus - LCY11 22033 - GL 20-22 - Phase 19 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet-01 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-17801Olympus - LCY11 22033 - GL 18-20 - Phase 17 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet-01 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-94001Gratings Phase 12/14 - G1 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | P02 | CRejected | 27 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-16901Olympus - LCY11 22033 - GL 18-20 - Phase 16 Temporary Steelwork Plan @+54.380m (G02) | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-94003Gratings Phase 13/15 - G1 | DR - Drawing (DR) | STR | 27 Jul 2026 | 27 Jul 2026Asite issue | P02 | CRejected | 27 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29131Connection No.: 29131 | CA - Calculations (CA) | STR | 28 Jul 2026 | 28 Jul 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00051Trade Contractor Weekly Report | RP - Report (RP) | STR | 28 Jul 2026 | 28 Jul 2026Asite issue | C01 | PendingAwaiting Design Review | 29 Jul 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29126Connection No.: 29126 | CA - Calculations (CA) | STR | 28 Jul 2026 | 28 Jul 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29131Connection No.: 29131 | CA - Calculations (CA) | STR | 28 Jul 2026 | 28 Jul 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00051Trade Contractor Weekly Report | RP - Report (RP) | STR | 28 Jul 2026 | 28 Jul 2026Asite issue | C01 | PendingAwaiting Design Review | 29 Jul 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29126Connection No.: 29126 | CA - Calculations (CA) | STR | 28 Jul 2026 | 28 Jul 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-94005Gratings Axis 18-22 North | DR - Drawing (DR) | STR | 29 Jul 2026 | 29 Jul 2026Asite issue | P01 | CRejected | 27 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-94006Gratings Axis 18-22 South | DR - Drawing (DR) | STR | 29 Jul 2026 | 29 Jul 2026Asite issue | P01 | CRejected | 27 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-19050Olympus - LCY11 22033 - GL 20-22 - Phase 19 Steelwork Elevation on GL 21 (GL A to F) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-17051Olympus - LCY11 22033 - GL 18-20 - Phase 17 Steelwork Elevation on GL 20 (GL A to F) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-19806Olympus - LCY11 22033 - GL 20-22 - Phase 19 Steelwork Plan @+57.770m (G02-Intermediate) Sheet-02 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-17808Olympus - LCY11 22033 - GL 18-20 - Phase 17 Steelwork Plan @+59.657m (R03) Sheet-02 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-16050Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Elevation on GL19 (GL F to K) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-18806Olympus - LCY11 22033 - GL 20-22 - Phase 18 Steelwork Plan @+57.770m (G02-Intermediate) Sheet-02 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-16809Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Plan @+63.700m (R03-Parapet) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-16052Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Elevation on GL F (GL 18 to 20) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-17807Olympus - LCY11 22033 - GL 18-20 - Phase 17 Steelwork Plan @+59.657m (R03) Sheet-01 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-18054Olympus - LCY11 22033 - GL 20-22 - Phase 18 Steelwork Elevation on GL J (GL 20 to 22) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-18805Olympus - LCY11 22033 - GL 20-22 - Phase 18 Steelwork Plan @+57.770m (G02-Intermediate) Sheet-01 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-16054Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Elevation on GL J (GL 18 to 20) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-19803Olympus - LCY11 22033 - GL 20-22 - Phase 19 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet-01 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | AAccepted | 11 Sept 2026 | Back to Workflow Originator For Action,Notify S5RUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-16055Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Elevation on GL K (GL 18 to 20) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-19055Olympus - LCY11 22033 - GL 20-22 - Phase 19 Steelwork Girt Elevation on GL B (GL 20 to 22) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-17055Olympus - LCY11 22033 - GL 18-20 - Phase 17 Steelwork Girt Elevation on GL B (GL 18 to 20) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-16057Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Girt Elevation on GL K (GL 18 to 20) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-17050Olympus - LCY11 22033 - GL 18-20 - Phase 17 Steelwork Girt Elevation on GL 19 (GL A to F) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-18808Olympus - LCY11 22033 - GL 20-22 - Phase 18 Steelwork Plan @+59.657m (R03) Sheet-02 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-19051Olympus - LCY11 22033 - GL 20-22 - Phase 19 Steelwork Elevation on GL 22 (GL A to F) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-18050Olympus - LCY11 22033 - GL 20-22 - Phase 18 Steelwork Elevation on GL 21 (GL F to K) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-18056Olympus - LCY11 22033 - GL 20-22 - Phase 18 Steelwork Girt Elevation on GL J (GL 20 to 22) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-18051Olympus - LCY11 22033 - GL 20-22 - Phase 18 Steelwork Elevation on GL 22 (GL F to K) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-19053Olympus - LCY11 22033 - GL 20-22 - Phase 19 Steelwork Elevation on GL B (GL 20 to 22) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-17053Olympus - LCY11 22033 - GL 18-20 - Phase 17 Steelwork Elevation on GL B (GL 18 to 20) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-19054Olympus - LCY11 22033 - GL 20-22 - Phase 19 Steelwork Girt Elevation on GL A (GL 20 to 22) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-18052Olympus - LCY11 22033 - GL 20-22 - Phase 18 Steelwork Elevation on GL F (GL 20 to 22) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-16807Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Plan @+59.657m (R03) Sheet-01 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-19807Olympus - LCY11 22033 - GL 20-22 - Phase 19 Steelwork Plan @+59.657m (R03) Sheet-01 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-19805Olympus - LCY11 22033 - GL 20-22 - Phase 19 Steelwork Plan @+57.770m (G02-Intermediate) Sheet-01 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-17901Olympus - LCY11 22033 - GL 18-20 - Phase 17 Temporary Steelwork Plan @+54.380m (G02) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-17804Olympus - LCY11 22033 - GL 18-20 - Phase 17 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet-02 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-19804Olympus - LCY11 22033 - GL 20-22 - Phase 19 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet-02 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-18057Olympus - LCY11 22033 - GL 20-22 - Phase 18 Steelwork Girt Elevation on GL K (GL 20 to 22) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-16051Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Elevation on GL20 (GL F to K) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-18053Olympus - LCY11 22033 - GL 20-22 - Phase 18 Steelwork Elevation on GL G (GL 20 to 22) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-19052Olympus - LCY11 22033 - GL 20-22 - Phase 19 Steelwork Elevation on GL A (GL 20 to 22) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-16808Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Plan @+59.657m (R03) Sheet-02 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-16053Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Elevation on GL G (GL 18 to 20) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-18809Olympus - LCY11 22033 - GL 20-22 - Phase 18 Steelwork Plan @+63.700m (R03-Parapet) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-16056Olympus - LCY11 22033 - GL 18-20 - Phase 16 Steelwork Girt Elevation on GL J (GL 18 to 20) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-17805Olympus - LCY11 22033 - GL 18-20 - Phase 17 Steelwork Plan @+57.770m (G02-Intermediate) Sheet-01 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-17054Olympus - LCY11 22033 - GL 18-20 - Phase 17 Steelwork Girt Elevation on GL A (GL 18 to 20) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-19808Olympus - LCY11 22033 - GL 20-22 - Phase 19 Steelwork Plan @+59.657m (R03) Sheet-02 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-18804Olympus - LCY11 22033 - GL 20-22 - Phase 18 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet-02 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | AAccepted | 11 Sept 2026 | Back to Workflow Originator For Action,Notify S5RUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-18055Olympus - LCY11 22033 - GL 20-22 - Phase 18 Steelwork Elevation on GL K (GL 20 to 22) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-17052Olympus - LCY11 22033 - GL 18-20 - Phase 17 Steelwork Elevation on GL A (GL 18 to 20) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-18803Olympus - LCY11 22033 - GL 20-23 - Phase 18 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet-01 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-18807Olympus - LCY11 22033 - GL 20-22 - Phase 18 Steelwork Plan @+59.657m (R03) Sheet-01 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-34521Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Cell Shield Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C03 | For InformationNo approval required | 30 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-17806Olympus - LCY11 22033 - GL 18-20 - Phase 17 Steelwork Plan @+57.770m (G02-Intermediate) Sheet-02 | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-34522Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Cell Shield Pots @+32.940m (L05) | DR - Drawing (DR) | STR | 30 Jul 2026 | 30 Jul 2026Asite issue | C03 | For InformationNo approval required | 30 Jul 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-39030Olympus - LCY11 22032 - GL 06-10 - Phase 39 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28158Connection No.: 28158 | CA - Calculations (CA) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01537Area 5 - Grids E-H Feature Panel Backing Grid Office Building GA East Elev. | DR - Drawing (DR) | FAC | 31 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03015Cladding Details 16 | DR - Drawing (DR) | FAC | 31 Jul 2026 | 07 Sept 2026Asite issue | C01 | AAccepted | 07 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01536Area 5 - Grids B-E Feature Panel Backing Grid Office Building GA East Elev. | DR - Drawing (DR) | FAC | 31 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01538Area 5 - Grids H-J Feature Panel Backing Grid Office Building GA East Elev. | DR - Drawing (DR) | FAC | 31 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03014Cladding Details 15 | DR - Drawing (DR) | FAC | 31 Jul 2026 | 07 Sept 2026Asite issue | C01 | AAccepted | 07 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03005Cladding Details 6 | DR - Drawing (DR) | FAC | 31 Jul 2026 | 07 Sept 2026Asite issue | C01 | AAccepted | 07 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29250Connection No.: 29250 | CA - Calculations (CA) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-60601Olympus - LCY11 22031 - GL 18-22 - Phase 60 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03017Cladding Details 18 | DR - Drawing (DR) | FAC | 31 Jul 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-40501Olympus - LCY11 22032 - GL 06-10 - Phase 40 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C04 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01539Area 5 - Grids B-E BrickClad Backing Grid Office Building GA East Elevation | DR - Drawing (DR) | FAC | 31 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-37030Olympus - LCY11 22032 - GL 06-10 - Phase 37 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-42030Olympus - LCY11 22032 - GL 06-10 - Phase 42 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01546Area 5 - Grids E-H BrickClad Office Building GA East Elevation | DR - Drawing (DR) | FAC | 31 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28237Connection No.: 28237 | CA - Calculations (CA) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-14501Olympus - LCY11 22031 - GL 14-18 - Phase 14 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C04 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-40501Olympus - LCY11 22032 - GL 06-10 - Phase 40 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C04 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03016Cladding Details 17 | DR - Drawing (DR) | FAC | 31 Jul 2026 | 07 Sept 2026Asite issue | C01 | AAccepted | 07 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01547Area 5 - Grids H-J BrickClad Office Building GA East Elevation | DR - Drawing (DR) | FAC | 31 Jul 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-41030Olympus - LCY11 22032 - GL 06-10 - Phase 41 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28259Connection No.: 28259 | CA - Calculations (CA) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28159Connection No.: 28159 | CA - Calculations (CA) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-14501Olympus - LCY11 22031 - GL 14-18 - Phase 14 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C04 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-57601Olympus - LCY11 22031 - GL 18-22 - Phase 57 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29237Connection No.: 29237 | CA - Calculations (CA) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-38030Olympus - LCY11 22032 - GL 06-10 - Phase 38 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-40030Olympus - LCY11 22032 - GL 06-10 - Phase 40 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 31 Jul 2026 | 31 Jul 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93014Stair 3 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 03 Aug 2026 | 03 Aug 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93016Stair 3 Section Views Sheet 1 | DR - Drawing (DR) | STR | 03 Aug 2026 | 03 Aug 2026Asite issue | C01 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93017Stair 3 Section Views Sheet 2 | DR - Drawing (DR) | STR | 03 Aug 2026 | 03 Aug 2026Asite issue | C01 | AAccepted | 14 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93015Stair 3 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 03 Aug 2026 | 03 Aug 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93013Stair 3 3d Views | DR - Drawing (DR) | STR | 03 Aug 2026 | 03 Aug 2026Asite issue | C01 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00052Trade Contractor Weekly Report | RP - Report (RP) | STR | 04 Aug 2026 | 05 Aug 2026Asite issue | C01 | For InformationNo approval required | 05 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00052Trade Contractor Weekly Report | RP - Report (RP) | STR | 04 Aug 2026 | 05 Aug 2026Asite issue | C01 | For InformationNo approval required | 05 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-35804Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet 02 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-38802Olympus - LCY11 22034 - GL 06-08 - Phase 38 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet 02 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-37805Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Plan @+57.770m (G02-Intermediate) Sheet 01 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-23013Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 Steelwork Elevation on GL 24 (GL E to H) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-23501Olympus - LCY11 22031 - GL 22-26 - Phase 23 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-36804Olympus - LCY11 22034 - GL 08-10 - Phase 36 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet 02 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-37801Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet 01 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-29101Olympus - LCY11 22031 - GL 22-26 - Phase 29 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-37802Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet 02 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-35807Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Plan @+59.657m (R03) Sheet 01 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-36050Olympus - LCY11 22034 - GL 08-10 - Phase 36 Steelwork Elevation on GL 8 (GL A to F) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-28101Olympus - LCY11 22031 - GL 22-26 - Phase 28 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-35056Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Girt Elevation on GL J (GL 08 to 10) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-25101Olympus - LCY11 22031 - GL 22-26 - Phase 25 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-26013Olympus - LCY11 22031 - GL 24 & 25 - Phase 26 Steelwork Stair Plans | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | BAccepted with comments | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-37052Olympus - LCY11 22034 - GL 08-10 - Phase 37 Steelwork Elevation on GL F (GL 06 to 08) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-23017Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 Steelwork Elevation on GL G | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-29101Olympus - LCY11 22031 - GL 22-26 - Phase 29 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-28201Olympus - LCY11 22031 - GL 22-26 - Phase 28 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-29201Olympus - LCY11 22031 - GL 22-26 - Phase 29 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-24101Olympus - LCY11 22031 - GL 22-26 - Phase 24 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-37804Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet 02 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-38804Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet 02 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-38808Olympus - LCY11 22034 - GL 06-08 - Phase 38 Steelwork Plan @+59.657m (R03) Sheet 02 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-23401Olympus - LCY11 22031 - GL 22-26 - Phase 23 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-37808Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Plan @+59.657m (R03) Sheet 02 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-37055Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Elevation on GL K (GL 06 to 08) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-28013Olympus - LCY11 22031 - GL 22-26 - Phases 28 & 29 Temporary Steelwork Elevation on GL B & J | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | BAccepted with comments | 07 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-04002Guard House BrickClad Specification Drawings | DR - Drawing (DR) | FAC | 05 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-36054Olympus - LCY11 22034 - GL 08-10 - Phase 36 Steelwork Girt Elevation on GL A (GL 08 to 10) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-35801Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet 01 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-23013Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 Steelwork Elevation on GL 24 (GL E to H) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-00002Steelwork Requirements 2 | DR - Drawing (DR) | FAC | 05 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-35805Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Plan @+57.770m (G02-Intermediate) Sheet 01 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-35057Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Girt Elevation on GL K (GL 08 to 10) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-24011Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 Steelwork Elevation on GL J | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-36055Olympus - LCY11 22034 - GL 08-10 - Phase 36 Steelwork Girt Elevation on GL B (GL 08 to 10) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-37054Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Elevation on GL J (GL 06 to 08) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-38801Olympus - LCY11 22034 - GL 06-08 - Phase 38 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet 01 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-35802Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet 02 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-38803Olympus - LCY11 22034 - GL 06-08 - Phase 38 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet 01 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-35051Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Elevation on GL 9 (GL F to K) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-35054Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Elevation on GL J (GL 08 to 10) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-38051Olympus - LCY11 22034 - GL 06-08 - Phase 38 Steelwork Elevation on GL 7 (GL A to F) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-26014Olympus - LCY11 22031 - GL 24 & 25 - Phase 26 Steelwork Stair Plans | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | BAccepted with comments | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-37803Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet 01 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-37806Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Plan @+57.770m (G02-Intermediate) Sheet 02 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-23011Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 Steelwork Elevation on GL 23 (GL E to H) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-37807Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Plan @+59.657m (R03) Sheet 01 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-37809Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Plan @+63.700m (R03-Parapet) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-00001Steelwork Requirements 1 | DR - Drawing (DR) | FAC | 05 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-00004Steelwork Requirements 4 | DR - Drawing (DR) | FAC | 05 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-36052Olympus - LCY11 22034 - GL 08-10 - Phase 36 Steelwork Elevation on GL A (GL 08 to 10) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-37053Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Elevation on GL G (GL 06 to 08) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-27013Olympus - LCY11 22031 - GL 24 & 25 - Phase 27 Steelwork Stair Plans | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | BAccepted with comments | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-35806Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Plan @+57.770m (G02-Intermediate) Sheet 02 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-36803Olympus - LCY11 22034 - GL 08-10 - Phase 36 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet 01 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-28030Olympus - LCY11 22031 - GL 20-26 - Phase 28 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-00003Steelwork Requirements 3 | DR - Drawing (DR) | FAC | 05 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-26012Olympus - LCY11 22031 - GL 24 & 25 - Phases 26 & 27 Steelwork Stair Section Views | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | BAccepted with comments | 05 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-38805Olympus - LCY11 22034 - GL 06-08 - Phase 38 Steelwork Plan @+57.770m (G02-Intermediate) Sheet 01 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-35053Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Elevation on GL G (GL 08 to 10) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-04001Guard House Feature Panel Specification Drawings | DR - Drawing (DR) | FAC | 05 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-28012Olympus - LCY11 22031 - GL 22-26 - Phases 28 & 29 Temporary Steelwork Elevation on GL 26 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | For InformationNo approval required | 05 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-35055Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Elevation on GL K (GL 08 to 10) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-37050Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Elevation on GL 6 (GL F to K) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-38054Olympus - LCY11 22034 - GL 06-08 - Phase 38 Steelwork Girt Elevation on GL A (GL 06 to 08) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-37051Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Elevation on GL 7 (GL F to K) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-23501Olympus - LCY11 22031 - GL 22-26 - Phase 23 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-24101Olympus - LCY11 22031 - GL 22-26 - Phase 24 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-29030Olympus - LCY11 22031 - GL 20-26 - Phase 29 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-23016Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 Steelwork Elevation on GL F | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-25101Olympus - LCY11 22031 - GL 22-26 - Phase 25 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-28101Olympus - LCY11 22031 - GL 22-26 - Phase 28 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-24013Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 Steelwork Elevation on GL 23 (GL H to K) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-23030Olympus - LCY11 22031 - GL 20-26 - Phases 23 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-29012Olympus - LCY11 22031 - GL 22-26 - Phase 29 - Grid A TO E Temporary Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | For InformationNo approval required | 05 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-29201Olympus - LCY11 22031 - GL 22-26 - Phase 29 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-23401Olympus - LCY11 22031 - GL 22-26 - Phase 23 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-25014Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 Steelwork Elevation on GL 23 (GL A to E) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-23301Olympus - LCY11 22031 - GL 22-26 - Phase 23 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-25011Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 Steelwork Elevation on GL B | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-27014Olympus - LCY11 22031 - GL 24 & 25 - Phase 27 Steelwork Stair Plans | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | BAccepted with comments | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-28014Olympus - LCY11 22031 - GL 22-26 - Phase 28 - Grid F TO K Temporary Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | For InformationNo approval required | 05 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-28201Olympus - LCY11 22031 - GL 22-26 - Phase 28 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-00002Steelwork Requirements 2 | DR - Drawing (DR) | FAC | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-00001Steelwork Requirements 1 | DR - Drawing (DR) | FAC | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-01006Cladding GA Elevation 7 | DR - Drawing (DR) | FAC | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-00003Steelwork Requirements 3 | DR - Drawing (DR) | FAC | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-00004Steelwork Requirements 4 | DR - Drawing (DR) | FAC | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 20 Aug 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-DR-X-03018Cladding Details 19 | DR - Drawing (DR) | FAC | 05 Aug 2026 | 07 Sept 2026Asite issue | C01 | AAccepted | 07 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-26015Olympus - LCY11 22031 - GL 22-26 - Phases 26 Steelwork Elevation on GL 25 (GL J To K) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-25015Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 Steelwork Elevation on GL 24 (GL A to E) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-24022Olympus - LCY11 22031 - GL 22-26 - Phases 24 to 25 Temporary Steelwork Elevation on GL 23 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | For InformationNo approval required | 05 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY16-FKG-GH-XX-DR-X-04000Guard House SIP Panel Specification Drawings | DR - Drawing (DR) | FAC | 05 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-38052Olympus - LCY11 22034 - GL 06-08 - Phase 38 Steelwork Elevation on GL A (GL 06 to 08) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-35901Olympus - LCY11 22034 - GL 08-10 - Phase 35 Temporary Steelwork Plan @ 54.380m (G02) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | For InformationNo approval required | 05 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-35050Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Elevation on GL 8 (GL F to K) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-36051Olympus - LCY11 22034 - GL 08-10 - Phase 36 Steelwork Elevation on GL 9 (GL A to F) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-38806Olympus - LCY11 22034 - GL 06-08 - Phase 38 Steelwork Plan @+57.770m (G02-Intermediate) Sheet 02 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-36805Olympus - LCY11 22034 - GL 08-10 - Phase 36 Steelwork Plan @+57.770m (G02-Intermediate) Sheet 01 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-37057Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Girt Elevation on GL K (GL 06 to 08) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-38050Olympus - LCY11 22034 - GL 06-08 - Phase 38 Steelwork Elevation on GL 6 (GL A to F) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-36808Olympus - LCY11 22034 - GL 08-10 - Phase 36 Steelwork Plan @+59.657m (R03) Sheet 02 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-36053Olympus - LCY11 22034 - GL 08-10 - Phase 36 Steelwork Elevation on GL B (GL 08 to 10) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-36802Olympus - LCY11 22034 - GL 08-10 - Phase 36 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet 02 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-36806Olympus - LCY11 22034 - GL 08-10 - Phase 36 Steelwork Plan @+57.770m (G02-Intermediate) Sheet 02 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-38055Olympus - LCY11 22034 - GL 06-08 - Phase 38 Steelwork Girt Elevation on GL B (GL 06 to 08) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-23011Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 Steelwork Elevation on GL 23 (GL E to H) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-37056Olympus - LCY11 22034 - GL 06-08 - Phase 37 Steelwork Girt Elevation on GL J (GL 06 to 08) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-38053Olympus - LCY11 22034 - GL 06-08 - Phase 38 Steelwork Elevation on GL B (GL 06 to 08) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-35052Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Elevation on GL F (GL 08 to 10) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-35808Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Plan @+59.657m (R03) Sheet 02 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-38807Olympus - LCY11 22034 - GL 06-08 - Phase 38 Steelwork Plan @+59.657m (R03) Sheet 01 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-35809Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Plan @+63.700m (R03-Parapet) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-35803Olympus - LCY11 22034 - GL 08-10 - Phase 35 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet 01 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-36801Olympus - LCY11 22034 - GL 08-10 - Phase 36 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet 01 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-36901Olympus - LCY11 22034 - GL 08-10 - Phase 36 Temporary Steelwork Plan @ 54.380m (G02) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | For InformationNo approval required | 05 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-37901Olympus - LCY11 22034 - GL 06-08 - Phase 37 Temporary Steelwork Plan @ 48.300m (G01) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | For InformationNo approval required | 05 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-36807Olympus - LCY11 22034 - GL 08-10 - Phase 36 Steelwork Plan @+59.657m (R03) Sheet 01 | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C01 | BAccepted with comments | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-23301Olympus - LCY11 22031 - GL 22-26 - Phase 23 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 05 Aug 2026 | 05 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00027Fosroc Galvafroid | TS - Technical Submittals (TS) | FAC | 07 Aug 2026 | 07 Aug 2026Asite issue | P01 | AAccepted | 28 Aug 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93019Stair 1 Plan Views Sheet 1 | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C01 | AAccepted | 28 Aug 2026 | Client Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-43401Olympus - LCY11 22032 - GL 02-06 - Phase 43 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05362Gantry Louvres East Details 3 | DR - Drawing (DR) | FAC | 10 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-47401Olympus - LCY11 22032 - GL 01-06 - Phase 47 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-40321Olympus - LCY11 22032 - GL 01-06 - Phase 43 To 47 Cellshield Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | For InformationNo approval required | 10 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-44010Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Elevation on GL I (GL 2 To 6) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-40222Olympus - LCY11 22032 - GL 01-06 - Phase 43 To 47 Cell Sheild Pots @+13.440m (L02) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | For InformationNo approval required | 10 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05163Gantry Louvres East GA Section 4 | DR - Drawing (DR) | FAC | 10 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93020Stair 1 Plan Views Sheet 2 | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C01 | AAccepted | 28 Aug 2026 | Client Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-43301Olympus - LCY11 22032 - GL 02-06 - Phase 43 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-40422Olympus - LCY11 22032 - GL 01-06 - Phase 43 To 47 Cellshield Plan @+26.440M (L04) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | For InformationNo approval required | 10 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-45018Olympus - LCY11 22032 - GL 02-06 - Phase 45 Steelwork Section | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-40121Olympus - LCY11 22032 - GL 01-06 - Phase 43 To 47 Cell Sheild Plan @ EL+8.940M (L01) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | For InformationNo approval required | 10 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-43016Olympus - LCY11 22032 - GL 02-06 - Phases 43 To 47 Steelwork Elevation on GL F | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-40221Olympus - LCY11 22032 - GL 01-06 - Phase 43 To 47 Cellshield Plan @+13.440M (L02) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | For InformationNo approval required | 10 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-47014Olympus - LCY11 22032 - GL 01-06 - Phase 47 Temporary Steelwork Plan at EL+32.780 (L05) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-46301Olympus - LCY11 22032 - GL 02-06 - Phase 46 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-46011Olympus - LCY11 22032 - GL 02-06 - Phase 43 to 47 Steelwork Elevation on GL 02 (GL F to I) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-47501Olympus - LCY11 22032 - GL 01-06 - Phase 47 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-46501Olympus - LCY11 22032 - GL 02-06 - Phase 46 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-47201Olympus - LCY11 22032 - GL 01-06 - Phase 47 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-47011Olympus - LCY11 22032 - GL 01-06 - Phase 43 to 47 Steelwork Elevation on GL 02 (GL B to F) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-43019Olympus - LCY11 22032 - GL 02-06 - Phase 43 Steelwork Section | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-46301Olympus - LCY11 22032 - GL 02-06 - Phase 46 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-46501Olympus - LCY11 22032 - GL 02-06 - Phase 46 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-46101Olympus - LCY11 22032 - GL 02-06 - Phase 46 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-43018Olympus - LCY11 22032 - GL 02-06 - Phases 43 To 47 Steelwork Elevation on GL H | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-43013Olympus - LCY11 22032 - GL 02-06 - Phase 43 to 47 Steelwork Elevation on GL 04 (GL E to H) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-46101Olympus - LCY11 22032 - GL 02-06 - Phase 46 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-47301Olympus - LCY11 22032 - GL 01-06 - Phase 47 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-43401Olympus - LCY11 22032 - GL 02-06 - Phase 43 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05164Gantry Louvres East GA Section 5 | DR - Drawing (DR) | FAC | 10 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-43301Olympus - LCY11 22032 - GL 02-06 - Phase 43 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-45013Olympus - LCY11 22032 - GL 02-06 - Phase 45 To 47 Steelwork Elevation on GL D | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-45017Olympus - LCY11 22032 - GL 02-06 - Phase 45 Steelwork Section | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-47012Olympus - LCY11 22032 - GL 01-06 - Phase 47 Steelwork Section | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-47401Olympus - LCY11 22032 - GL 01-06 - Phase 47 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-45016Olympus - LCY11 22032 - GL 01-06 - Phase 45 Temporary Steelwork Elevation on GL 4 and 5 | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-46015Olympus - LCY11 22032 - GL 02-06 - Phase 46 Temporary Steelwork Elevation on GL I and 2 | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-40421Olympus - LCY11 22032 - GL 01-06 - Phase 43 To 47 Cellshield Plan @+26.440M (L04) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | For InformationNo approval required | 10 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05064Gantry Louvres East GA Elevation 5 | DR - Drawing (DR) | FAC | 10 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-46401Olympus - LCY11 22032 - GL 02-06 - Phase 46 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-43013Olympus - LCY11 22032 - GL 02-06 - Phase 43 to 47 Steelwork Elevation on GL 04 (GL E to H) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-45012Olympus - LCY11 22032 - GL 02-06 - Phase 45 To 47 Steelwork Elevation on GL C | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-40322Olympus - LCY11 22032 - GL 01-06 - Phase 43 To 47 Cell Sheild Pots @+19.940m (L03) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | For InformationNo approval required | 10 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-43201Olympus - LCY11 22032 - GL 02-06 - Phase 43 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-47201Olympus - LCY11 22032 - GL 01-06 - Phase 47 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-47011Olympus - LCY11 22032 - GL 01-06 - Phase 43 to 47 Steelwork Elevation on GL 02 (GL B to F) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-46201Olympus - LCY11 22032 - GL 02-06 - Phase 46 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05363Gantry Louvres East Details 4 | DR - Drawing (DR) | FAC | 10 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93021Stair 1 Section Views Sheet 1 | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C01 | AAccepted | 14 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-43011Olympus - LCY11 22032 - GL 02-06 - Phase 43 to 47 Steelwork Elevation on GL 05 (GL E to H) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-46401Olympus - LCY11 22032 - GL 02-06 - Phase 46 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-46011Olympus - LCY11 22032 - GL 02-06 - Phase 43 to 47 Steelwork Elevation on GL 02 (GL F to I) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-47501Olympus - LCY11 22032 - GL 01-06 - Phase 47 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-40122Olympus - LCY11 22032 - GL 01-06 - Phase 43 To 47 Cell Sheild Pots @ EL+8.940m (L01) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | For InformationNo approval required | 10 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93018Stair 1 3d Views | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C01 | AAccepted | 14 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-47013Olympus - LCY11 22032 - GL 01-06 - Phase 47 Temporary Steelwork Elevation on GL 2 | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-44011Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Elevation on GL J (GL 2 To 6) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-46012Olympus - LCY11 22032 - GL 02-06 - Phase 46 Steelwork Elevation on GL I (GL 2 To 4) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | BAccepted with comments | 25 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-40522Olympus - LCY11 22032 - GL 01-06 - Phase 43 To 47 Cellshield Plots @+32.940m (L05) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | For InformationNo approval required | 10 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-43201Olympus - LCY11 22032 - GL 02-06 - Phase 43 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-47301Olympus - LCY11 22032 - GL 01-06 - Phase 47 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-46201Olympus - LCY11 22032 - GL 02-06 - Phase 46 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-44015Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Section And Detail View | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-93022Stair 1 Section Views Sheet 2 | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C01 | AAccepted | 14 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05364Gantry Louvres East Details 5 | DR - Drawing (DR) | FAC | 10 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-46013Olympus - LCY11 22032 - GL 02-06 - Phase 46 Steelwork Elevation on GL H (GL 2 To 4) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-40521Olympus - LCY11 22032 - GL 01-06 - Phase 43 To 47 Cellshield Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | For InformationNo approval required | 10 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-46014Olympus - LCY11 22032 - GL 02-06 - Phase 46 Temporary Steelwork Plan at EL+32.780 (L05) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 18 Aug 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-43017Olympus - LCY11 22032 - GL 02-06 - Phases 43 To 47 Steelwork Elevation on GL G | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05063Gantry Louvres East GA Elevation 4 | DR - Drawing (DR) | FAC | 10 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-43011Olympus - LCY11 22032 - GL 02-06 - Phase 43 to 47 Steelwork Elevation on GL 05 (GL E to H) | DR - Drawing (DR) | STR | 10 Aug 2026 | 10 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00053Trade Contractor Weekly Report | RP - Report (RP) | STR | 11 Aug 2026 | 11 Aug 2026Asite issue | C01 | For InformationNo approval required | 11 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05302Gantry Louvres South Details 2 | DR - Drawing (DR) | FAC | 11 Aug 2026 | 18 Aug 2026Asite issue | P02 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05303Gantry Louvres South Details 3 | DR - Drawing (DR) | FAC | 11 Aug 2026 | 18 Aug 2026Asite issue | P01 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05102Gantry Louvres South GA Section 2 | DR - Drawing (DR) | FAC | 11 Aug 2026 | 18 Aug 2026Asite issue | P02 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01101Grids 10-14 Tolerance Channel GA North Elevation | DR - Drawing (DR) | FAC | 11 Aug 2026 | 11 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05103Gantry Louvres South GA Section 3 | DR - Drawing (DR) | FAC | 11 Aug 2026 | 18 Aug 2026Asite issue | P01 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01601Grids 22-24 Tolerance Channel GA North Elevation | DR - Drawing (DR) | FAC | 11 Aug 2026 | 11 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05002Gantry Louvres South GA Elevation 2 | DR - Drawing (DR) | FAC | 11 Aug 2026 | 18 Aug 2026Asite issue | P02 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05301Gantry Louvres South Details 1 | DR - Drawing (DR) | FAC | 11 Aug 2026 | 18 Aug 2026Asite issue | P02 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01201Grids 14-18 Tolerance Channel GA North Elevation | DR - Drawing (DR) | FAC | 11 Aug 2026 | 11 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01401Grids 18-22 Tolerance Channel GA North Elevation | DR - Drawing (DR) | FAC | 11 Aug 2026 | 11 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05003Gantry Louvres South GA Elevation 3 | DR - Drawing (DR) | FAC | 11 Aug 2026 | 18 Aug 2026Asite issue | P02 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01301Grids 06-10 Tolerance Channel GA North Elevation | DR - Drawing (DR) | FAC | 11 Aug 2026 | 11 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05001Gantry Louvres South GA Elevation 1 | DR - Drawing (DR) | FAC | 11 Aug 2026 | 18 Aug 2026Asite issue | P02 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00053Trade Contractor Weekly Report | RP - Report (RP) | STR | 11 Aug 2026 | 11 Aug 2026Asite issue | C01 | For InformationNo approval required | 11 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05101Gantry Louvres South GA Section 1 | DR - Drawing (DR) | FAC | 11 Aug 2026 | 18 Aug 2026Asite issue | P02 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28914Connection No.: 28914 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-42201Olympus - LCY11 22032 - GL 06-10 - Phase 42 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C04 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-41201Olympus - LCY11 22032 - GL 06-10 - Phase 41 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C04 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28901Connection No.: 28901 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28975Connection No.: 28975 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28898Connection No.: 28898 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29038Connection No.: 29038 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29016Connection No.: 29016 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29018Connection No.: 29018 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28990Connection No.: 28990 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29014Connection No.: 29014 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29015Connection No.: 29015 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-CA-S-28606Connection No.: 28606 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | For InformationNo approval required | 17 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29022Connection No.: 29022 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29028Connection No.: 29028 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29621Connection No.: 29621 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28834Connection No.: 28834 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28780Connection No.: 28780 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28837Connection No.: 28837 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28831Connection No.: 28831 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28763Connection No.: 28763 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28848Connection No.: 28848 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28778Connection No.: 28778 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28884Connection No.: 28884 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28875Connection No.: 28875 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28743Connection No.: 28743 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28832Connection No.: 28832 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28847Connection No.: 28847 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28856Connection No.: 28856 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28891Connection No.: 28891 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28765Connection No.: 28765 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28786Connection No.: 28786 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28788Connection No.: 28788 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28774Connection No.: 28774 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28874Connection No.: 28874 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28742Connection No.: 28742 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28777Connection No.: 28777 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28768Connection No.: 28768 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28851Connection No.: 28851 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28881Connection No.: 28881 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28892Connection No.: 28892 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28787Connection No.: 28787 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28791Connection No.: 28791 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28895Connection No.: 28895 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28871Connection No.: 28871 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28886Connection No.: 28886 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28897Connection No.: 28897 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28762Connection No.: 28762 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28792Connection No.: 28792 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28849Connection No.: 28849 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28850Connection No.: 28850 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28873Connection No.: 28873 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28883Connection No.: 28883 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28855Connection No.: 28855 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28983Connection No.: 28983 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28764Connection No.: 28764 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28790Connection No.: 28790 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28779Connection No.: 28779 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28878Connection No.: 28878 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28877Connection No.: 28877 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28900Connection No.: 28900 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28902Connection No.: 28902 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28967Connection No.: 28967 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28776Connection No.: 28776 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28766Connection No.: 28766 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28885Connection No.: 28885 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28896Connection No.: 28896 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28985Connection No.: 28985 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28912Connection No.: 28912 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29017Connection No.: 29017 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29036Connection No.: 29036 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28775Connection No.: 28775 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28887Connection No.: 28887 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28879Connection No.: 28879 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28976Connection No.: 28976 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28904Connection No.: 28904 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28767Connection No.: 28767 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28890Connection No.: 28890 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28876Connection No.: 28876 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28986Connection No.: 28986 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28913Connection No.: 28913 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29021Connection No.: 29021 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29633Connection No.: 29633 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28872Connection No.: 28872 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28981Connection No.: 28981 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28903Connection No.: 28903 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28987Connection No.: 28987 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29606Connection No.: 29606 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29023Connection No.: 29023 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28880Connection No.: 28880 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28905Connection No.: 28905 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28963Connection No.: 28963 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28991Connection No.: 28991 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29025Connection No.: 29025 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28960Connection No.: 28960 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | PendingAwaiting Design Review | 17 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28988Connection No.: 28988 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28917Connection No.: 28917 | CA - Calculations (CA) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C01 | AAccepted | 03 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-41201Olympus - LCY11 22032 - GL 06-10 - Phase 41 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C04 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-42201Olympus - LCY11 22032 - GL 06-10 - Phase 42 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 17 Aug 2026 | 17 Aug 2026Asite issue | C04 | AAccepted | 04 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01652Area 6 - Grids 22-24 K-ROC GA South Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C02 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01515Area 5 - Grids H-J Rainscreen GA West Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | AAccepted | 21 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03060West Rainscreen Details 1 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01302Area 3 - Grids 06-10 K-ROC GA North Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C02 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01653Area 6 - Grids 22-24 Perforated Plank Backing Grid GA South Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05383Ground Floor Louvres Details 4 | DR - Drawing (DR) | FAC | 18 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05182Ground Floor Louvres GA Section 3 | DR - Drawing (DR) | FAC | 18 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01633Area 6 - Grids E-H Rainscreen GA East Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03041East Rainscreen Details 12 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05083Ground Floor Louvres GA Elevation 4 | DR - Drawing (DR) | FAC | 18 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03067West Rainscreen Details 8 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01604Area 6 - Grids 22-24 300mm Deep Rainscreen Backing Grid GA North Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01153Area 1 - Grids 10-14 Perforated Plank Backing Grid GA South Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01253Area 2 - Grids 14-18 Perforated Plank Backing Grid GA South Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01403Area 4 - Grids 18-22 Perforated Plank Backing Grid GA North Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05180Ground Floor Louvres GA Section 1 | DR - Drawing (DR) | FAC | 18 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01634Area 6 - Grids H-J Rainscreen GA East Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05081Ground Floor Louvres GA Elevation 2 | DR - Drawing (DR) | FAC | 18 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03034East Rainscreen Details 5 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03033East Rainscreen Details 4 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 21 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05384Ground Floor Louvres Details 5 | DR - Drawing (DR) | FAC | 18 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01203Area 2 - Grids 14-18 Perforated Plank Backing Grid GA North Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28124Connection No.: 28124 | CA - Calculations (CA) | STR | 18 Aug 2026 | 18 Aug 2026Asite issue | C07 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01513Area 5 - Grids B-E Rainscreen GA West Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | AAccepted | 21 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29193Connection No.: 29193 | CA - Calculations (CA) | STR | 18 Aug 2026 | 18 Aug 2026Asite issue | C01 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05080Ground Floor Louvres GA Elevation 1 | DR - Drawing (DR) | FAC | 18 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03062West Rainscreen Details 3 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03064West Rainscreen Details 5 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 21 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01104Area 1 - Grids 10-14 300mm Deep Rainscreen Backing Grid GA North Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03036East Rainscreen Details 7 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01452Area 4 - Grids 18-22 K-ROC GA South Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C02 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01304Area 3 - Grids 06-10 300mm Deep Rainscreen Backing Grid GA North Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01202Area 2 - Grids 14-18 K-ROC GA North Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C02 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03063West Rainscreen Details 4 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 21 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01654Area 6 - Grids 22-24 300mm Deep Rainscreen Backing Grid GA South Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28306Connection No.: 28306 | CA - Calculations (CA) | STR | 18 Aug 2026 | 18 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05381Ground Floor Louvres Details 2 | DR - Drawing (DR) | FAC | 18 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01013RAINSCREEN CLADDING WEST ELEVATION & SECTIONS PANELS | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | P01 | PendingAwaiting Design Review | 21 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05183Ground Floor Louvres GA Section 4 | DR - Drawing (DR) | FAC | 18 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03069West Rainscreen Details 10 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03061West Rainscreen Details 2 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03035East Rainscreen Details 6 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01014RAINSCREEN CLADDING EAST ELEVATION & SECTIONS PANELS | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | P01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05084Ground Floor Louvres GA Elevation 5 | DR - Drawing (DR) | FAC | 18 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28308Connection No.: 28308 | CA - Calculations (CA) | STR | 18 Aug 2026 | 18 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01352Area 3 - Grids 06-10 K-ROC GA South Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C02 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03030East Rainscreen Details 1 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | CRejected | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01102Area 1 - Grids 10-14 K-ROC GA North Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C02 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01402Area 4 - Grids 18-22 K-ROC GA North Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C02 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28309Connection No.: 28309 | CA - Calculations (CA) | STR | 18 Aug 2026 | 18 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28121Connection No.: 28121 | CA - Calculations (CA) | STR | 18 Aug 2026 | 18 Aug 2026Asite issue | C07 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28121Connection No.: 28121 | CA - Calculations (CA) | STR | 18 Aug 2026 | 18 Aug 2026Asite issue | C07 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01404Area 4 - Grids 18-22 300mm Deep Rainscreen Backing Grid GA North Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05382Ground Floor Louvres Details 3 | DR - Drawing (DR) | FAC | 18 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01303Area 3 - Grids 06-10 Perforated Plank Backing Grid GA North Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29002CMP ALIGN E & F (axes 1 to 26) | CA - Calculations (CA) | STR | 18 Aug 2026 | 18 Aug 2026Asite issue | C20 | For InformationNo approval required | 18 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05184Ground Floor Louvres GA Section 5 | DR - Drawing (DR) | FAC | 18 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01154Area 1 - Grids 10-14 300mm Deep Rainscreen Backing Grid GA South Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28124Connection No.: 28124 | CA - Calculations (CA) | STR | 18 Aug 2026 | 18 Aug 2026Asite issue | C07 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01254Area 2 - Grids 14-18 300mm Deep Rainscreen Backing Grid GA South Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01632Area 6 - Grids B-E Rainscreen GA East Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03032East Rainscreen Details 3 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03038East Rainscreen Details 9 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03068West Rainscreen Details 9 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01603Area 6 - Grids 22-24 Perforated Plank Backing Grid GA North Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05181Ground Floor Louvres GA Section 2 | DR - Drawing (DR) | FAC | 18 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29002CMP ALIGN E & F (axes 1 to 26) | CA - Calculations (CA) | STR | 18 Aug 2026 | 18 Aug 2026Asite issue | C20 | For InformationNo approval required | 18 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01152Area 1 - Grids 10-14 K-ROC GA South Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C02 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05082Ground Floor Louvres GA Elevation 3 | DR - Drawing (DR) | FAC | 18 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03031East Rainscreen Details 2 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03037East Rainscreen Details 8 | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01602Area 6 - Grids 22-24 K-ROC GA North Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C02 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01252Area 2 - Grids 14-18 K-ROC GA South Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C02 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01103Area 1 - Grids 10-14 Perforated Plank Backing Grid GA North Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01453Area 4 - Grids 18-22 Perforated Plank Backing Grid GA South Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01353Area 3 - Grids 06-10 Perforated Plank Backing Grid GA South Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01514Area 5 - Grids E-H Rainscreen GA West Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 20 Aug 2026Asite issue | C01 | AAccepted | 21 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01204Area 2 - Grids 14-18 300mm Deep Rainscreen Backing Grid GA North Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01354Area 3 - Grids 06-10 300mm Deep Rainscreen Backing Grid GA South Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01454Area 4 - Grids 18-22 300mm Deep Rainscreen Backing Grid GA South Elevation | DR - Drawing (DR) | FAC | 18 Aug 2026 | 27 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05380Ground Floor Louvres Details 1 | DR - Drawing (DR) | FAC | 18 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY18-WHL-DC-XX-DR-S-13004Olympus - LCY18 22035 - GL 22 - 28 - Phase 13 Steelwork Section and Details | DR - Drawing (DR) | STR | 19 Aug 2026 | 19 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00054Trade Contractor Weekly Report | RP - Report (RP) | STR | 19 Aug 2026 | 19 Aug 2026Asite issue | C01 | For InformationNo approval required | 19 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-00-DR-S-14002Olympus - LCY18 22035 - GL 01 - 06 - Phase 14 Steelwork Foundation Plan at EL+1.520m | DR - Drawing (DR) | STR | 19 Aug 2026 | 19 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-94008Gratings Axis 6-10 | DR - Drawing (DR) | STR | 19 Aug 2026 | 19 Aug 2026Asite issue | P01 | CRejected | 27 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY18-WHL-DC-XX-DR-S-10002Olympus - LCY18 22035 - GL 01 - 28 - Phase 11 to 14 Steelwork Typical Base Plate Details | DR - Drawing (DR) | STR | 19 Aug 2026 | 19 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00054Trade Contractor Weekly Report | RP - Report (RP) | STR | 19 Aug 2026 | 19 Aug 2026Asite issue | C01 | For InformationNo approval required | 19 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-XX-DR-S-14004Olympus - LCY18 22035 - GL 01 - 06 - Phase 14 Steelwork Section and Details | DR - Drawing (DR) | STR | 19 Aug 2026 | 19 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-00-DR-S-13002Olympus - LCY18 22035 - GL 22 - 28 - Phase 13 Steelwork Foundation Plan at EL+1.520m | DR - Drawing (DR) | STR | 19 Aug 2026 | 19 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-00-DR-S-12002Olympus - LCY18 22035 - GL 06 -13 - Phase 12 Steelwork Foundation Plan at EL+1.520m | DR - Drawing (DR) | STR | 19 Aug 2026 | 19 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-RF-DR-S-14003Olympus - LCY18 22035 - GL 01 - 06 - Phase 14 Steelwork Roof Level Plan at EL+8.422m | DR - Drawing (DR) | STR | 19 Aug 2026 | 19 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-XX-DR-S-10001Olympus - LCY18 22035 - GL 01 - 28 - Phase 11 to 14 Steelwork Typical Base Plate Details | DR - Drawing (DR) | STR | 19 Aug 2026 | 19 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status B - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28340Steel Stairs 1 Calculations | CA - Calculations (CA) | STR | 19 Aug 2026 | 19 Aug 2026Asite issue | P01 | PendingAwaiting Design Review | 19 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY18-WHL-DC-00-DR-S-11002Olympus - LCY18 22035 - GL 13 - 22 - Phase 11 Steelwork Foundation Plan at EL+1.520m | DR - Drawing (DR) | STR | 19 Aug 2026 | 19 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| ARC-003Reflected Ceiling Plan | drawing | ARC | 19 Aug 2026 | 18 Aug 2026Asite issue | P01 | CRejected | 20 Aug 2026 | Returned to OriginatorDesign Document Review | A1 · R1 · !0 |
| LCY18-WHL-DC-RF-DR-S-13003Olympus - LCY18 22035 - GL 22 - 28 - Phase 13 Steelwork Roof Level Plan at EL+8.422m | DR - Drawing (DR) | STR | 19 Aug 2026 | 19 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-WHL-DC-XX-DR-S-14005Olympus - LCY18 22035 - GL 01 - 06 - Phase 14 Steelwork Section and Details | DR - Drawing (DR) | STR | 19 Aug 2026 | 19 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY18-FKG-DC-XX-CA-X-00001Dust Canopy Structural Cladding Calculations | CA - Calculations (CA) | FAC | 20 Aug 2026 | 20 Aug 2026Asite issue | C01 | BAccepted with comments | 28 Aug 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28728Connection No.: 28728 | CA - Calculations (CA) | STR | 20 Aug 2026 | 20 Aug 2026Asite issue | C02 | AAccepted | 09 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28652Connection No.: 28652 | CA - Calculations (CA) | STR | 20 Aug 2026 | 20 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Back to Workflow Originator For ActionRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-24014Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 Steelwork Elevation on GL 24 (GL H to K) | DR - Drawing (DR) | STR | 20 Aug 2026 | 20 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28723Connection No.: 28723 | CA - Calculations (CA) | STR | 20 Aug 2026 | 20 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28738Connection No.: 28738 | CA - Calculations (CA) | STR | 20 Aug 2026 | 20 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28710Connection No.: 28710 | CA - Calculations (CA) | STR | 20 Aug 2026 | 20 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28725Connection No.: 28725 | CA - Calculations (CA) | STR | 20 Aug 2026 | 20 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28712Connection No.: 28712 | CA - Calculations (CA) | STR | 20 Aug 2026 | 20 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28729Connection No.: 28729 | CA - Calculations (CA) | STR | 20 Aug 2026 | 20 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28709Connection No.: 28709 | CA - Calculations (CA) | STR | 20 Aug 2026 | 20 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28343Steel Stairs 2 To 4 Calculations | CA - Calculations (CA) | STR | 20 Aug 2026 | 20 Aug 2026Asite issue | P01 | PendingAwaiting Design Review | 21 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-12401Olympus - LCY11 22031 - GL 14-18 - Phase 12 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28294Connection No.: 28294 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03120BRICKCLAD DETAILS 21 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01892STAIR 04 NORTH WEST - RAINSCREEN GA ELEVATION 3 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01896STAIR 04 NORTH WEST - RAINSCREEN GA ELEVATION 7 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01890STAIR 04 NORTH WEST - RAINSCREEN GA ELEVATION 1 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01741STAIR 01 SOUTH WEST - RAINSCREEN GA ELEVATION 2 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03105BRICKCLAD DETAILS 6 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-25010Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-24012Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 Steelwork Elevation on GL K | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03111BRICKCLAD DETAILS 12 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01570AREA 5 - GRIDS I-E RAINSCREEN OFFICE BUILDING GA WEST ELEVATION 1 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01743STAIR 01 SOUTH WEST - RAINSCREEN GA ELEVATION 4 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03101BRICKCLAD DETAILS 2 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03107BRICKCLAD DETAILS 8 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03114BRICKCLAD DETAILS 15 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01572AREA 5 - GRIDS E-D RAINSCREEN OFFICE BUILDING GA WEST ELEVATION 1 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01745STAIR 01 SOUTH WEST - RAINSCREEN GA ELEVATION 6 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03117BRICKCLAD DETAILS 18 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01894STAIR 04 NORTH WEST - RAINSCREEN GA ELEVATION 5 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01891STAIR 04 NORTH WEST - RAINSCREEN GA ELEVATION 2 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01742STAIR 01 SOUTH WEST - RAINSCREEN GA ELEVATION 3 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-81611Olympus -LCY11 22032 -GL 06-10 - Phase 77 to 82 Steelwork Elevation on GL 06 (GL H to K) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01543AREA 5 - GRIDS E - D K-ROC OFFICE BUILDING GA WEST ELEVATION 1 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03103BRICKCLAD DETAILS 4 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03109BRICKCLAD DETAILS 10 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03118BRICKCLAD DETAILS 19 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03100BRICKCLAD DETAILS 1 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03106BRICKCLAD DETAILS 7 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-82611Olympus -LCY11 22032 -GL 06-10 - Phase 77 to 82 Steelwork Elevation on GL 06 (GL A to E) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03119BRICKCLAD DETAILS 20 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03110BRICKCLAD DETAILS 11 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03104BRICKCLAD DETAILS 5 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01544AREA 5 - GRIDS 4 - 1 K-ROC OFFICE BUILDING GA WEST ELEVATION 1 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01895STAIR 04 NORTH WEST - RAINSCREEN GA ELEVATION 6 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03113BRICKCLAD DETAILS 14 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01571AREA 5 - GRIDS I-E RAINSCREEN OFFICE BUILDING GA WEST ELEVATION 2 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01744STAIR 01 SOUTH WEST - RAINSCREEN GA ELEVATION 5 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01893STAIR 04 NORTH WEST - RAINSCREEN GA ELEVATION 4 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03121BRICKCLAD DETAILS 22 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03102BRICKCLAD DETAILS 3 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01746STAIR 01 SOUTH WEST - RAINSCREEN GA ELEVATION 7 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03108BRICKCLAD DETAILS 9 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01711STAIR 01 SOUTH WEST - K-ROC GA ELEVATION 2 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | AAccepted | 04 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01866STAIR 04 NORTH WEST - K-ROC GA ELEVATION 7 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | AAccepted | 04 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01864STAIR 04 NORTH WEST - K-ROC GA ELEVATION 5 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | AAccepted | 04 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01716STAIR 01 SOUTH WEST - K-ROC GA ELEVATION 7 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | AAccepted | 04 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01713STAIR 01 SOUTH WEST - K-ROC GA ELEVATION 4 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | AAccepted | 04 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01740STAIR 01 SOUTH WEST - RAINSCREEN GA ELEVATION 1 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01861STAIR 04 NORTH WEST - K-ROC GA ELEVATION 2 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | AAccepted | 04 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03116BRICKCLAD DETAILS 17 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01862STAIR 04 NORTH WEST - K-ROC GA ELEVATION 3 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | AAccepted | 04 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-11018Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL F | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-12201Olympus - LCY11 22031 - GL 14-18 - Phase 12 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-13201Olympus - LCY11 22031 - GL 14-18 - Phase 13 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01710STAIR 01 SOUTH WEST - K-ROC GA ELEVATION 1 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | AAccepted | 04 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-16201Olympus - LCY11 22031 - GL 14-18 - Phase 16 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-14013Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 18 (GL E TO H) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01865STAIR 04 NORTH WEST - K-ROC GA ELEVATION 6 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | AAccepted | 04 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-11001Olympus - LCY11 22031 - GL 14-20 - Phases 11 to 19 Steelwork Foundation Plan (GL H TO K) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01863STAIR 04 NORTH WEST - K-ROC GA ELEVATION 4 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | AAccepted | 04 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01715STAIR 01 SOUTH WEST - K-ROC GA ELEVATION 6 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | AAccepted | 04 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-14101Olympus - LCY11 22031 - GL 14-18 - Phase 14 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01712STAIR 01 SOUTH WEST - K-ROC GA ELEVATION 3 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | AAccepted | 04 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01860STAIR 04 NORTH WEST - K-ROC GA ELEVATION 1 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | AAccepted | 04 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01714STAIR 01 SOUTH WEST - K-ROC GA ELEVATION 5 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | AAccepted | 04 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-16301Olympus - LCY11 22031 - GL 14-18 - Phase 16 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-12401Olympus - LCY11 22031 - GL 14-18 - Phase 12 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-13401Olympus - LCY11 22031 - GL 14-18 - Phase 13 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-16501Olympus - LCY11 22031 - GL 14-18 - Phase 16 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28118Connection No.: 28118 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C05 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-42011Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL 06 (GL A to E) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-13501Olympus - LCY11 22031 - GL 14-18 - Phase 13 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-15501Olympus - LCY11 22031 - GL 14-18 - Phase 15 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-11015Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 16 (GL E TO H) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-11011Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 14 (GL E TO H) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13011Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | BAccepted with comments | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12013Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL K | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28122Connection No.: 28122 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28219Connection No.: 28219 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01542AREA 5 - GRIDS G - D K-ROC OFFICE BUILDING GA WEST ELEVATION 1 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-13101Olympus - LCY11 22031 - GL 14-18 - Phase 13 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | BAccepted with comments | 10 Sept 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-15201Olympus - LCY11 22031 - GL 14-18 - Phase 15 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-15401Olympus - LCY11 22031 - GL 14-18 - Phase 15 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29265Connection No.: 29265 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-12301Olympus - LCY11 22031 - GL 14-18 - Phase 12 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01541AREA 5 - GRIDS I - G K-ROC OFFICE BUILDING GA WEST ELEVATION 2 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-14011Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 17 (GL E TO H) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-16011Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 18 (GL A TO E) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-16010Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 17 (GL A TO E) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13015Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 14 (GL A TO E) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13031Olympus - LCY11 22031 - GL 14-18 - Phases 13 Steelwork Section & Detail Views | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12022Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Temporary Steelwork Elevation on GL I & J | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28160Connection No.: 28160 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 21 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12023Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Temporary Steelwork Elevation on GL K | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-15010Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 17 (GL H TO K) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12013Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL K | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-67601Olympus - LCY11 22031 - GL 22-26 - Phase 67 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C01 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13011Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | BAccepted with comments | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-11015Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 16 (GL E TO H) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-15501Olympus - LCY11 22031 - GL 14-18 - Phase 15 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-13501Olympus - LCY11 22031 - GL 14-18 - Phase 13 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-12030Olympus - LCY11 22031 - GL 14-20 - Phases 12 Steelwork Foundation plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-11032Olympus - LCY11 22031 - GL 14-20 - Phases 11 to 19 Steelwork Foundation Details - Sheet 2 | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12022Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Temporary Steelwork Elevation on GL I & J | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13031Olympus - LCY11 22031 - GL 14-18 - Phases 13 Steelwork Section & Detail Views | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-13401Olympus - LCY11 22031 - GL 14-18 - Phase 13 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-14011Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 17 (GL E TO H) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-14030Olympus - LCY11 22031 - GL 14-20 - Phases 14 Steelwork Foundation plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12031Olympus - LCY11 22031 - GL 14-18 - Phases 12 Steelwork Section & Detail Views | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-15011Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 18 (GL H TO K) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-13201Olympus - LCY11 22031 - GL 14-18 - Phase 13 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-14401Olympus - LCY11 22031 - GL 14-18 - Phase 14 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-11031Olympus - LCY11 22031 - GL 14-20 - Phases 11 to 19 Steelwork Foundation Details - Sheet 1 | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-11022Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Temporary Steelwork Elevation on GL E & H | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13017Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 16 (GL A TO E) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-16022Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Temporary Steelwork Elevation on GL 18 | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-16201Olympus - LCY11 22031 - GL 14-18 - Phase 16 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-13101Olympus - LCY11 22031 - GL 14-18 - Phase 13 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | BAccepted with comments | 10 Sept 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-11018Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL F | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-11013Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 15 (GL E TO H) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-14201Olympus - LCY11 22031 - GL 14-18 - Phase 14 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12014Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 14 (GL H TO K) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | BAccepted with comments | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13023Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Temporary Steelwork Elevation on GL 16 & 17 | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-11321Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 CellSheild Plan @+19.940M (L03) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-15401Olympus - LCY11 22031 - GL 14-18 - Phase 15 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-12301Olympus - LCY11 22031 - GL 14-18 - Phase 12 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-12101Olympus - LCY11 22031 - GL 14-18 - Phase 12 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | BAccepted with comments | 10 Sept 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-16030Olympus - LCY11 22031 - GL 14-20 - Phases 16 Steelwork Foundation plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13016Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 15 (GL A TO E) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-11034Olympus - LCY11 22031 - GL 14-20 - Phases 11 to 19 Steelwork Foundation Details - Sheet 3 | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-13301Olympus - LCY11 22031 - GL 14-18 - Phase 13 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-15301Olympus - LCY11 22031 - GL 14-18 - Phase 15 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-16011Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 18 (GL A TO E) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| FAC-001Curtain Wall Typical Bay Drawing | drawing | FAC | 21 Aug 2026 | —Awaiting issue | P01 | — | — | — | A1 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-11002Olympus - LCY11 22031 - GL 14-20 - Phases 11 to 19 Steelwork Foundation Plan (GL A TO E) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-11033Olympus - LCY11 22031 - GL 14-18 - Phases 11 Steelwork Section & Detail Views | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 21 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13022Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Temporary Steelwork Elevation on GL 14 & 15 | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-11221Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 CellSheild Plan @+13.440M (L02) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-15301Olympus - LCY11 22031 - GL 14-18 - Phase 15 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-13301Olympus - LCY11 22031 - GL 14-18 - Phase 13 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-12201Olympus - LCY11 22031 - GL 14-18 - Phase 12 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-15030Olympus - LCY11 22031 - GL 14-20 - Phases 15 Steelwork Foundation plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-16401Olympus - LCY11 22031 - GL 14-18 - Phase 16 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13015Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 14 (GL A TO E) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-11001Olympus - LCY11 22031 - GL 14-20 - Phases 11 to 19 Steelwork Foundation Plan (GL H TO K) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-14101Olympus - LCY11 22031 - GL 14-18 - Phase 14 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-16010Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 17 (GL A TO E) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-11013Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 15 (GL E TO H) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13024Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Temporary Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-11421Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 CellSheild Plan @+26.440M (L04) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-14201Olympus - LCY11 22031 - GL 14-18 - Phase 14 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-20003Olympus - LCY11 22031 - GL 20-26 - Phases 20 to 29 Steelwork Foundation Plan (GL E TO H) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-16301Olympus - LCY11 22031 - GL 14-18 - Phase 16 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29266Connection No.: 29266 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-41011Olympus - LCY11 22032 - GL 06-10 - Phase 37 to 42 Steelwork Elevation on GL 06 (GL H to K) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-11032Olympus - LCY11 22031 - GL 14-20 - Phases 11 to 19 Steelwork Foundation Details - Sheet 2 | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-11002Olympus - LCY11 22031 - GL 14-20 - Phases 11 to 19 Steelwork Foundation Plan (GL A TO E) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-12030Olympus - LCY11 22031 - GL 14-20 - Phases 12 Steelwork Foundation plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13025Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Temporary Steelwork Elevation on GL B & C | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12016Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 16 (GL H TO K) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-11030Olympus - LCY11 22031 - GL 14-20 - Phases 11 Steelwork Foundation plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29240Connection No.: 29240 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28270Connection No.: 28270 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01785Stair 02 South East - Built-Up GA Elevation 1 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01770Stair 02 South East - BrickClad Backing Grid GA Elevation 1 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28231Connection No.: 28231 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01725Stair 01 South West - Digital Line GA Elevation 1 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-11421Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 CellSheild Plan @+26.440M (L04) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13024Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Temporary Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-11003Olympus - LCY11 22031 - GL 14-20 - Phases 11 to 19 Steelwork Foundation Plan (GL E TO H) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-12101Olympus - LCY11 22031 - GL 14-18 - Phase 12 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | BAccepted with comments | 10 Sept 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28153Connection No.: 28153 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12015Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 15 (GL H TO K) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01780Stair 02 South East - BrickClad GA Elevation 1 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01765Stair 02 South East - Digital Line Backing Grid GA Elevation 1 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01735Stair 01 South West - Built-Up GA Elevation 1 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01720Stair 01 South West - BrickClad Backing Grid GA Elevation 1 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-11521Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 CellSheild Plan @+32.940M (L05) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-15011Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 18 (GL H TO K) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12031Olympus - LCY11 22031 - GL 14-18 - Phases 12 Steelwork Section & Detail Views | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-14030Olympus - LCY11 22031 - GL 14-20 - Phases 14 Steelwork Foundation plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-15010Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 17 (GL H TO K) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01776Stair 02 South East - Digital Line GA Elevation 2 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12023Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Temporary Steelwork Elevation on GL K | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01761Stair 02 South East - K-ROC GA Elevation 2 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01731Stair 01 South West - BrickClad GA Elevation 2 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-13030Olympus - LCY11 22031 - GL 14-20 - Phases 13 Steelwork Foundation plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-16022Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Temporary Steelwork Elevation on GL 18 | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13017Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 16 (GL A TO E) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-14401Olympus - LCY11 22031 - GL 14-18 - Phase 14 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01775Stair 02 South East - Digital Line GA Elevation 1 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01760Stair 02 South East - K-ROC GA Elevation 1 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01730Stair 01 South West - BrickClad GA Elevation 1 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-11022Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Temporary Steelwork Elevation on GL E & H | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-11031Olympus - LCY11 22031 - GL 14-20 - Phases 11 to 19 Steelwork Foundation Details - Sheet 1 | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-11321Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 CellSheild Plan @+19.940M (L03) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13023Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Temporary Steelwork Elevation on GL 16 & 17 | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12014Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 14 (GL H TO K) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | BAccepted with comments | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-11003Olympus - LCY11 22031 - GL 14-20 - Phases 11 to 19 Steelwork Foundation Plan (GL E TO H) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-11221Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 CellSheild Plan @+13.440M (L02) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01786Stair 02 South East - Built-Up GA Elevation 2 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01771Stair 02 South East - BrickClad Backing Grid GA Elevation 2 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13016Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 15 (GL A TO E) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01726Stair 01 South West - Digital Line GA Elevation 2 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-16030Olympus - LCY11 22031 - GL 14-20 - Phases 16 Steelwork Foundation plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-11521Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 CellSheild Plan @+32.940M (L05) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12015Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 15 (GL H TO K) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01540AREA 5 - GRIDS I - G K-ROC OFFICE BUILDING GA WEST ELEVATION 1 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01545GRIDS 4 - 1 K-ROC OFFICE BUILDING GA WEST ELEVATION 2 | DR - Drawing (DR) | FAC | 21 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-12501Olympus - LCY11 22031 - GL 14-18 - Phase 12 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-16401Olympus - LCY11 22031 - GL 14-18 - Phase 16 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28122Connection No.: 28122 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28153Connection No.: 28153 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01781Stair 02 South East - BrickClad GA Elevation 2 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01766Stair 02 South East - Digital Line Backing Grid GA Elevation 2 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01736Stair 01 South West - Built-Up GA Elevation 2 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01721Stair 01 South West - BrickClad Backing Grid GA Elevation 2 | DR - Drawing (DR) | FAC | 21 Aug 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-11019Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL G | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-11019Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL G | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-11011Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 14 (GL E TO H) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28231Connection No.: 28231 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-16501Olympus - LCY11 22031 - GL 14-18 - Phase 16 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28270Connection No.: 28270 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-11030Olympus - LCY11 22031 - GL 14-20 - Phases 11 Steelwork Foundation plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-29263Connection No.: 29263 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 04 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-12016Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 16 (GL H TO K) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13025Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Temporary Steelwork Elevation on GL B & C | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-1154522031 - GL 14-18 - Phases 11 to 16 ComFlor 80 and Shear Stud Layout to L05 | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | BAccepted with comments | 10 Sept 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28118Connection No.: 28118 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C05 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-15030Olympus - LCY11 22031 - GL 14-20 - Phases 15 Steelwork Foundation plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28160Connection No.: 28160 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 21 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-20003Olympus - LCY11 22031 - GL 20-26 - Phases 20 to 29 Steelwork Foundation Plan (GL E TO H) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C04 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-14013Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Steelwork Elevation on GL 18 (GL E TO H) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-12501Olympus - LCY11 22031 - GL 14-18 - Phase 12 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-15201Olympus - LCY11 22031 - GL 14-18 - Phase 15 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-13022Olympus - LCY11 22031 - GL 14-18 - Phases 11 to 16 Temporary Steelwork Elevation on GL 14 & 15 | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | For InformationNo approval required | 21 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-11033Olympus - LCY11 22031 - GL 14-18 - Phases 11 Steelwork Section & Detail Views | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 21 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-CA-S-28219Connection No.: 28219 | CA - Calculations (CA) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Status A - CMTCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-13030Olympus - LCY11 22031 - GL 14-20 - Phases 13 Steelwork Foundation plan - Coupler Setting Out | DR - Drawing (DR) | STR | 21 Aug 2026 | 21 Aug 2026Asite issue | C02 | AAccepted | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| FAC-002Façade Fire Barrier Layout | drawing | FAC | 24 Aug 2026 | 25 Aug 2026Asite issue | P01 | Under Review | — | Fire Consultant ReviewDesign Document Review | A1 · R0 · !0 |
| STR-001Slab Edge Setting Out | drawing | STR | 25 Aug 2026 | 24 Aug 2026Asite issue | P02 | BAccepted with comments | 26 Aug 2026 | Returned with CommentsDesign Document Review | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-04000TYPICAL K-ROC SPECIFICATION HEAD & CILL (BEHIND RAINSCREEN) | DR - Drawing (DR) | FAC | 25 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-27011Olympus - LCY11 22031 - GL 22-26 - Phase 23 to 29 Steelwork Elevation on GL 25 (GL A to F) | DR - Drawing (DR) | STR | 25 Aug 2026 | 25 Aug 2026Asite issue | C03 | BAccepted with comments | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-04001K-ROC EXPLODED INSTILLATION JOINT DETAILS | DR - Drawing (DR) | FAC | 25 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-20035Olympus - LCY11 22031 - GL 23-26 - Phases 23 to 29 Steelwork Foundation Details - Sheet 5 | DR - Drawing (DR) | STR | 25 Aug 2026 | 25 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00055Trade Contractor Weekly Report | RP - Report (RP) | STR | 25 Aug 2026 | 25 Aug 2026Asite issue | C01 | For InformationNo approval required | 25 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-20036Olympus - LCY11 22031 - GL 23-26 - Phases 23 to 29 Steelwork Foundation Details - Sheet 6 | DR - Drawing (DR) | STR | 25 Aug 2026 | 25 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-TS-X-00028KINGSPAN K-ROC EVOLUTION PANEL | TS - Technical Submittals (TS) | FAC | 25 Aug 2026 | 25 Aug 2026Asite issue | P01 | BAccepted with comments | 04 Sept 2026 | Status B (Accepted with Comments)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00055Trade Contractor Weekly Report | RP - Report (RP) | STR | 25 Aug 2026 | 25 Aug 2026Asite issue | C01 | For InformationNo approval required | 25 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03016North & South Rainscreen Details 16 | DR - Drawing (DR) | FAC | 25 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-20034Olympus - LCY11 22031 - GL 23-26 - Phases 23 to 29 Steelwork Foundation Details - Sheet 4 | DR - Drawing (DR) | STR | 25 Aug 2026 | 25 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-03017North & South Rainscreen Details 17 | DR - Drawing (DR) | FAC | 25 Aug 2026 | 01 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 01 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-10001Steelwork Plan Early Columns - Phase 10 | DR - Drawing (DR) | STR | 25 Aug 2026 | 25 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | Client Lead Status Change,Client CommentRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-27011Olympus - LCY11 22031 - GL 22-26 - Phase 23 to 29 Steelwork Elevation on GL 25 (GL A to F) | DR - Drawing (DR) | STR | 25 Aug 2026 | 25 Aug 2026Asite issue | C03 | BAccepted with comments | 02 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-63614Olympus - LCY11 22031 - GL 22-26 - Phases 63 to 67 Steelwork Elevation on GL 23 (GL E TO H) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-66607Olympus - LCY11 22031 - GL 22-26 - Phase 67 Steelwork Stair Section View | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | BAccepted with comments | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-64611Olympus - LCY11 22031 - GL 22-26 - Phases 63 to 67 Steelwork Elevation on GL J | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-64612Olympus - LCY11 22031 - GL 22-26 - Phases 63 to 67 Steelwork Elevation on GL K | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-67701Olympus - LCY11 22031 - GL 22-26 - Phase 67 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-64613Olympus - LCY11 22031 - GL 22-26 - Phases 63 to 67 Steelwork Elevation on GL 23 (GL H to K) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-65610Olympus - LCY11 22031 - GL 22-26 - Phases 63 to 67 Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-63701Olympus - LCY11 22031 - GL 22-26 - Phase 63 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-63615Olympus - LCY11 22031 - GL 22-26 - Phases 63 to 67 Steelwork Elevation on GL 24 (GL E TO H) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-65701Olympus - LCY11 22031 - GL 22-26 - Phase 65 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-66602Olympus - LCY11 22031 - GL 22-26 - Phases 63 to 67 Steelwork Elevation on GL 25 (GL F to K) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-65601Olympus - LCY11 22031 - GL 22-26 - Phase 65 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-64701Olympus - LCY11 22031 - GL 22-26 - Phase 64 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-66605Olympus - LCY11 22031 - GL 22-26 - Phase 66 Steelwork Stair Section View | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | BAccepted with comments | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-67602Olympus - LCY11 22031 - GL 22-26 - Phases 63 to 67 Steelwork Elevation on GL 25 (GL A to F) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-64614Olympus - LCY11 22031 - GL 22-26 - Phases 63 to 67 Steelwork Elevation on GL 24 (GL H to K) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-66604Olympus - LCY11 22031 - GL 22-26 - Phase 66 Steelwork Stair Plans | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | BAccepted with comments | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-66601Olympus - LCY11 22031 - GL 22-26 - Phase 66 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-63601Olympus - LCY11 22031 - GL 22-26 - Phase 63 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-65614Olympus - LCY11 22031 - GL 22-26 - Phases 63 to 67 Steelwork Elevation on GL 23 (GL A to E) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-66701Olympus - LCY11 22031 - GL 22-26 - Phase 66 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-67604Olympus - LCY11 22031 - GL 22-26 - Phase 67 Steelwork Stair Plans | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | BAccepted with comments | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-66603Olympus - LCY11 22031 - GL 22-26 - Phases 66 to 67 Steelwork Elevation on GL 25 (GL J to K) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | BAccepted with comments | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-65615Olympus - LCY11 22031 - GL 22-26 - Phases 63 to 67 Steelwork Elevation on GL 24 (GL A to E) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-80611Olympus -LCY11 22032 -GL 06-10 - Phase 77 to 82 Steelwork Elevation on GL 06 (GL E to H) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C03 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-66606Olympus - LCY11 22031 - GL 22-26 - Phase 66 Steelwork Stair Section View | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | BAccepted with comments | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-63612Olympus - LCY11 22031 - GL 22-26 - Phases 63 to 67 Steelwork Elevation on GL G | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-64601Olympus - LCY11 22031 - GL 22-26 - Phase 64 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-67605Olympus - LCY11 22031 - GL 22-26 - Phase 67 Steelwork Stair Plans | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | BAccepted with comments | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-63611Olympus - LCY11 22031 - GL 22-26 - Phases 63 to 67 Steelwork Elevation on GL F | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | AAccepted | 26 Aug 2026 | Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-67603Olympus - LCY11 22031 - GL 22-26 - Phase 67 Temporary Steelwork Elevation on GL 25 | DR - Drawing (DR) | STR | 26 Aug 2026 | 26 Aug 2026Asite issue | C02 | For InformationNo approval required | 26 Aug 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-46030Olympus - LCY11 22032 - GL 01-06 - Phases 46 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 27 Aug 2026 | 27 Aug 2026Asite issue | C01 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-44030Olympus - LCY11 22032 - GL 01-06 - Phases 44 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 27 Aug 2026 | 27 Aug 2026Asite issue | C01 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-47030Olympus - LCY11 22032 - GL 01-06 - Phases 43 to 47 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 27 Aug 2026 | 27 Aug 2026Asite issue | C01 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-2324222031 - GL 22-26 - Phases 23 to 27 ComFlor 80 and Shear Stud Layout to L02 | DR - Drawing (DR) | STR | 27 Aug 2026 | 27 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-1724222031 - GL 18-22 - Phases 17 to 22 ComFlor 80 and Shear Stud Layout to L02 | DR - Drawing (DR) | STR | 27 Aug 2026 | 27 Aug 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-40004Olympus - LCY11 22032 - GL 01-06 - Phases 43 to 47 Steelwork Foundation Plan on GL H to K | DR - Drawing (DR) | STR | 27 Aug 2026 | 27 Aug 2026Asite issue | C01 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-40005Olympus - LCY11 22032 - GL 01-06 - Phases 43 to 47 Steelwork Foundation Plan on GL E to H | DR - Drawing (DR) | STR | 27 Aug 2026 | 27 Aug 2026Asite issue | C01 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-43030Olympus - LCY11 22032 - GL 01-06 - Phases 43 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 27 Aug 2026 | 27 Aug 2026Asite issue | C01 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| MEP-002Plantroom Builderwork Drawing | drawing | MEP | 27 Aug 2026 | 26 Aug 2026Asite issue | P02 | AAccepted | — | Main Contractor ReviewDesign Document Review | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-2344422031 - GL 22-26 - Phases 23 to 27 ComFlor 80 and Shear Stud Layout to L04 | DR - Drawing (DR) | STR | 27 Aug 2026 | 27 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-45030Olympus - LCY11 22032 - GL 02-06 - Phases 45 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 27 Aug 2026 | 27 Aug 2026Asite issue | C01 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-40006Olympus - LCY11 22032 - GL 01-06 - Phases 43 to 47 Steelwork Foundation Plan on GL A to E | DR - Drawing (DR) | STR | 27 Aug 2026 | 27 Aug 2026Asite issue | C01 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-2334322031 - GL 22-26 - Phases 23 to 27 ComFlor 80 and Shear Stud Layout to L03 | DR - Drawing (DR) | STR | 27 Aug 2026 | 27 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-2354522031 - GL 22-26 - Phases 23 to 27 ComFlor 80 and Shear Stud Layout to L05 | DR - Drawing (DR) | STR | 27 Aug 2026 | 27 Aug 2026Asite issue | C02 | AAccepted | 10 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-47101Olympus - LCY11 22032 - GL 01-06 - Phase 47 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 28 Aug 2026 | 28 Aug 2026Asite issue | C04 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| ARC-001Ground Floor GA Drawing | drawing | ARC | 28 Aug 2026 | 26 Aug 2026Asite issue | P03 | BAccepted with comments | — | Lead Designer ReviewDesign Document Review | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-47101Olympus - LCY11 22032 - GL 01-06 - Phase 47 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 28 Aug 2026 | 28 Aug 2026Asite issue | C04 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| FAC-003CWCT Testing Proposal | report | FAC | 29 Aug 2026 | —Awaiting issue | P01 | — | — | — | A0 · R0 · !0 |
| MEP-001Riser Coordination Drawing | drawing | MEP | 30 Aug 2026 | —Awaiting issue | P03 | — | — | — | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05161Gantry Louvres East GA Section 2 | DR - Drawing (DR) | FAC | 31 Aug 2026 | 11 Sept 2026Asite issue | P02 | BAccepted with comments | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05160Gantry Louvres East GA Section 1 | DR - Drawing (DR) | FAC | 31 Aug 2026 | 11 Sept 2026Asite issue | P02 | BAccepted with comments | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05061Gantry Louvres East GA Elevation 2 | DR - Drawing (DR) | FAC | 31 Aug 2026 | 11 Sept 2026Asite issue | P02 | BAccepted with comments | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05361Gantry Louvres East Details 2 | DR - Drawing (DR) | FAC | 31 Aug 2026 | 11 Sept 2026Asite issue | P02 | BAccepted with comments | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05360Gantry Louvres East Details 1 | DR - Drawing (DR) | FAC | 31 Aug 2026 | 11 Sept 2026Asite issue | P02 | BAccepted with comments | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05162Gantry Louvres East GA Section 3 | DR - Drawing (DR) | FAC | 31 Aug 2026 | 11 Sept 2026Asite issue | P01 | PendingAwaiting Design Review | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05060Gantry Louvres East GA Elevation 1 | DR - Drawing (DR) | FAC | 31 Aug 2026 | 11 Sept 2026Asite issue | P02 | BAccepted with comments | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-05062Gantry Louvres East GA Elevation 3 | DR - Drawing (DR) | FAC | 31 Aug 2026 | 11 Sept 2026Asite issue | P02 | BAccepted with comments | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-23101Olympus - LCY11 22031 - GL 22-26 - Phase 23 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 01 Sept 2026 | 01 Sept 2026Asite issue | C04 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-26101Olympus - LCY11 22031 - GL 22-26 - Phase 26 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 01 Sept 2026 | 01 Sept 2026Asite issue | C04 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-23101Olympus - LCY11 22031 - GL 22-26 - Phase 23 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 01 Sept 2026 | 01 Sept 2026Asite issue | C04 | BAccepted with comments | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-26101Olympus - LCY11 22031 - GL 22-26 - Phase 26 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 01 Sept 2026 | 01 Sept 2026Asite issue | C04 | AAccepted | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| FAC-005Façade Access Strategy | report | FAC | 01 Sept 2026 | —Awaiting issue | P01 | — | — | — | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99207Temporary Works – TW04-03 – MEWP/MLP on R01 Composite Floors | TW - Temporary Works (TW) | STR | 02 Sept 2026 | 02 Sept 2026Asite issue | C02 | AAccepted | 08 Sept 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00056Trade Contractor Weekly Report | RP - Report (RP) | STR | 02 Sept 2026 | 02 Sept 2026Asite issue | C01 | For InformationNo approval required | 03 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| ARC-002Door Schedule | schedule | ARC | 02 Sept 2026 | —Awaiting issue | P02 | — | — | — | A0 · R0 · !0 |
| FA-PEP-001Package Execution Plan | Unclassified | FAC | 02 Sept 2026 | 02 Sept 2026Asite issue | P01 | — | — | — | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99207Temporary Works – TW04-03 – MEWP/MLP on R01 Composite Floors | TW - Temporary Works (TW) | STR | 02 Sept 2026 | 02 Sept 2026Asite issue | C02 | AAccepted | 08 Sept 2026 | Status A (Accepted)COMPLETED | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00056Trade Contractor Weekly Report | RP - Report (RP) | STR | 02 Sept 2026 | 02 Sept 2026Asite issue | C01 | For InformationNo approval required | 03 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-44017Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Stair 4 Mid Landing Plans | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C03 | BAccepted with comments | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-27012Olympus - LCY11 22031 - Gl 22-26 - Phases 27 Temporary Steelwork Elevation on GL 25 | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C04 | For InformationNo approval required | 03 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-23522Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 CellSheild Pots @+32.940m (L05) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C04 | For InformationNo approval required | 03 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-23521Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 CellSheild Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C04 | For InformationNo approval required | 03 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-85701Olympus - LCY11 22032 - GL 02-06 - Phase 85 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | AAccepted | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-23222Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 CellSheild Pots @+13.440m (L02) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C04 | For InformationNo approval required | 03 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-85601Olympus - LCY11 22032 - GL 02-06 - Phase 85 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-44016Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Stair 4 Mid Landing Plans | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C03 | BAccepted with comments | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-45020Olympus - LCY11 22032 - GL 02-06 - Phase 45 Steel Work Stair 1 Mid Landing Plans | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C03 | BAccepted with comments | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-43501Olympus - LCY11 22032 - GL 02-06 - Phase 43 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C04 | AAccepted | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-85618Olympus - LCY11 22032 - GL 02-06 - Phases 85 Steelwork Section View Sheet 3 | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | AAccepted | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-85611Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Steelwork Elevation on GL B | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | AAccepted | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-84615Olympus - LCY11 22032 - GL 02-06 - Phases 84 Steelwork Section View | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-43501Olympus - LCY11 22032 - GL 02-06 - Phase 43 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C04 | AAccepted | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-85610Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-45401Olympus - LCY11 22032 - GL 02-06 - Phase 45 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C04 | AAccepted | 11 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-85616Olympus - LCY11 22032 - GL 02-06 - Phases 85 Steelwork Section View Sheet 1 | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | AAccepted | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-85615Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Steelwork Elevation on GL 04 (GL A to E) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-29011Olympus - LCY11 22031 - GL 22-26 - Phase 23 to 29 Steelwork Elevation on GL 26 (GL A to F) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C03 | AAccepted | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-84601Olympus - LCY11 22032 - GL 02-06 - Phase 84 Steelwork Plan @+39.440m (L06) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-84612Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Steelwork Elevation on GL K | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-85619Olympus - LCY11 22032 - GL 02-06 - Phases 85 Steelwork Stair 1 Mid Landing Plans | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | BAccepted with comments | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-84611Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Steelwork Elevation on GL J | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | AAccepted | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-85614Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Steelwork Elevation on GL 05 (GL A to E) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-84613Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Steelwork Elevation on GL 05 (GL H to K) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-85617Olympus - LCY11 22032 - GL 02-06 - Phases 85 Steelwork Section View Sheet 2 | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | BAccepted with comments | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-84701Olympus - LCY11 22032 - GL 02-06 - Phase 84 Steelwork Plan @+45.940m (R01) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | AAccepted | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-84614Olympus - LCY11 22032 - GL 02-06 - Phases 83 to 85 Steelwork Elevation on GL 04 (GL H to K) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-84616Olympus - LCY11 22032 - GL 02-06 - Phases 84 Steelwork Stair 4 Mid Landing Plans | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C02 | BAccepted with comments | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-29011Olympus - LCY11 22031 - GL 22-26 - Phase 23 to 29 Steelwork Elevation on GL 26 (GL A to F) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C03 | AAccepted | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-23121Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 CellSheild Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C05 | For InformationNo approval required | 03 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-45019Olympus - LCY11 22032 - GL 02-06 - Phase 45 Steel Work Stair 1 Mid Landing Plans | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C03 | BAccepted with comments | 03 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-23122Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 CellSheild Pots @+8.940m (L01) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C05 | For InformationNo approval required | 03 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-45401Olympus - LCY11 22032 - GL 02-06 - Phase 45 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C04 | AAccepted | 11 Sept 2026 | Design Comment,MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-23322Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 CellSheild Pots @+19.940m (L03) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C04 | For InformationNo approval required | 03 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-23421Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 CellSheild Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C04 | For InformationNo approval required | 03 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| FA-ER-001Façade ER Extract | Unclassified | FAC | 03 Sept 2026 | 03 Sept 2026Asite issue | P02 | — | — | — | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-23422Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 CellSheild Pots @+26.440m (L04) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C04 | For InformationNo approval required | 03 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-23221Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 CellSheild Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C04 | For InformationNo approval required | 03 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-23321Olympus - LCY11 22031 - GL 22-26 - Phases 23 to 29 CellSheild Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 03 Sept 2026 | 03 Sept 2026Asite issue | C04 | For InformationNo approval required | 03 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| FA-INT-001Interface Register (with ST-001) | Unclassified | FAC | 04 Sept 2026 | 04 Sept 2026Asite issue | P03 | — | — | — | A0 · R0 · !0 |
| FA-MUP-001Mock-up Test Plan | Unclassified | FAC | 05 Sept 2026 | 05 Sept 2026Asite issue | P04 | — | — | — | A0 · R0 · !0 |
| STR-002Transfer Structure Details | drawing | STR | 05 Sept 2026 | 24 Aug 2026Asite issue | P04 | AAccepted | 25 Aug 2026 | CompleteDesign Document Review | A0 · R0 · !0 |
| FA-DET-101Typical Slab Edge / Bracket Detail | Unclassified | FAC | 06 Sept 2026 | 06 Sept 2026Asite issue | P04 | — | — | — | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06050External Door Details 1 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06005External Door GA Elevation 5 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06523Area 5 - Curtain Walling Detail 4 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06503Area 5 - Curtain Walling GA Elevation 3 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06501Area 5 - Curtain Walling GA Elevation 1 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06056External Door Details 7 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06055External Door Details 6 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06502Area 5 - Curtain Walling GA Elevation 2 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06539Area 5 - Curtain Walling Detail 20 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06521Area 5 - Curtain Walling Detail 2 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06540Area 5 - Curtain Walling Detail 21 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06534Area 5 - Curtain Walling Detail 15 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-63702Olympus - LCY11 22031 - GL 22-26 - Phase 63 to 69 Cell Shield Panel @+45.940m (R01) | DR - Drawing (DR) | STR | 07 Sept 2026 | 07 Sept 2026Asite issue | C03 | For InformationNo approval required | 07 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06527Area 5 - Curtain Walling Detail 8 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06528Area 5 - Curtain Walling Detail 9 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06530Area 5 - Curtain Walling Detail 11 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06533Area 5 - Curtain Walling Detail 14 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06010External Door GA Elevation 10 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06531Area 5 - Curtain Walling Detail 12 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06537Area 5 - Curtain Walling Detail 18 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06004External Door GA Elevation 4 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06003External Door GA Elevation 3 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06525Area 5 - Curtain Walling Detail 6 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06505Area 5 - Curtain Walling GA Elevation 5 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06006External Door GA Elevation 6 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06524Area 5 - Curtain Walling Detail 5 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-63616Olympus - LCY11 22031 - GL 22-26 - Phase 63 to 69 Cell Shield Panel @+39.440m (L06) | DR - Drawing (DR) | STR | 07 Sept 2026 | 07 Sept 2026Asite issue | C03 | For InformationNo approval required | 07 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06504Area 5 - Curtain Walling GA Elevation 4 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY18-WHL-DC-RF-DR-S-12003Olympus - LCY18 22035 - GL 06 -13 - Phase 12 Steelwork Roof Level Plan at EL+8.422m | DR - Drawing (DR) | STR | 07 Sept 2026 | 07 Sept 2026Asite issue | C02 | AAccepted | 07 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06057External Door Details 8 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06535Area 5 - Curtain Walling Detail 16 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06058External Door Details 9 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06052External Door Details 3 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06051External Door Details 2 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06007External Door GA Elevation 7 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06001External Door GA Elevation 1 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06538Area 5 - Curtain Walling Detail 19 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06009External Door GA Elevation 9 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-63703Olympus - LCY11 22031 - GL 22-26 - Phase 63 to 69 Cell Shield POT @+45.940m (R01) | DR - Drawing (DR) | STR | 07 Sept 2026 | 07 Sept 2026Asite issue | C03 | For InformationNo approval required | 07 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| FA-DOC-006Unitised Panel General Arrangement | Unclassified | FAC | 07 Sept 2026 | 07 Sept 2026Asite issue | P01 | — | — | — | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06054External Door Details 5 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06532Area 5 - Curtain Walling Detail 13 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06526Area 5 - Curtain Walling Detail 7 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06529Area 5 - Curtain Walling Detail 10 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06520Area 5 - Curtain Walling Detail 1 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06059External Door Details 10 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06522Area 5 - Curtain Walling Detail 3 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06053External Door Details 4 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-63617Olympus - LCY11 22031 - GL 22-26 - Phase 63 to 69 Cell Shield POT @+39.440m (L06) | DR - Drawing (DR) | STR | 07 Sept 2026 | 07 Sept 2026Asite issue | C03 | For InformationNo approval required | 07 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06008External Door GA Elevation 8 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06002External Door GA Elevation 2 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-06536Area 5 - Curtain Walling Detail 17 | DR - Drawing (DR) | FAC | 07 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-24201Olympus - LCY11 22031 - GL 22-26 - Phase 24 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-20804Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet-02 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-23813Olympus - LCY11 22033 - GL 24-25 - Phase 23 Steelwork Girt Section | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-21052Olympus - LCY11 22033 - GL 22-24 - Phase 21 Steelwork Elevation on GL A (GL 22 to 24) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-22803Olympus - LCY11 22033 - GL 24-25 - Phase 22 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet-01 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-22050Olympus - LCY11 22033 - GL 24-25 - Phase 22 Steelwork Elevation on GL 25 (GL F to K) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-20801Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet-01 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-23201Olympus - LCY11 22031 - GL 22-26 - Phase 23 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-25201Olympus - LCY11 22031 - GL 22-26 - Phase 25 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-22807Olympus - LCY11 22033 - GL 24-25 - Phase 22 Steelwork Plan @+59.657m (R03) Sheet-01 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-20805Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Plan @+57.770m (G02-Intermediate) Sheet-01 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-23808Olympus - LCY11 22033 - GL 24-25 - Phase 23 Steelwork Plan @+59.657m (R03) Sheet-02 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-27201Olympus - LCY11 22031 - GL 22-26 - Phase 27 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-20056Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Girt Elevation on GL J (GL 22 to 24) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-20050Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Elevation on GL 23 (GL F to K) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-20055Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Elevation on GL K (GL 22 to 24) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-CA-S-28701Connection No.: 28701 | CA - Calculations (CA) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C10 | For InformationNo approval required | 08 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-24201Olympus - LCY11 22031 - GL 22-26 - Phase 24 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-20807Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Plan @Roof Level (R03) Sheet-01 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-26201Olympus - LCY11 22031 - GL 22-26 - Phase 26 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-23804Olympus - LCY11 22033 - GL 24-25 - Phase 23 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet-02 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-20802Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet-02 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-22052Olympus - LCY11 22033 - GL 24-25 - Phase 22 Steelwork Elevation on GL K (GL 24 to 25) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-23053Olympus - LCY11 22033 - GL 24-25 - Phase 23 Steelwork Girt Elevation on GL 25 (GL A to F) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-23050Olympus - LCY11 22033 - GL 24-25 - Phase 23 Steelwork Elevation on GL 25 (GL A to F) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-21807Olympus - LCY11 22033 - GL 22-24 - Phase 21 Steelwork Plan @+59.657m (R03) Sheet-01 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-23802Olympus - LCY11 22033 - GL 24-25 - Phase 23 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet-02 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-44101Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-45101Olympus - LCY11 22032 - GL 02-06 - Phase 45 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-22051Olympus - LCY11 22033 - GL 24-25 - Phase 22 Steelwork Elevation on GL J (GL 24 to 25) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-44201Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-22808Olympus - LCY11 22033 - GL 24-25 - Phase 22 Steelwork Plan @+59.657m (R03) Sheet-02 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-23807Olympus - LCY11 22033 - GL 24-25 - Phase 23 Steelwork Plan @+59.657m (R03) Sheet-01 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-20051Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Elevation on GL 24 (GL F to K) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-22811Olympus - LCY11 22033 - GL 24-25 - Phase 22 Steelwork Plan Stair 3 Mid Landing Plans | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-23811Olympus - LCY11 22033 - GL 24-25 - Phase 23 Steelwork Plan Stair 2 Mid Landing Plans | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-23803Olympus - LCY11 22033 - GL 24-25 - Phase 23 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet-01 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-21801Olympus - LCY11 22033 - GL 22-24 - Phase 21 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet-01 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-21051Olympus - LCY11 22033 - GL 22-24 - Phase 21 Steelwork Elevation on GL 24 (GL A to F) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-27101Olympus - LCY11 22031 - GL 22-26 - Phase 27 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-21808Olympus - LCY11 22033 - GL 22-24 - Phase 21 Steelwork Plan @+59.657m (R03) Sheet-02 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-20809Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Plan @+63.700m (R03-Parapet) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-20803Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet-01 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-21803Olympus - LCY11 22033 - GL 22-24 - Phase 21 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet-01 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-22812Olympus - LCY11 22033 - GL 24-25 - Phase 22 Steelwork Section | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-24401Olympus - LCY11 22031 - GL 22-26 - Phase 24 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-26401Olympus - LCY11 22031 - GL 22-26 - Phase 26 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-21050Olympus - LCY11 22033 - GL 22-24 - Phase 21 Steelwork Elevation on GL 23 (GL A to F) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-20054Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Elevation on GL J (GL 22 to 24) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-25501Olympus - LCY11 22031 - GL 22-26 - Phase 25 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-27501Olympus - LCY11 22031 - GL 22-26 - Phase 27 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-22804Olympus - LCY11 22033 - GL 24-25 - Phase 22 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet-02 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-24501Olympus - LCY11 22031 - GL 22-26 - Phase 24 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-26501Olympus - LCY11 22031 - GL 22-26 - Phase 26 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| FA-DOC-007Anchor Channel Setting Out | Unclassified | FAC | 08 Sept 2026 | 08 Sept 2026Asite issue | P01 | — | — | — | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-25301Olympus - LCY11 22031 - GL 22-26 - Phase 25 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-27301Olympus - LCY11 22031 - GL 22-26 - Phase 27 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-44301Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-24301Olympus - LCY11 22031 - GL 22-26 - Phase 24 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-20002Olympus - LCY11 22031 - GL 20-26 - Phases 20 to 29 Steelwork Foundation Plan (GL A to E) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C05 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-22802Olympus - LCY11 22033 - GL 24-25 - Phase 22 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet-02 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-26301Olympus - LCY11 22031 - GL 22-26 - Phase 26 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-45301Olympus - LCY11 22032 - GL 02-06 - Phase 45 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-44501Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-44401Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-22801Olympus - LCY11 22033 - GL 24-25 - Phase 22 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet-01 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-22053Olympus - LCY11 22033 - GL 24-25 - Phase 22 Steelwork Girt Elevation on GL 25 (GL F to K) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-21053Olympus - LCY11 22033 - GL 22-24 - Phase 21 Steelwork Elevation on GL B (GL 22 to 24) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-20001Olympus - LCY11 22031 - GL 20-26 - Phases 20 to 29 Steelwork Foundation Plan (GL H to K) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C05 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-45201Olympus - LCY11 22032 - GL 02-06 - Phase 45 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-23801Olympus - LCY11 22033 - GL 24-25 - Phase 23 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet-01 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-20806Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Plan @+57.770m (G02-Intermediate) Sheet-02 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-20053Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Elevation on GL G (GL 22 to 24) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00057Trade Contractor Weekly Report | RP - Report (RP) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | For InformationNo approval required | 08 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-45501Olympus - LCY11 22032 - GL 02-06 - Phase 45 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-45101Olympus - LCY11 22032 - GL 02-06 - Phase 45 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-25501Olympus - LCY11 22031 - GL 22-26 - Phase 25 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-27501Olympus - LCY11 22031 - GL 22-26 - Phase 27 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-23201Olympus - LCY11 22031 - GL 22-26 - Phase 23 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-25201Olympus - LCY11 22031 - GL 22-26 - Phase 25 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-26501Olympus - LCY11 22031 - GL 22-26 - Phase 26 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-24501Olympus - LCY11 22031 - GL 22-26 - Phase 24 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-44501Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-44201Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-45301Olympus - LCY11 22032 - GL 02-06 - Phase 45 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-27201Olympus - LCY11 22031 - GL 22-26 - Phase 27 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-45201Olympus - LCY11 22032 - GL 02-06 - Phase 45 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-20002Olympus - LCY11 22031 - GL 20-26 - Phases 20 to 29 Steelwork Foundation Plan (GL A to E) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C05 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-20001Olympus - LCY11 22031 - GL 20-26 - Phases 20 to 29 Steelwork Foundation Plan (GL H to K) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C05 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-45501Olympus - LCY11 22032 - GL 02-06 - Phase 45 Steelwork Plan @+32.940m (L05) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-XX-XX-RP-X-00057Trade Contractor Weekly Report | RP - Report (RP) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | For InformationNo approval required | 08 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-44401Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-27401Olympus - LCY11 22031 - GL 22-26 - Phase 27 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-25401Olympus - LCY11 22031 - GL 22-26 - Phase 25 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-44301Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-25301Olympus - LCY11 22031 - GL 22-26 - Phase 25 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-27301Olympus - LCY11 22031 - GL 22-26 - Phase 27 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-44101Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-CA-S-28702Connection No.: 28702 | CA - Calculations (CA) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C10 | For InformationNo approval required | 08 Sept 2026 | For InformationCOMPLETED | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-23052Olympus - LCY11 22033 - GL 24-25 - Phase 23 Steelwork Elevation on GL B (GL 24 to 25) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-21054Olympus - LCY11 22033 - GL 22-24 - Phase 21 Steelwork Girt Elevation on GL A (GL 22 to 24) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-21804Olympus - LCY11 22033 - GL 22-24 - Phase 21 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet-02 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-20808Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Plan @+59.657m (R03) Sheet-02 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-23812Olympus - LCY11 22033 - GL 24-25 - Phase 23 Steelwork Sections | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-DR-S-22813Olympus - LCY11 22033 - GL 24-25 - Phase 22 Steelwork Girt Section | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-26401Olympus - LCY11 22031 - GL 22-26 - Phase 26 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-24401Olympus - LCY11 22031 - GL 22-26 - Phase 24 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-27101Olympus - LCY11 22031 - GL 22-26 - Phase 27 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-24301Olympus - LCY11 22031 - GL 22-26 - Phase 24 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-21055Olympus - LCY11 22033 - GL 22-24 - Phase 21 Steelwork Girt Elevation on GL B (GL 22 to 24) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-23051Olympus - LCY11 22033 - GL 24-25 - Phase 23 Steelwork Elevation on GL A (GL 24 to 25) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-21806Olympus - LCY11 22033 - GL 22-24 - Phase 21 Steelwork Plan @+57.770m (G02-Intermediate) Sheet-02 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-21805Olympus - LCY11 22033 - GL 22-24 - Phase 21 Steelwork Plan @+57.770m (G02-Intermediate) Sheet-01 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-21802Olympus - LCY11 22033 - GL 22-24 - Phase 21 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet-02 | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-20052Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Elevation on GL F (GL 22 to 24) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-20057Olympus - LCY11 22033 - GL 22-24 - Phase 20 Steelwork Girt Elevation on GL K (GL 22 to 24) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-26301Olympus - LCY11 22031 - GL 22-26 - Phase 26 Steelwork Plan @+19.940m (L03) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-26201Olympus - LCY11 22031 - GL 22-26 - Phase 26 Steelwork Plan @+13.440m (L02) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-25401Olympus - LCY11 22031 - GL 22-26 - Phase 25 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-25030Olympus - LCY11 22031 - GL 20-26 - Phases 25 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C03 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-26030Olympus - LCY11 22031 - GL 20-26 - Phase 26 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C03 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-24030Olympus - LCY11 22031 - GL 20-26 - Phases 24 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C03 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-BF-DR-S-27030Olympus - LCY11 22031 - GL 20-26 - Phase 27 Steelwork Foundation Plan - Coupler Setting Out | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C03 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-45010Olympus - LCY11 22032 - GL 02-06 - Phase 45 To 47 Steelwork Elevation on GL A | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C03 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-45015Olympus - LCY11 22032 - GL 02-06 - Phase 45 To 47 Steelwork Elevation on GL 4 (GL A To E) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C03 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-45014Olympus - LCY11 22032 - GL 02-06 - Phase 45 To 47 Steelwork Elevation on GL 5 (GL A To E) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C03 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-45011Olympus - LCY11 22032 - GL 02-06 - Phase 45 To 47 Steelwork Elevation on GL B | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C03 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-44014Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Elevation on GL 4 (GL H To K) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C03 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-44013Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Elevation on GL 5 (GL H To K) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C03 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-44012Olympus - LCY11 22032 - GL 01-06 - Phase 44 Steelwork Elevation on GL K (GL 2 To 6) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C03 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-27401Olympus - LCY11 22031 - GL 22-26 - Phase 27 Steelwork Plan @+26.440m (L04) | DR - Drawing (DR) | STR | 08 Sept 2026 | 08 Sept 2026Asite issue | C04 | AAccepted | 08 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92001Risersafe Level R1 Grid 12-16 Plan Views Sheet 01 | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92030Risersafe Level R1 Grid 04-08 General Arrangement | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92041Risersafe Level R1 Grid 22-25 Plan Views Sheet 01 | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TS-S-00007Durbar PTV Value | TS - Technical Submittals (TS) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| FA-DOC-008Typical Mullion Detail | Unclassified | FAC | 09 Sept 2026 | 09 Sept 2026Asite issue | P01 | — | — | — | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92021Risersafe Level R1 Grid 18-12 Plan Views Sheet 01 | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| FAC-004Glass Technical Data | report | FAC | 09 Sept 2026 | 25 Aug 2026Asite issue | P02 | AAccepted | 26 Aug 2026 | CompleteDesign Document Review | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92034Risersafe Level R1 Grid 04-08 Plan Views Sheet 04 | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92040Risersafe Level R1 Grid 22-25 General Arrangement | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92032Risersafe Level R1 Grid 04-08 Plan Views Sheet 02 | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92011Risersafe Level R1 Grid 08-12 Plan Views Sheet 01 | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92002Risersafe Level R1 Grid 12-16 Plan Views Sheet 02 | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92012Risersafe Level R1 Grid 08-12 Plan Views Sheet 02 | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TS-S-00007Durbar PTV Value | TS - Technical Submittals (TS) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92031Risersafe Level R1 Grid 04-08 Plan Views Sheet 01 | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92043Risersafe Level R1 Grid 22-25 Plan Views Sheet 03 | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92000Risersafe Level R1 Grid 12-16 General Arrangement | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92020Risersafe Level R1 Grid 18-12 General Arrangement | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92042Risersafe Level R1 Grid 22-25 Plan Views Sheet 02 | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92010Risersafe Level R1 Grid 08-12 General Arrangement | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-R1-DR-S-92033Risersafe Level R1 Grid 04-08 Plan Views Sheet 03 | DR - Drawing (DR) | STR | 09 Sept 2026 | 09 Sept 2026Asite issue | C01 | PendingAwaiting Design Review | 09 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| FA-DOC-009Vision Glass Build-Up | Unclassified | FAC | 10 Sept 2026 | 10 Sept 2026Asite issue | P01 | — | — | — | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-3134322032 - GL 10-14 - Phases 31 to 36 ComFlor 80 and Shear Stud Layout to L03 | DR - Drawing (DR) | STR | 10 Sept 2026 | 10 Sept 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-03-DR-S-3734322032 - GL 06-10 - Phases 37 to 42 ComFlor 80 and Shear Stud Layout to L03 | DR - Drawing (DR) | STR | 10 Sept 2026 | 10 Sept 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-7764622032 - GL 06-10 - Phases 77 to 82 ComFlor 80 and Shear Stud Layout to L06 | DR - Drawing (DR) | STR | 10 Sept 2026 | 10 Sept 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-3124222032 - GL 10-14 - Phases 31 to 36 ComFlor 80 and Shear Stud Layout to L02 | DR - Drawing (DR) | STR | 10 Sept 2026 | 10 Sept 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-3744422032 - GL 06-10 - Phases 37 to 42 ComFlor 80 and Shear Stud Layout to L04 | DR - Drawing (DR) | STR | 10 Sept 2026 | 10 Sept 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-04-DR-S-3144422032 - GL 10-14 - Phases 31 to 36 ComFlor 80 and Shear Stud Layout to L04 | DR - Drawing (DR) | STR | 10 Sept 2026 | 10 Sept 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-06-DR-S-7164622032 - GL 10-14 - Phases 71 to 76 ComFlor 80 and Shear Stud Layout to L06 | DR - Drawing (DR) | STR | 10 Sept 2026 | 10 Sept 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-3154522032 - GL 10-14 - Phases 31 to 36 ComFlor 80 and Shear Stud Layout to L05 | DR - Drawing (DR) | STR | 10 Sept 2026 | 10 Sept 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-43101Olympus - LCY11 22032 - GL 02-06 - Phase 43 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 10 Sept 2026 | 10 Sept 2026Asite issue | C04 | AAccepted | 10 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-05-DR-S-3754522032 - GL 06-10 - Phases 37 to 42 ComFlor 80 and Shear Stud Layout to L05 | DR - Drawing (DR) | STR | 10 Sept 2026 | 10 Sept 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-40101Olympus - LCY11 22032 - GL 06-10 - Phase 40 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 10 Sept 2026 | 10 Sept 2026Asite issue | C04 | BAccepted with comments | 10 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-02-DR-S-3724222032 - GL 06-10 - Phases 37 to 42 ComFlor 80 and Shear Stud Layout to L02 | DR - Drawing (DR) | STR | 10 Sept 2026 | 10 Sept 2026Asite issue | C03 | AAccepted | 10 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-40101Olympus - LCY11 22032 - GL 06-10 - Phase 40 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 10 Sept 2026 | 10 Sept 2026Asite issue | C04 | BAccepted with comments | 10 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-01-DR-S-43101Olympus - LCY11 22032 - GL 02-06 - Phase 43 Steelwork Plan @+8.940m (L01) | DR - Drawing (DR) | STR | 10 Sept 2026 | 10 Sept 2026Asite issue | C04 | AAccepted | 10 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31051Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Elevation on GL 13 (GL F to K) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31052Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Elevation on GL F (GL 12 to 14) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-32801Olympus - LCY11 22034 - GL 12-14 - Phase 32 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet 01 | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-32803Olympus - LCY11 22034 - GL 12-14 - Phase 32 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet 01 | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-XX-TW-S-99212Temporary Works – TW04-04 – touch-up MEWP on (Typical) Composite Floors | TW - Temporary Works (TW) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C01 | Awaiting MCL Review | 11 Sept 2026 | MCL StatusRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-32802Olympus - LCY11 22034 - GL 12-14 - Phase 32 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet 02 | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31053Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Elevation on GL G (GL 12 to 14) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31055Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Elevation on GL K (GL 12 to 14) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31054Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Elevation on GL J (GL 12 to 14) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-31802Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet 02 | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31902Olympus - LCY11 22034 - GL 12-14 - Phase 31 Temporary Steelwork Brackets Plan @+48.300m (G01) & 54.380m (G02) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C01 | For InformationNo approval required | 11 Sept 2026 | Notify S2RUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-31821Olympus - LCY11 22034 - GL 10-14 - Phase 31 to 34 Steelwork Cell Sheild Panels Plan @+54.380m (G02-Upper Gantry) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C01 | For InformationNo approval required | 11 Sept 2026 | Notify S2RUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-31803Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet 01 | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-31050Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Elevation on GL 12 (GL F to K) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-32804Olympus - LCY11 22034 - GL 12-14 - Phase 32 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet 02 | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-32050Olympus - LCY11 22034 - GL 12-14 - Phase 32 Steelwork Elevation on GL 12 (GL A to F) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-31822Olympus - LCY11 22034 - GL 10-14 - Phase 31 to 34 Steelwork Cell Sheild Pots Plan @+54.380m (G02-Upper Gantry) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C01 | For InformationNo approval required | 11 Sept 2026 | Notify S2RUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-31822Olympus - LCY11 22034 - GL 10-14 - Phase 31 to 34 Steelwork Cell Sheild Pots Plan @+48.300m (G01-Lower Gantry) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C01 | For InformationNo approval required | 11 Sept 2026 | Notify S2RUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-32053Olympus - LCY11 22034 - GL 12-14 - Phase 32 Steelwork Elevation on GL B (GL 12 to 14) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| FA-DOC-010Spandrel Build-Up | Unclassified | FAC | 11 Sept 2026 | 11 Sept 2026Asite issue | P01 | — | — | — | A0 · R0 · !0 |
| LCY11-WHL-B1-R3-DR-S-31809Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Plan @+63.700m (R03-Parapet) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-32902Olympus - LCY11 22034 - GL 12-14 - Phase 32 Temporary Steelwork Brackets Plan @+48.300m (G01) & 54.380m (G02) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C01 | For InformationNo approval required | 11 Sept 2026 | Notify S2RUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-31821Olympus - LCY11 22034 - GL 10-14 - Phase 31 to 34 Steelwork Cell Sheild Panels Plan @+48.300m (G01-Lower Gantry) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C01 | For InformationNo approval required | 11 Sept 2026 | Notify S2RUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-32052Olympus - LCY11 22034 - GL 12-14 - Phase 32 Steelwork Elevation on GL A (GL 12 to 14) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-ZZ-DR-S-32051Olympus - LCY11 22034 - GL 12-14 - Phase 32 Steelwork Elevation on GL 13 (GL A to F) | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G1-DR-S-31801Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Plan @+48.300m (G01-Lower Gantry) Sheet 01 | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| LCY11-WHL-B1-G2-DR-S-31804Olympus - LCY11 22034 - GL 12-14 - Phase 31 Steelwork Plan @+54.380m (G02-Upper Gantry) Sheet 02 | DR - Drawing (DR) | STR | 11 Sept 2026 | 11 Sept 2026Asite issue | C02 | AAccepted | 11 Sept 2026 | Design Comment,Design Lead Status ChangeRUNNING | A0 · R0 · !0 |
| FA-DOC-011Façade Design Deliverable 11 | Unclassified | FAC | 12 Sept 2026 | 12 Sept 2026Asite issue | P01 | — | — | — | A0 · R0 · !0 |
| FA-DOC-012Façade Design Deliverable 12 | Unclassified | FAC | 13 Sept 2026 | 13 Sept 2026Asite issue | P01 | — | — | — | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01679Area 6 - Grids B-E BrickClad Backing Grid Lower Building GA East Elevation | DR - Drawing (DR) | FAC | 14 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01683Area 6 - Grids E-H Feature Panel Lower Building GA East Elevation | DR - Drawing (DR) | FAC | 14 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01687Area 6 - Grids H-J BrickClad Lower Building GA East Elevation | DR - Drawing (DR) | FAC | 14 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01681Area 6 - Grids H-J BrickClad Backing Grid Lower Building GA East Elevation | DR - Drawing (DR) | FAC | 14 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01677Area 6 - Grids E-H Feature Panel Backing Grid Lower Building GA East Elev. | DR - Drawing (DR) | FAC | 14 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| FA-DOC-013Façade Design Deliverable 13 | Unclassified | FAC | 14 Sept 2026 | 14 Sept 2026Asite issue | P01 | — | — | — | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01680Area 6 - Grids E-H BrickClad Backing Grid Lower Building GA East Elevation | DR - Drawing (DR) | FAC | 14 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01684Area 6 - Grids H-J Feature Panel Lower Building GA East Elevation | DR - Drawing (DR) | FAC | 14 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01685Area 6 - Grids B-E BrickClad Lower Building GA East Elevation | DR - Drawing (DR) | FAC | 14 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01676Area 6 - Grids B-E Feature Panel Backing Grid Lower Building GA East Elev. | DR - Drawing (DR) | FAC | 14 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01686Area 6 - Grids E-H BrickClad Lower Building GA East Elevation | DR - Drawing (DR) | FAC | 14 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01682Area 6 - Grids B-E Feature Panel Lower Building GA East Elevation | DR - Drawing (DR) | FAC | 14 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01678Area 6 - Grids H-J Feature Panel Backing Grid Lower Building GA East Elev. | DR - Drawing (DR) | FAC | 14 Sept 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| FA-DOC-014Façade Design Deliverable 14 | Unclassified | FAC | 15 Sept 2026 | 15 Sept 2026Asite issue | P01 | — | — | — | A0 · R0 · !0 |
| FA-DOC-015Façade Design Deliverable 15 | Unclassified | FAC | 16 Sept 2026 | 16 Sept 2026Asite issue | P01 | — | — | — | A0 · R0 · !0 |
| FA-DOC-016Façade Design Deliverable 16 | Unclassified | FAC | 17 Sept 2026 | 17 Sept 2026Asite issue | P01 | — | — | — | A0 · R0 · !0 |
| FA-DOC-018Façade Design Deliverable 18 | Unclassified | FAC | 18 Sept 2026 | —Awaiting issue | P01 | — | — | — | A0 · R0 · !0 |
| FA-DOC-017Façade Design Deliverable 17 | Unclassified | FAC | 18 Sept 2026 | 18 Sept 2026Asite issue | P01 | — | — | — | A0 · R0 · !0 |
| FA-DOC-019Façade Design Deliverable 19 | Unclassified | FAC | 18 Sept 2026 | —Awaiting issue | P01 | — | — | — | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-01023K-ROC GA Elevation 4 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-01041Feature Panel GA Elevation 1 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-01063BrickClad GA Elevation 4 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03015Water & Waste Building Details 16 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03009Water & Waste Building Details 10 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03003Water & Waste Building Details 4 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-01061BrickClad GA Elevation 2 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03019Water & Waste Building Details 20 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03005Water & Waste Building Details 6 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03007Water & Waste Building Details 8 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| FA-DOC-020Façade Design Deliverable 20 | Unclassified | FAC | 01 Oct 2026 | —Awaiting issue | P01 | — | — | — | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03011Water & Waste Building Details 12 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03001Water & Waste Building Details 2 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03017Water & Waste Building Details 18 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-01062BrickClad GA Elevation 3 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-01043Feature Panel GA Elevation 1 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-01021K-ROC GA Elevation 2 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03014Water & Waste Building Details 15 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-01002Tolerance Channel GA Elevation 3 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03008Water & Waste Building Details 9 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03002Water & Waste Building Details 3 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-01060BrickClad GA Elevation 1 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-01022K-ROC GA Elevation 3 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-01000Tolerance Channel GA Elevation 1 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03004Water & Waste Building Details 5 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03018Water & Waste Building Details 19 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03012Water & Waste Building Details 13 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-01040Feature Panel GA Elevation 1 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03006Water & Waste Building Details 7 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03000Water & Waste Building Details 1 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03016Water & Waste Building Details 17 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03010Water & Waste Building Details 11 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-01042Feature Panel GA Elevation 1 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-03013Water & Waste Building Details 14 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-01001Tolerance Channel GA Elevation 2 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-01020K-ROC GA Elevation 1 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-01003Tolerance Channel GA Elevation 4 | DR - Drawing (DR) | FAC | 01 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| FA-DOC-021Façade Design Deliverable 21 | Unclassified | FAC | 02 Oct 2026 | —Awaiting issue | P01 | — | — | — | A0 · R0 · !0 |
| FA-DOC-022Façade Design Deliverable 22 | Unclassified | FAC | 03 Oct 2026 | —Awaiting issue | P01 | — | — | — | A0 · R0 · !0 |
| FA-DOC-023Façade Design Deliverable 23 | Unclassified | FAC | 04 Oct 2026 | —Awaiting issue | P01 | — | — | — | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01880Stair 04 North West - BrickClad GA Elevation 1 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01881Stair 04 North West - BrickClad GA Elevation 2 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01875Stair 04 North West - Digital Line GA Elevation 1 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01811Stair 03 North East - K-ROC GA Elevation 2 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01825Stair 03 North East - Digital Line GA Elevation 1 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01835Stair 03 North East - Built-Up GA Elevation 1 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01820Stair 03 North East - BrickClad Backing Grid GA Elevation 1 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01810Stair 03 North East - K-ROC GA Elevation 1 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01885Stair 04 North West - Built-Up GA Elevation 1 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01821Stair 03 North East - BrickClad Backing Grid GA Elevation 2 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01836Stair 03 North East - Built-Up GA Elevation 2 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01876Stair 04 North West - Digital Line GA Elevation 2 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| FA-DOC-024Façade Design Deliverable 24 | Unclassified | FAC | 05 Oct 2026 | —Awaiting issue | P01 | — | — | — | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01871Stair 04 North West - BrickClad Backing Grid GA Elevation 2 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01886Stair 04 North West - Built-Up GA Elevation 2 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01831Stair 03 North East - BrickClad GA Elevation 2 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01816Stair 03 North East - Digital Line Backing Grid GA Elevation 2 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01826Stair 03 North East - Digital Line GA Elevation 2 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01815Stair 03 North East - Digital Line Backing Grid GA Elevation 1 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01830Stair 03 North East - BrickClad GA Elevation 1 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01870Stair 04 North West - BrickClad Backing Grid GA Elevation 1 | DR - Drawing (DR) | FAC | 05 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| FA-DOC-025Façade Design Deliverable 25 | Unclassified | FAC | 06 Oct 2026 | —Awaiting issue | P01 | — | — | — | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-04001Water & Waste Building Specification Drawings | DR - Drawing (DR) | FAC | 29 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-04002Water & Waste Building Specification Drawings | DR - Drawing (DR) | FAC | 29 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY14-FKG-WS-XX-DR-X-04000Water & Waste Building K-ROC Specification Drawings | DR - Drawing (DR) | FAC | 29 Oct 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01751Stair 02 South East - Tolerance Channel GA Elevation 1 | DR - Drawing (DR) | FAC | 02 Nov 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01752Stair 02 South East - Tolerance Channel GA Elevation 2 | DR - Drawing (DR) | FAC | 02 Nov 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01701Stair 01 South West - Tolerance Channel GA Elevation 1 | DR - Drawing (DR) | FAC | 02 Nov 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01702Stair 01 South West - Tolerance Channel GA Elevation 2 | DR - Drawing (DR) | FAC | 02 Nov 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01802Stair 03 North East - Tolerance Channel GA Elevation 2 | DR - Drawing (DR) | FAC | 14 Dec 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01801Stair 03 North East - Tolerance Channel GA Elevation 1 | DR - Drawing (DR) | FAC | 14 Dec 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01851Stair 04 North West - Tolerance Channel GA Elevation 1 | DR - Drawing (DR) | FAC | 14 Dec 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |
| LCY11-FKG-B1-XX-DR-X-01852Stair 04 North West - Tolerance Channel GA Elevation 2 | DR - Drawing (DR) | FAC | 14 Dec 2026Planned placeholder | —Not issued | P01 | PrepublishedNot issued | 21 May 2026 | ------ | A0 · R0 · !0 |